U.W. Marx, Inc. v. Mountbatten Surety Co.

3 A.D.3d 688, 770 N.Y.S.2d 777, 2004 N.Y. App. Div. LEXIS 342
CourtAppellate Division of the Supreme Court of the State of New York
DecidedJanuary 15, 2004
StatusPublished
Cited by5 cases

This text of 3 A.D.3d 688 (U.W. Marx, Inc. v. Mountbatten Surety Co.) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
U.W. Marx, Inc. v. Mountbatten Surety Co., 3 A.D.3d 688, 770 N.Y.S.2d 777, 2004 N.Y. App. Div. LEXIS 342 (N.Y. Ct. App. 2004).

Opinion

Lahtinen, J.

(1) Cross appeals from that part of an order of the Supreme Court (Ceresia, Jr., J.), entered July 23, 2002 in Rensselaer County, which partially granted plaintiffs motion for summary judgment on the issue of damages and partially denied defendant’s motion for summary judgment, (2) appeal from the judgment entered thereon, (3) appeal from an order of said court, entered October 23, 2002 in Rensselaer County, which, upon reargument, adhered to its prior decision, (4) appeal from an order of the Supreme Court (Hummel J.), entered January 6, 2003 in Rensselaer County, upon a decision of the [689]*689court in favor of plaintiff on the issue of damages, and (5) appeal from the judgment entered thereon.

Plaintiff sued defendant for allegedly breaching its obligation under a performance bond. We previously upheld an order granting plaintiff partial summary judgment on the issue of liability and denying defendant’s motion to amend its answer (290 AD2d 621 [2002]). In these appeals from various orders and judgments awarding damages, defendant urges that the damages awarded by Supreme Court were excessive and plaintiff counters that they were inadequate.

Plaintiff and Kleen Resources, Inc. formed a joint venture in 1996 to bid on a multimillion dollar contract with the Office of General Services (hereinafter OGS). Their bid was accepted and, under the joint venture terms, plaintiff agreed to procure the bonding required by OGS for the project and Kleen promised to complete all the work. As part of their agreement, plaintiff required Kleen to provide a performance bond, which it obtained from defendant. Defendant’s bond, in the sum of $1,356,000, named Kleen as the contractor and the joint venture as the obligee. With respect to compensation under the terms of the joint venture agreement, plaintiff was to receive 8% of all contract payments made by OGS, and Kleen was to receive all funds left after paying suppliers, subcontractors, its payroll and the 8% to plaintiff.

Plaintiff obtained the bonding required by OGS, thus satisfying its obligation under the joint venture agreement. Moreover, for the first couple of years as payments were made under the OGS contract, plaintiff received 8% from the joint venture for a total of $646,130. In 1998, however, plaintiff discovered that Kleen could not account for $658,759 that had been received under the OGS contract. Kleen then defaulted on its promise to perform all the work on the OGS project and assigned its rights in the joint venture to plaintiff.

Plaintiff demanded that defendant honor the performance bond. Defendant refused, resulting in plaintiff undertaking to complete the OGS contract for the joint venture. At the time Kleen defaulted, subcontractors were reportedly owed $272,097 by the joint venture. Plaintiff assumed responsibility for those claims and, additionally, allegedly expended substantially more to complete the OGS contract than it received in remaining payments from OGS. Plaintiff brought this action against defendant and successfully moved for summary judgment on the issue of liability.

The parties stipulated that the damages could be decided by Supreme Court on submitted papers. Defendant argued that [690]*690plaintiff was not entitled to any damages and plaintiff sought damages as follows:

Labor, materials, additional
bonding and insurance to
complete the OGS contract $2,016,755.44
Overhead at 10% of prior
number + 201,675.54
Subtotal I $2,218,430.98
Profit at 10% of subtotal I + 221,843.10
Subtotal II $ 2,440,274.08
Minus payments by OGS to plaintiff ($1,844,786.75)
Subtotal III $ 595,487.33
8% fee under joint
venture agreement + 212,767.19
Subcontractor’s claims at time
Kleen defaulted + 272,097.43
Subtotal IV $ 1,080,351.95
Statutory interest of $49,090.21
on the 8% fee and of $186,686.40
on the OGS payment shortfall + 235,776.611
Total alleged damages $ 1,316,128.56

