US Wind Inc. v. Intermoor, Inc.

CourtDistrict Court, D. Maryland
DecidedSeptember 13, 2023
Docket1:19-cv-02984
StatusUnknown

This text of US Wind Inc. v. Intermoor, Inc. (US Wind Inc. v. Intermoor, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
US Wind Inc. v. Intermoor, Inc., (D. Md. 2023).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF MARYLAND

* US WIND INC., * * Plaintiff / Counter-Defendant * * v. * Civil Case No. SAG-19-02984 * INTERMOOR, INC., * * * Defendant / Counter-Plaintiff. * * * * * * * * * * * * * * * MEMORANDUM OPINION

Plaintiff US Wind Inc. (“US Wind”), the developer of a windfarm off the coast of Ocean City, Maryland, brought this action against Defendant InterMoor, Inc. (“InterMoor”) for (1) breach of contract; (2) breach of warranty; (3) rescission of contract; (4) unjust enrichment; and (5) tortious interference with prospective economic relationships. See ECF 75-2. Three of these claims plus three counterclaims remain, and this matter is set to begin trial on Monday, October 2, 2023. Currently pending are InterMoor’s third and fifth motions in limine. ECF 207. This Court held a pretrial conference on September 8, 2023, during which it heard argument on these motions. ECF 227. For the reasons explained below, the Court grants both of InterMoor’s remaining motions in limine. I. FACTUAL BACKGROUND This Court’s memorandum opinion on InterMoor’s partial motion for summary judgment, ECF 194, contains a comprehensive discussion of the factual background of this case. At a high level, though, US Wind and InterMoor entered a contractual relationship on July 29, 2019, for the installation of a Meteorological Mast (“Met Mast”) offshore of Ocean City, Maryland. ECF 221 at 27. A lift boat named the Great White was to transport the Met Mast from Louisiana to the project site later that summer. ECF 174-8; ECF 174-9. Delays and challenging weather conditions that the Great White encountered ultimately led to US Wind calling off the project. ECF 93 ¶ 63; ECF 174-30; ECF 221 at 27.

The parties took steps to terminate their agreement. US Wind believed that InterMoor breached the contract and considered it to be a default termination, ECF 174-20, whereas InterMoor interpreted US Wind’s actions as a voluntary termination. ECF 174-16 at 2. The parties also disputed whether and when the Met Mast was to be dropped off in Baltimore or journey back to Louisiana on the Great White. ECF 174-24 at 2; ECF 174-27 at 2; ECF 174-21 at 3. Ultimately, no arrangements were made for the Met Mast to be unloaded, and it continued back to Louisiana. ECF 174-25 at 2. After litigation in multiple U.S. district courts, US Wind eventually retrieved the mast and associated property, ECF 174 at 26, but the 2019 installation of the Met Mast had failed. In bringing this action, US Wind has sought damages as well as “reimbursement for its reasonable attorney fees and costs of litigation incurred in this action and all related actions,

including actions which were or are being litigated in [several federal and state courts] and any further related actions that have been or will be instituted by the parties.” ECF 93 ¶ 201. II. LEGAL STANDARD “A motion in limine is a request for guidance by the court regarding an evidentiary question.” Hunt Valley Baptist Church, Inc. v. Baltimore Cnty., No. 17-CV-804, 2018 WL 2717834, at *7 (D. Md. June 6, 2018) (quoting United States v. Luce, 713 F.2d 1236, 1239 (6th Cir. 1983)). Typically, pretrial motions in limine seek to exclude prejudicial evidence before it is offered at trial. Changzhou Kaidi Elec. Co., Ltd. v. Okin Am., Inc., 102 F. Supp. 3d 740, 745 (D. Md. 2015) (quoting Luce v. United States, 469 U.S. 38, 40 n.2 (1984)). These motions help to streamline a case by allowing a court to avoid “lengthy argument at, or interruption of, the trial.” Banque Hypothecaire Du Canton De Geneve v. Union Mines, Inc., 652 F. Supp. 1400, 1401 (D. Md. 1987); see also Changzhou Kaidi, 102 F. Supp. 3d at 745 (“[Motions in limine] are ‘designed to narrow the evidentiary issues for trial and to eliminate unnecessary trial interruptions.’” (quoting

