USCOC of Greater Missouri, LLC v. County of Franklin

636 F.3d 927, 2011 WL 710484
CourtCourt of Appeals for the Eighth Circuit
DecidedMarch 2, 2011
Docket09-2525
StatusPublished
Cited by5 cases

This text of 636 F.3d 927 (USCOC of Greater Missouri, LLC v. County of Franklin) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
USCOC of Greater Missouri, LLC v. County of Franklin, 636 F.3d 927, 2011 WL 710484 (8th Cir. 2011).

Opinions

BEAM, Circuit Judge.

Appellant USCOC (U.S. Cellular) appeals from the district court’s sua sponte dismissal of U.S. Cellular’s complaint and denial of all outstanding motions. Because this matter was not moot at the time of the dismissal, we reverse the district court’s order and remand for further proceedings consistent with this decision.

I. BACKGROUND

U.S. Cellular desires to construct a cellular telephone tower in Franklin County, Missouri. To that end, U.S. Cellular filed an application for a conditional use permit (CUP) with the County in January 2007. On April 11, 2007, the Franklin County Planning and Zoning Commission (Commission) denied the application. U.S. Cellular appealed this decision and on July 11, 2007, the Franklin County Board of Zoning Adjustment (the BOZA) affirmed the Commission’s earlier denial of U.S. Cellular’s application.

U.S. Cellular filed this action in federal district court on August 10, 2007, challenging the BOZA’s July 11, 2007, decision, alleging claims arising under the Federal Telecommunications Act of 1996(TCA), as well as Missouri state law. In its complaint, U.S. Cellular prayed for three specific forms of relief in addition to certain monetary requests: 1) a declaration that Franklin County’s denial of the CUP violated TCA procedural and substantive requirements and the Franklin County Unified Land Regulation; 2) an injunction or writ compelling Franklin County to issue a CUP; and 3) an order reserving jurisdiction in the district court “to resolve any issues between the parties as to further site plan and building permit issues, to ensure the integrity of dealings between the parties” regarding the CUP application.

On August 20, 2008, the district court determined that the July 11, 2007, written decision did not satisfy TCA requirements because it did not contain any explanation of the reasons for the denial, i.e., it did not articulate the “substantial evidence” supporting the BOZA’s denial of the U.S. [929]*929Cellular CUP application. Accordingly, the court remanded the action to the BOZA for a new hearing and a new written decision. In that same order, the district court stayed the remainder of U.S. Cellular’s federal action, thus maintaining jurisdiction in the federal court during the pendency of the BOZA remand proceedings.

Following the district court’s remand to the BOZA, the BOZA held rehearings and issued a new written decision on December 23, 2008. In that decision, instead of merely providing the requested written support for the initial denial of U.S. Cellular’s application, the BOZA granted U.S. Cellular’s CUP. U.S. Cellular notified the district court of the BOZA’s action by way of a status report filed on February 17, 2009. Also in that status report, U.S. Cellular notified the district court that Fritz Trust had filed suit in state court on January 21, 2009 (the Fritz Trust action), requesting that the December 23, 2008, BOZA approval be set aside.1 U.S. Cellular’s status report further emphasized that even though the BOZA granted the CUP, Franklin County would not sign it until the County was satisfied that certain conditions were met. This left the entire matter in a state of uncertainty.

The BOZA’s change of tune in its later grant of the CUP lends to the unique posture of this case. On April 3, 2009, the district court issued an order specifically requesting that the parties “file briefs addressing whether [U.S. Cellular’s] First Amended Complaint should be dismissed as moot.” In response, on May 8, 2009, U.S. Cellular filed a Motion for Judgment seeking an order from the district court requiring the County to issue the CUP along with any other required permits, and asking the court to otherwise dispose of all pending motions. U.S. Cellular further requested that the court grant Fritz Trust’s pending motion to consolidate, which would then allow the court to deny the then-pending motion to remand in the Fritz Trust action. U.S. Cellular explained that it moved for judgment because the pending Fritz Trust action prevented the County from issuing all permits necessary for the project to move forward. U.S. Cellular argued in its motion for judgment that “[n]ow, at the eleventh hour, Fritz seeks to undo the work of this Court, relitigate issues that have already been decided, and send this dispute back to square one.” On the issue of mootness, U.S. Cellular claimed that, because it was yet unable to begin construction, it had not yet been fully remedied and the case was thus not moot until work began.

On May 26, 2009, the district court held that because U.S. Cellular’s initial claims were directed at the July 11, 2007, denial of its CUP application — a decision superseded by the BOZA’s December 23, 2008, approval of the same application — the claims were directed at a decision no longer in force or effect. Accordingly, the district court dismissed the case as moot. On June 4, 2009, shortly after the district court’s dismissal in the instant action, the district court handling the Fritz Trust action, which was also in the Eastern District of Missouri but handled by a different judge, granted Fritz Trust’s motion to amend its complaint to remove all federal allegations and remanded the case back to state court. U.S. Cellular did not appeal [930]*930that court’s decision to decline to exercise supplemental jurisdiction in the Fritz Trust action, although it could have. See Carlsbad Tech., Inc. v. HIF Bio, Inc., — U.S. —, 129 S.Ct. 1862, 1867, 173 L.Ed.2d 843 (2009) (“When a district court remands claims to a state court after declining to exercise supplemental jurisdiction, the remand order is not based on a lack of subject-matter jurisdiction for purposes of §§ 1447(c) and (d)” and is thus reviewable on appeal.).2

Currently before us is U.S. Cellular’s appeal from the district court’s sua sponte dismissal in the TCA action. Franklin County elected not to file a brief on appeal.

II. DISCUSSION

We review a district court’s dismissal for mootness de novo. Midwest Farmworker Emp’t and Training, Inc. v. U.S. Dep’t of Labor, 200 F.3d 1198, 1201 (8th Cir.2000).

The TCA enactment in 1996 made substantial changes to the federal regulation of telecommunications as Congress sought “ ‘to accelerate rapidly private sector deployment of advanced telecommunications and information technologies and services to all Americans by opening all telecommunications markets to competition.’” New York SMSA Ltd. P’ship v. Town of Clarkstown, 612 F.3d 97, 100 (2d Cir.2010) (quoting H.R.Rep. No. 104-458, at 113 (1996), reprinted in 1996 U.S.C.C.A.N. 10, 124). The TCA included “new provisions applicable only to wireless telecommunications service providers.” Sprint Telephony PCS, L.P. v. County of San Diego, 543 F.3d 571, 576 (9th Cir.2008) (emphasis in original).

In section 332(c)(7) of the TCA, Congress preserved the authority of state and local governments over zoning and land use issues, but imposed limitations on that authority. 47 U.S.C. § 332(c)(7).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Benton County Sewer District No. 1
674 F. App'x 611 (Eighth Circuit, 2017)
Ne Colorado Cellular, Inc. v. City of North Platte
764 F.3d 929 (Eighth Circuit, 2014)
St. Charles Tower, Inc. v. Kurtz
643 F.3d 264 (Eighth Circuit, 2011)
USCOC of Greater Missouri, LLC v. County of Franklin
636 F.3d 927 (Eighth Circuit, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
636 F.3d 927, 2011 WL 710484, Counsel Stack Legal Research, https://law.counselstack.com/opinion/uscoc-of-greater-missouri-llc-v-county-of-franklin-ca8-2011.