Thilemann v. City of New York

82 A.D. 136
Appellate Division of the Supreme Court of the State of New York·Decided July 1, 1903·Published·Cited by 8 cases

Opinions

O’Brien, J. :

The plaintiff seeks to recover upon five separate causes of action, based upon claims which arose in the course of his performance of a contract entered into with the city of New York, whereby he agreed to construct a sewer in East One Hundred and Eighty-seventh street and in adjoining streets and avenues.

For the work performed a certificate was given to the plaintiff, amounting in the aggregate to the sum of $66,633.14, of which he was paid $63,372.67, the sum of $2,611.47 being retained as repairing security, and the sum of $549 being deducted by the city as damages for overtime. The plaintiff’s first cause of action is to recover this sum of $549, he claiming that it was wrongfully deducted and that the defendant had unlawfully delayed him. The contract provided that the work should be completed within 350 days, exclusive of Sundays and holidays and days excepted by the contract, unless more time was required for certain additional work, when it was to be extended proportionally; that the time was to be compared with the aggregate time of inspectors, and not construed as consecutive days, and that the city might deduct as liquidated damages for the non-completion of the work the sum due for “ inspectors’ wages (four dollars a day) for each and every day the aggregate time of all the inspectors * • * * may exceed the time stipulated.” There was no provision in the contract for an allowance of time for delays occasioned by the act, omission or fault of the defendant nor that a certificate of such delays be given, but for unnecessary delay and non-performance by the plaintiff the city was given the right to abrogate the contract.

[138] The defendant’s evidence in the form of certificates and letters and testimony of those connected with the work shows that the inspectors’ time was 978f- days; that 139J days were allowed for unsuitable weather, and that 352 days were allowed for delays occasioned by the city, leaving as overtime above the 350 days stipulated iii the contract 13Y-J days to be charged the contractor, which, at $4 a day, amounted to $549, the sum deducted. The evidence offered by the plaintiff was directed to showing that 510 instead of 352 days should be allowed for the delays occasioned and recognized by the city, and, moreover, that in addition the city was responsible for loss of time in the execution of the contract after the work, was awarded, owing to questions which had arisen regarding the debt limit and: other matters.

It was further claimed by the plaintiff upon the. trial that the computation made by the defendant and the view taken by the court were erroneous in confusing “inspectors’ days” and calendar days. The main insistence- of the plaintiff, however, was that the first cause of action should not be submitted to the jury, but that the court should direct a verdict in his favor, and to the refusal of the court so to do an exception was taken. This exception is urged on our attention upon this appeal, and it is contended that the prosecution of the work having concededly been hindered and delayed by the defendant’s fault, this abrogated the time limit of 350 days prescribed in the- contract, and no deduction should be made by the city, the plaintiff having performed the work within a reasonable time.

If this first cause of action was one properly submitted to the jury, then, upon the evidence adduced, their verdict in defendant’s favor should not be disturbed. We think, however, that the plaintiff’s contention that the conceded delays occasioned by the city abrogated the provision of the contract with respect to damages for overtime, and thereafter the contractor might complete within reasonable time, is correct. No provision of the contract permitted an allowance for delays by the city, and, in the absence of such a provision, it is inconsistent" to hold the plaintiff for overtime in performing and on the other hand compel him to allow delay on the part of the city. (Dady v. Mayor, 57 Hun, 456; Weeks v. Little, 89 N. Y. 566; Phelan v. Mayor, 119 id. 86.) In Dady v. Mayor [139] (supra,) it was said: “ When the city caused any substantial delay in the work, it lost the right to charge the contractors with the stipulated liquidated damages for overtime, and could only insist that the time of completion should be reasonable.” Here the city did not claim nor attempt to establish that there was any unreasonable delay by the contractor, but it stood upon its rights given by that provision of the contract which prescribed the time limit and damages. We think, therefore, that the city was not justified in deducting the sum mentioned or any sum as damages for overtime, and that, for the amount retained as such damages, a verdict should have been directed in plaintiffs favor. It is unnecessary to discuss the subject of the proper manner of computing the overtime, in view of the conclusion at which we have thus arrived with respect to the first cause of action.

The second causé of action is to recover $1,836 for increased cost occasioned by the defendant permitting other contractors to place filling upon the line of his sewer construction, thus necessitating extra labor. That such'extra work was performed is not disputed, but the defendant’s claim is that the plaintiff was aware that the filling would be placed upon the avenues by those who preceded him; that the contract so indicated and that the city in any event, allowed him for the delay thereby occasioned.

Allowance merely for delay, however, would not compensate the plaintiff for the work performed in removing the filling. Nor do the terms of the contract referred to show that the city was not to be liable for extra work occasioned by its permitting others to place filling which it would be necessary for the plaintiff to remove. The particular provisions relied upon by the city in this respect state: “ It is further agreed that should postponement or delay be occasioned by the precedence of other contracts on the' line of the work which may be either let or executed before or after the execution of this contract, no claim for damages therefor shall be made or allowed, nor shall any claims for damages be made or allowed in consequence of the street or adjoining sewer not being in the condition contemplated by the parties at the time of making the contract except that if the contractor shall be delayed * * * by reason of the street or adjoining sewer not being in such condition, such allowance of time shall be made him as shall be deemed reasonable. [140] * * * Any incumbrances or obstructions which may be upon the line of the work when it is begun or may thereafter be placed there, shall if directed by the engineer be removed by the contractor at his own expense.”

Free access — add to your briefcase to read the full text and ask questions with AI

Thilemann v. City of New York, 82 A.D. 136 (N.Y. Ct. App. 1903).

82 A.D. 136 (Thilemann v. City of New York) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

New Again Construction Co. v. City of New York
76 Misc. 2d 943 (New York Supreme Court, 1974)
Johnson v. State
46 Misc. 2d 303 (New York State Court of Claims, 1963)
Shea v. City of Los Angeles
45 P.2d 221 (California Court of Appeal, 1935)
Uvalde Asphalt Paving Co. v. City of New York
196 A.D. 740 (Appellate Division of the Supreme Court of New York, 1921)
Leopold v. City of New York
184 A.D. 244 (Appellate Division of the Supreme Court of New York, 1918)
Mechanics' Bank v. City of New York
164 A.D. 128 (Appellate Division of the Supreme Court of New York, 1914)
Holland Torpedo Boat Co. v. Nixon
61 Misc. 469 (New York Supreme Court, 1908)
Lentilhon v. City of New York
92 N.Y.S. 897 (Appellate Division of the Supreme Court of New York, 1905)