Supreme Court (Ceresia, Jr., J.), found a factual issue requiring a trial as to the claim for overhead costs (i.e., $201,675.54), did not allow the claim for profit (i.e., $221,843.10), and did not allow the amount for the subcontractors’ claims at the time Kleen defaulted (i.e., $272,097.43). The court otherwise accepted plaintiffs damages and, thus, granted judgment in the amount of $620,512.49, plus postdecision interest of $20,809.2 After granting reargument to plaintiff regarding dismissal of the amounts owed subcontractors, Supreme Court adhered to its decision regarding such issue. Following a trial on the issue of additional overhead expenses incurred by plaintiff, Supreme Court (Hummel, J.) awarded plaintiff a further judgment of [691]*691$165,414, plus statutory interest of $67,792.98. These appeals ensued.

The purpose of a performance bond is to insure that a contract will be completed consistent with its terms (see Matter of Cataract Disposal v Town Bd. of Town of Newfane, 53 NY2d 266, 271 [1981]). “[A] surety bond attaches to the principal contract and must be construed in conjunction with it” (Carrols Equities Corp. v Villnave, 57 AD2d 1044, 1045 [1977], lv denied 42 NY2d 810 [1977]). In the event of a contractor’s default, the surety’s obligation is to either complete the work or to pay the obligee the amount necessary for it to have the contract completed (see United States v Seaboard Sur. Co., 817 F2d 956, 959 [1987], cert denied 484 US 855 [1987]). Liability of the surety is generally limited to the amount of the bond and as provided in the contract (see Tri-City Elec. Co. v People, 63 NY2d 969, 971 [1984]; Mendel-Mesick-Cohen-Architects v Peerless Ins. Co., 74 AD2d 712, 712-713 [1980]). Where, as here, the surety fails to perform after the contractor defaults, the surety’s liability may include the cost of completion, as well as damages flowing from its breach (see Hunt v Bankers & Shippers Ins. Co., 73 AD2d 797 [1979], affd 50 NY2d 938 [1980]; 4 NY Prac, Commercial Litigation in New York Courts § 65.7; 11 NY Jur 2d, Bonds § 119).

Defendant argues that plaintiff was not entitled to any damages because the joint venture (i.e., the obligee) allegedly impaired defendant’s collateral security. Defendant asserts such impairment in the failure to account for $658,759 in payments received from OGS (i.e., the amount for which Kleen could not account) and by making payments to plaintiff of $646,130 (i.e., the 8% fee prior to Kleen’s default). However, this argument was not preserved for review by the record. Defendant has attempted to address its omission by providing this Court with copies of memoranda of law it submitted to Supreme Court. Those memoranda speak primarily to an alleged diversion of trust funds under Lien Law article 3-A, which is an argument that defendant previously attempted to interject via an amended answer.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

SCE Envtl. Group, Inc. v. Murnane Bldg. Contrs., Inc.
2025 NY Slip Op 05997 (Appellate Division of the Supreme Court of New York, 2025)
WBP Central Associates, LLC v. DeCola
91 A.D.3d 861 (Appellate Division of the Supreme Court of New York, 2012)
Travelers Casualty & Surety Co. v. Dormitory Authority-State
735 F. Supp. 2d 42 (S.D. New York, 2010)
Vil. of Hempstead Community Dev. Agency v. Colonia Ins. Co. of N.Y.
2004 NY Slip Op 50237(U) (New York Supreme Court, Nassau County, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
3 A.D.3d 688, 770 N.Y.S.2d 777, 2004 N.Y. App. Div. LEXIS 342, Counsel Stack Legal Research, https://law.counselstack.com/opinion/uw-marx-inc-v-mountbatten-surety-co-nyappdiv-2004.