Uvalde Asphalt Paving Co. v. City of New York

196 A.D. 740, 188 N.Y.S. 304, 1921 N.Y. App. Div. LEXIS 5603
CourtAppellate Division of the Supreme Court of the State of New York
DecidedMay 13, 1921
StatusPublished
Cited by8 cases

This text of 196 A.D. 740 (Uvalde Asphalt Paving Co. v. City of New York) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Uvalde Asphalt Paving Co. v. City of New York, 196 A.D. 740, 188 N.Y.S. 304, 1921 N.Y. App. Div. LEXIS 5603 (N.Y. Ct. App. 1921).

Opinion

Greenbaum, J.:

This action arises out' of a contract made between the parties on September 11, 1902, for the construction of the Grand Concourse from One Hundred and Sixty-first street to Mosholu Parkway in the borough of The Bronx. The complaint sets forth two causes of action: the first for moneys alleged to have been earned under the contract, and the second for damages for the defendant’s alleged breach of the contract.

The trial court directed a verdict for the plaintiff as prayed for in the first cause of action for the full amount thereof with interest, making a total of $42,484.43.

So far as the appeal relates to that part of the judgment which resulted in a direction of a verdict by the court upon the first cause of action for $28,364.90 with interest, making a total of $42,484.43, we are of opinion that the court was justified in so directing the jury.

In respect of the second cause of action, however, an entirely different situation exists. The record of the trial is an exceedingly voluminous one.

The second cause of action is predicated upon various alleged breaches of the contract during its performance, on the part of the defendant, in that it “ failed and neglected to prepare and furnish necessary detailed plans to plaintiff as required by said contract and furnished erroneous and faulty plans; refused to permit plaintiff to make suitable foundations for the viaduct; * * * and failed and neglected to give proper stakes and grades for said work; and failed to procure and give to plaintiff at the proper time permits to do certain portions of said contract work; failed and neglected promptly to procure as required easements necessary for the proper per[743]*743formance of said contract; interfered with the plaintiff’s work by the performance of work independent of said contract by its own subordinates and through independent contractors; arbitrarily revised and changed the plans and portions of said work; refused to permit plaintiff to perform the work in the manner contemplated by the contract; refused and neglected to give plaintiff possession of the site of the whole work; constructed, and permitted the construction of, various numerous sewers and water mains throughout and on the site of the work, and permitted the said work to be delayed and failed to complete it or to require it to be completed within the contract periods or within a reasonable time thereafter; required plaintiff to do work not called for by its contract but covered by said contracts of independent contractors; required plaintiff to do again work which had theretofore been duly and properly performed by it; refused and neglected to remove obstructions from the site of the work which it was defendant’s duty to remove or to require to be removed; constructed transverse roads and viaducts across and under the site of plaintiff’s work, thereby obstructing it and cutting it into separate sections and preventing plaintiff from proceeding with said work as a unit, and from transporting and depositing available excavated material from one portion of the work to another; and damaged and destroyed work performed by plaintiff, necessitating the doing of said work again.”

It was alleged that by reason of the foregoing acts of commission and omission on the part of defendant, the work of completing the contract was made more expensive by the sum of $464,416.29, for, which sum as damages judgment was demanded by the plaintiff. By its bill of particulars the plaintiff limited its claim to the sum of $376,376.93, for which amount the jury found a verdict in favor of the plaintiff. The defendant’s answer, after general denials, set up, (1) payment; (2) that the plaintiff exceeded by 129% days the contract allowance of 1,000 working days within which to complete the contract, for which excess the defendant would be entitled to liquidated damages amounting to $6,475; (3) that the contract authorized the letting of other contracts, and that any delays that were caused by the letting of said contracts were provided for by the contract and were within the contemplation of the [744]*744parties; (4) that the contract authorized the suspension of the work in the interest of the city and that the work was suspended; (5) that plaintiff released the defendant from all claims, and (6) as a counterclaim, that plaintiff failed to make repairs to the work called for under the contract amounting to $43,110. The contract is not for a gross sum. It is what is known as a unit price job, that is, to be paid for at specified unit rates for the different kinds of materials furnished and of work performed.

The contract was awarded the plaintiff as the lowest public bidder. The proposals for estimates contained inter alia the following provisions: Grading of the Grand Boulevard and Concourse, from East One Hundred and Sixty-first Street to Mosholu Parkway and constructing temporary roadways, sidewalks and paths. * * * The time allowed for the completion of the whole work will be 1,000 consecutive working days. The time so allowed refers to consecutive working days and not to the aggregate time of such inspectors as may be appointed on the work. * * * Bidders must satisfy themselves by personal examination of the location of .the proposed work and by such other means as they may prefer, as to the accuracy of the foregoing engineer’s estimate. Bidders must also determine for themselves the probable amount of sinkage, shrinkage or settlement, and allow therefor, and shall not, at any time after the submission of a proposal, dispute or complain of such statement or estimate, nor assert that there was any misunderstanding in regard to the depth or character of the excavation and filling to be made or the nature or amount of the work to be done. * * * Bidders are specially notified that the President of the Borough reserves the right to determine the times and places for commencing and prosecuting the work, and that postponement or delay on the whole, or any part thereof, occasioned by the precedence of the other contracts, which may be either let or executed before or after the execution of the contract for this work, cannot constitute a claim for damages, nor for a reduction of the damages fixed for delay in completing the work beyond the time allowed.”

The agreement signed by the respective parties defines the word engineer ” whenever used in the specifications or in the contract as the engineer designated by the President to [745]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Berley Industries, Inc. v. City of New York
385 N.E.2d 281 (New York Court of Appeals, 1978)
Kec Corp. v. Fulton-Montgomery Community College
44 A.D.2d 737 (Appellate Division of the Supreme Court of New York, 1974)
Shore Bridge Corp. v. State
186 Misc. 1005 (New York State Court of Claims, 1946)
American Bridge Co. v. State
245 A.D. 535 (Appellate Division of the Supreme Court of New York, 1935)
Odell v. City of New York
206 A.D. 68 (Appellate Division of the Supreme Court of New York, 1923)
Feeney & Sheehan Building Co. v. State
120 Misc. 240 (New York State Court of Claims, 1923)
Degnon Contracting Co. v. City of New York
202 A.D. 390 (Appellate Division of the Supreme Court of New York, 1922)

Cite This Page — Counsel Stack

Bluebook (online)
196 A.D. 740, 188 N.Y.S. 304, 1921 N.Y. App. Div. LEXIS 5603, Counsel Stack Legal Research, https://law.counselstack.com/opinion/uvalde-asphalt-paving-co-v-city-of-new-york-nyappdiv-1921.