Thilemann v. City of New York

81 N.Y.S. 773
CourtAppellate Division of the Supreme Court of the State of New York
DecidedApril 17, 1903
StatusPublished
Cited by3 cases

This text of 81 N.Y.S. 773 (Thilemann v. City of New York) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Thilemann v. City of New York, 81 N.Y.S. 773 (N.Y. Ct. App. 1903).

Opinions

O’BRIEN, J.

The plaintiff seeks to recover upon five separate ■causes of action based upon claims which arose in the course of his performance of a contract entered into with the city of New York whereby he agreed to construct a sewer in East 187th street and in ■adjoining streets and avenues. For the work performed a certificate was given to the plaintiff amounting in the aggregate to the sum of $66,533.14, of which he was paid $63,372.67, the sum of $2,611.47 being retained as repairing security, and the sum of $549 being deducted by the city as damages for overtime. The plaintiff’s first cause of action is to recover this sum of $549, he claiming that it was wrongfully deducted, and that the defendant had unlawfully delayed him. The contract provided that the work should be completed within 350 days, ex■clusive of Sundays and holidays and days excepted by the contract, unless more time was required for certain additional work, when it was to be extended proportionally; that the time was to be compared with the aggregate time of inspectors, and not construed as consecutive days; and that the city might deduct as liquidated damages for the noncompletion of the work the sum due for “inspector's wages [775]*775(four dollars a day) for each and every day the aggregate time of all the inspectors * * * may exceed the time stipulated.” There was no provision in the contract for an allowance of time for delays occasioned by the act, omission, or fault of the defendant, nor that a certificate of such delays be given, but for unnecessary delay and nonperformance by the plaintiff the city was given the right to abrogate the contract.

The defendant’s evidence, in the form of certificates and letters and testimony of those connected with the work, shows that the inspector’s time was 978)4 days; that 139)4 days were allowed for unsuitable weather, and that 352 days were allowed for delays occasioned by the city; leaving as overtime, above the 350 days stipulated in the contract, 137)4 days to be charged the contractor, which, at $4 a day, amounted to $549, the sum deducted. The evidence offered by the plaintiff was directed to showing that 510 instead of 352 days should be allowed for the delays occasioned and recognized by the city; and, moreover, that in addition the city was responsible for loss of time in the execution of the contract after the work was awarded, owing to questions which had arisen regarding the debt limit and other matters. It was further claimed by the plaintiff upon the trial that the computation made by the defendant and the view taken by the court were erroneous in confusing “inspector’s days” and calendar days. The main insistence of the plaintiff, however, was that the first cause of action should not be submitted to the jury, but that the court should direct a verdict in his favor, and to the refusal of the court so to do an exception was taken. This exception is urged on our attention upon this appeal, and it is contended that, the prosecution of the work having concededly been hindered and delayed by the defendant’s fault, this abrogated the time limit of 350 days prescribed in the contract, and no deduction should be made by the city, the plaintiff having performed the work within a reasonable time.

If this first cause of action was one properly submitted to the jury, then, upon the evidence adduced, their verdict in defendant’s favor should not be disturbed. We think, however, that the plaintiff’s contention that the conceded delays occasioned by the city abrogated the provision of the contract with respect to damages for overtime, and thereafter the contractor might complete within reasonable time, is correct. No provision of the contract permitted an allowance for delays by the city, and in the absence of such a provision it is inconsistent to hold the plaintiff for overtime in performing, and, on the other hand, compel him to allow delay on the part of the city. Dady v. Mayor, 57 Hun, 456, 10 N. Y. Supp. 819; Weeks v. Little, 89 N. Y. 566; Phelan v. Mayor, 119 N. Y. 86, 23 N. E. 175. In Dady v. Mayor, supra, it was said: “When the city caused any substantial delay in the work, it lost the right to charge the contractor with the stipulated liquidated damages for overtime, and could only insist that the time of completion should be reasonable." Here the city did not claim nor attempt to establish that there was any unreasonable delay by the contractor, but it stood upon its rights given by that provision of the contract which prescribed the time limit and damages. We think, therefore, that the city was not justified in deducting the sum [776]*776mentioned or any sum as damages for overtime, and that for the amount retained as such damages a verdict should have been directed in plaintiff’s favor. It is unnecessary to discuss the subject of the proper manner of computing the-overtime, in view of the conclusion at which we have thus arrived with respect to the first cause of action.

The second cause of action is to recover $1,836 for increased cost occasioned by the defendant permitting other contractors to place filling upon the line of his sewer construction, thus necessitating extra labor. That such extra work was performed is not disputed; but the defendant’s claim is that the plaintiff was aware that the filling would be placed upon the avenues by those who preceded him, that the contract so indicated, and that the city, in any event, allowed him for the delay thereby occasioned.

Allowance merely for delay, however, would not compensate the plaintiff for the work performed in removing the filling. Nor do the terms of the contract referred to show that the city was not to be liable for extra work occasioned by its permitting others to place filling which it would be necessary for the plaintiff to remove. The particular provisions relied upon by the city in this respect state:

“It is further agreed that, should postponement or delay be occasioned by the precedence of other contracts on the line of the work which may be either let or executed before or after the execution of this contract, no claim for damages therefor shall be made or allowed, nor shall any claim for damages be made or allowed in consequence of the street or adjoining sewer not being in the condition contemplated by the parties at the time of making the contract, except that, if the contractor shall be delayed * * * by reason of the street or adjoining sewer not being in such condition, such allowance of time shall be made him as shall be deemed reasonable, * * * and incumbrances or obstructions which may be upon the line of the work when it is begun or may be thereafter placed there shall, if directed by the engineer, be removed by the contractor at his own expense.”

The facts show that the contract was awarded the plaintiff in November, 1897, and executed October 26, 1898, for the construction of a sewer in and along various streets and avenues, including portions of Crotona avenue and Arthur avenue. On August 11, 1897, a contract was awarded by the city to Alfred P. Whitton for regulating and grading Crotona avenue, including that part thereof in which the plaintiff was to construct the sewer; and on March 10, 1898, a contract was awarded by the city to George Clarke for the regulating and grading of Arthur avenue, including that part thereof in which the plaintiff was to construct his sewer. Under their contracts with the city, the said Whitton and Clarke proceeded to regulate and grade the said avenues, and in so doing filled in for a considerable depth before the plaintiff had reached with his sewer those portions of the avenues.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Shea v. City of Los Angeles
45 P.2d 221 (California Court of Appeal, 1935)
Callan v. Peck
91 A. 34 (Supreme Court of Rhode Island, 1914)
Lentilhon v. City of New York
92 N.Y.S. 897 (Appellate Division of the Supreme Court of New York, 1905)

Cite This Page — Counsel Stack

Bluebook (online)
81 N.Y.S. 773, Counsel Stack Legal Research, https://law.counselstack.com/opinion/thilemann-v-city-of-new-york-nyappdiv-1903.