Vacker v. Yeager

151 Ill. App. 144, 1909 Ill. App. LEXIS 689
CourtAppellate Court of Illinois
DecidedOctober 25, 1909
StatusPublished
Cited by9 cases

This text of 151 Ill. App. 144 (Vacker v. Yeager) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Vacker v. Yeager, 151 Ill. App. 144, 1909 Ill. App. LEXIS 689 (Ill. Ct. App. 1909).

Opinion

Mr. Presiding Justice Baume

delivered the opinion of the court.

The plaintiff, Charles Vacker, recovered a verdict and judgment in the Circuit Court of Vermilion county against the defendants, M. Yeager and O. P. Yeager, partners doing business as M. Yeager & Son, for the sum of $7000' as damages for personal injuries. The declaration contains two counts. The first count alleges that the defendants on June 25,1907, had the contract for the erection and construction of a seven-story building in the city of Danville; that Joseph A. Dondono and John Gerance, employed under the name of Dondono i& Gerance, were the foremen for the defendants to superintend and direct the erection and construction of the steel work upon said building; that one Charles Bushong was the general foreman of defendants in the construction of said building; that plaintiff was a structural iron worker employed as such by the defendants, and that plaintiff and all other structural iron workers of defendants, and said Dondono and Gerance, as foremen, were under the personal control, direction and supervision of said general foreman, Charles Bushong, and were then and there in pursuance of said employment working upon a scaffold located three feet below the fourth floor of said structure, where they were engaged in riveting under the general direction and with the knowledge of defendants’ general foreman; that the steel work of said building had been erected to the sixth story and certain employes of the defendants were then and there working upon said sixth story erecting the beams of the seventh story; that defendants negligently failed to use reasonable care to protect plaintiff’s working place from falling tools and material dropping from the sixth floor and negligently failed to properly cover the floor of that part of the sixth floor above the place where plaintiff was at work, but negligently used a certain temporary floor constructed of planks which were too short to reach from one side of the structure to the other, whereby open spaces were left eight feet in length and six inches in width, of which defendants had knowledge and the plaintiff had no knowledge nor could by the exercise of reasonable care have had knowledge; that while the plaintiff was in the pursuance of his said employment and exercising due care for his own safety a wooden roller which was being used by the employes of the defendants upon the sixth floor was inadvertently pushed toward one of said open spaces and fell upon the head of plaintiff. The second count contains the additional allegation that the unsafe condition of the said floor upon the sixth story of the building had existed for five days prior to the injury complained of. To this declaration the defendants pleaded the general issue and also a special plea averring that the plaintiff was not an employe of the defendants and was not performing any duty or work for them, and that the defendants did not owe to the plaintiff the duties alleged in the declaration, but that plaintiff was at the time mentioned and prior thereto an employe of Joseph A. Dondono and John Geranee, partners doing business as Dondono & Geranee, independent contractors, and was working for them in the erection of the steel work of said building; that the temporary flooring mentioned in the declaration was laid and constructed by said Dondono & Geranee, as such independent contractors and not by the defendants, and that the employes engaged in moving said wooden roller upon the sixth floor, as well as the plaintiff, were all employes of Dondono & Geranee, and were performing such work for and acting under the directions of said Dondono & Geranee, and not of the defendants.

On November 23, 1906, W. F. Baum & Son, as owners, entered into a written contract with the defendants, M. Yeager & Son, for the construction by the latter of a seven-story steel building in compliance with the architects’ plans and specifications for the sum of $116,198.20 including the cost of labor and material, and the sum of $7500 as compensation for their services. The contract provided that the contractors might sublet any portion of the work, and on January 28,1907, said contractors entered into a written agreement with Joseph A. Dondono and John Gerance, designated as a copartnership' and as subcontractors, whereby, as such subcontractors, said Dondono & Gerance agreed to erect all the necessary steel work for the building in accordance with the architects’ plans and specifications and under the direction of the contractors or their authorized foremen, for the sum of $7.50 per ton for all steel erected. As to the manner of payment to said subcontractors the contract provided that the contractors should pay for all labor necessary in the erection of said steel according to pay rolls as submitted by the subcontractors, said pay rolls to be made up and paid every two weeks according to time books kept by the superintendent for the contractors, and that the subcontractors Dondono & Gerance, should each be allowed $30 per week; that after all the steel work had been set and completed to the satisfaction of the contractors and architects, the actual weight of the steel should be determined and the amount, if any, then remaining due to the subcontractors should be paid to them within thirty days thereafter. Said subcontract further provided, that in the erection of the work the contractors were to furnish all the necessary equipment to do the work, with the exception of the small hand tools, which were to be furnished by the subcontractors.

On June 25, 1907, while the plaintiff was engaged in his employment as a structural iron worker on the fourth story of the building, a wooden roller which was being used by certain other structural iron workers on the sixth story of the building fell through an opening in the temporary platform or floor constructed of planks on said sixth story and struck the plaintiff on the head causing the injuries complained of. It is uncontroverted that the plaintiff together with all of the other structural iron workers employed on the building were hired by Dondono & Gerance and that the general method of installing the equipment necessary to the erection of the structural iron work was directed and controlled by said Dondono & Gerance; that the necessary equipment for the proper performance of the work, including planks to be used as temporary floors on the several stories of the building as the work progressed, was furnished by the defendants, M. Yeager & Son; that at the time plaintiff was injured there was a sufficient supply of planks furnished by the defendants and1 accessible to Dondono & Gerance for use in constructing a close temporary floor on the sixth story of the building. The evidence tends to show that there was a difference of opinion' between Gerance and Dondono as to the manner in which such temporary floor should be constructed, Dondono insisting that such floor should be put in tight while Gerance considered the method adopted as sufficient for the purpose.

If the written contract which was entered into between the defendants and Dondono & Gerance is controlling and conclusive as to the relation of the parties it must be held that Dondono & Gerance were thereby created independent contractors to construct and erect the structural iron work. The contract in question in so far as it provides that the work shall be done under the direction of the defendants or their authorized foremen and to the acceptance of the architects or their authorized representative, is not unlike the contract involved in Pioneer Construction Co. v. Hansen, 176 Ill.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Vendo Co. v. Stoner
438 N.E.2d 933 (Appellate Court of Illinois, 1982)
Martino v. Barra
293 N.E.2d 745 (Appellate Court of Illinois, 1973)
Seyferlich v. Maxwell
171 N.E.2d 806 (Appellate Court of Illinois, 1961)
Pagano v. Leisner
125 N.E.2d 301 (Appellate Court of Illinois, 1955)
Van Drake v. Thomas
38 N.E.2d 878 (Indiana Court of Appeals, 1942)
Hartley v. Red Ball Transit Co.
259 Ill. App. 229 (Appellate Court of Illinois, 1930)
Schramko v. Boston Store
243 Ill. App. 251 (Appellate Court of Illinois, 1927)
Devine v. Rosenbaum Bros.
192 Ill. App. 30 (Appellate Court of Illinois, 1915)
Stanley v. Aurora, Elgin & Chicago Railroad
166 Ill. App. 132 (Appellate Court of Illinois, 1911)

Cite This Page — Counsel Stack

Bluebook (online)
151 Ill. App. 144, 1909 Ill. App. LEXIS 689, Counsel Stack Legal Research, https://law.counselstack.com/opinion/vacker-v-yeager-illappct-1909.