Louzon v. Ford Motor Co., 718 F.3d 556, 561 (6th Cir. 2013))). Motions in limine further promote judicial efficiency by preserving the issues raised for appeal and eliminating the need for parties to renew their objections at trial, “just so long as the movant has clearly identified the ruling sought and the trial court has ruled upon it.” United States v. Williams, 81 F.3d 1321, 1325 (4th Cir. 1996); see FED. R. EVID. 103(a); cf. R. 103(a) advisory committee’s note to 2000 amendment (acknowledging that Rule 103(a) “applies to all rulings on evidence . . . including so-called ‘in limine’ rulings”). Generally, courts should grant a motion in limine “only when the evidence is clearly inadmissible on all potential grounds.” Dorman v. Anne Arundel Med. Ctr., No. 15-1102, 2018 WL 2431859, at *1 (D. Md. May 30, 2018) (quoting Emami v. Bolden, 241 F. Supp. 3d 673, 681

(E.D. Va. 2017)). Ultimately, rulings on these motions fall within the trial court’s “broad discretion.” Kauffman v. Park Place Hospitality Grp., 468 F. App’x 220, 222 (4th Cir. 2012); see also United States v. Johnson, 617 F.3d 286, 292 (4th Cir. 2010) (noting that evidentiary rulings fall within a trial court’s discretion). III. ANALYSIS A. INTERMOOR’S MOTION IN LIMINE NO. 3 InterMoor moves to exclude evidence of attorneys’ fees and litigation costs “unrelated to the actual prosecution of this case” because such fees must be proved at trial as an element of damages, and US Wind “wrongly withheld such evidence” during pretrial discovery and disclosure. ECF 207 at 12. In its written opposition, US Wind argues (1) that lawsuits originating from other courts are essentially “one and the same” to the present litigation; (2) the Master Services Agreement (“MSA”) contains a prevailing party provision that allows cost recovery “in any litigation relating to this Agreement,” and such a clause may be treated as a collateral matter

post-trial, not as an element of damages; and (3) US Wind put InterMoor on notice of its intent to seek attorneys’ fees and costs in its discovery responses. ECF 212 at 3–6. The parties agree that the prevailing party in this litigation will be able to seek attorneys’ fees from this Court in a collateral proceeding after the trial. The dispute here is about the scope of the fees that can be sought via that process. See FED. R. CIV. P. 54(d)(2); Carolina Power & Light Co. v. Dynegy Mktg. & Trade, 415 F.3d 354, 358 (4th Cir. 2005), abrogated on other grounds by Ray Haluch Gravel Co. v. Cent. Pension Fund of Int’l Union of Operating Eng’rs & Participating Emps., 571 U.S. 177 (2014) (describing “a division in the handling of attorneys fees claims between claims that are not part of the underlying substantive claim, which must be made by motion, and claims that are an element of damages, which presumably must be made by

complaint”). This Court need not decide, at this juncture, whether the lawsuits involving US Wind in other courts are “one and the same” with this action and whether the fees associated with those other cases can be awarded collaterally under the prevailing party provision in this case.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Luce v. United States
469 U.S. 38 (Supreme Court, 1984)
United States v. Johnson
617 F.3d 286 (Fourth Circuit, 2010)
Moien Louzon v. Ford Motor Company
718 F.3d 556 (Sixth Circuit, 2013)
Changzhou Kaidi Electrical Co. v. Okin America, Inc.
102 F. Supp. 3d 740 (D. Maryland, 2015)
Emami v. Bolden
241 F. Supp. 3d 673 (E.D. Virginia, 2017)
Haile v. Holder
468 F. App'x 220 (Fourth Circuit, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
US Wind Inc. v. Intermoor, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/us-wind-inc-v-intermoor-inc-mdd-2023.