U.S. West Financial Services, Inc. v. Buhler, Inc.

150 F.3d 929
CourtCourt of Appeals for the Eighth Circuit
DecidedJuly 31, 1998
Docket97-3548MN
StatusPublished
Cited by3 cases

This text of 150 F.3d 929 (U.S. West Financial Services, Inc. v. Buhler, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
U.S. West Financial Services, Inc. v. Buhler, Inc., 150 F.3d 929 (8th Cir. 1998).

Opinion

RICHARD S. ARNOLD, Circuit Judge.

This appeal arises out of the construction of a municipal waste composting facility in Pembroke Pines, Florida, by Reuter Recycling of Florida. Buhler, Inc., which is owned by Buhler International, Ltd. (then known as Buhler Brothers, Inc.), provided equipment, design, and engineering services for the facility. U.S. West Financial Services lent Reuter money to finance the facility. Less than a year after the facility began operation, it was shut down by the state because of odor problems. Reuter defaulted on its loan payments to U.S. West and. assigned its legal rights to U.S. West.

U.S. West initiated arbitration against Buhler Inc. and Buhler International on fraud and negligence claims. It then alleged substantially the same claims in federal suits, against both Buhler parties in its capacity as lender, and against .Buhler International in its capacity as Reuter’s assignee. The District Court 1 stayed both actions pending the arbitration award. Ultimately, the arbitration panel awarded no damages to U.S. West. Buhler Inc. and Buhler International then moved to confirm the arbitrators’ decision, and U.S. West moved to vacate or modify it as to Buhler International. The District Court confirmed the award as to bbth defendants. It dismissed U.S. West’s assignee action on grounds of res judicata. In U.S. West’s lender action, it granted summary judgment for Buhler Inc. and Buhler International.

On appeal, U.S. West challenges the dismissal of its assignee action against Buhler International and the dismissal of its lender action against both Buhler partiés. We affirm.

I.

In 1990, Reuter and Buhler Inc. agreed that Buhler would design, engineer, and provide equipment for the Pembroke Pines facility’s material separation and recovery system and composting process. The contract included-a requirement that controversies arising from it be arbitrated. Later, U.S. West agreed to lend Reuter $48,545,000 to finance the facility. Soon after the facility was completed and began operation in October 1991, it developed odor problems, and was cited and fined for violations of state odor regulations. U.S. West lent Reuter an additional $4,700,000 to address these problems. The facility had to close in November 1992.

When the plant’s 'odor problems began, Reuter initiated arbitration against Eneorp, the designer of the underground aeration system, for design and construction defects, and was awarded $2.5 million. In December 1994, Reuter initiated arbitration against Buhler Inc. and Buhler International. Buh-ler Inc. asked the District Court to stop the arbitration, on grounds that the claims should have been addressed in the Eneorp litigation. The Court allowed the arbitration to proceed.

In 1995, Reuter defaulted on its loan and assigned its legal rights to U.S. West. In January 1996, U.S. West filed its own arbitration complaint against Buhler Inc. and Buhler International. It sought damages on theories of fraudulent and negligent misrepresentation, promissory estoppel, negligent *932 design and professional malpractice, breach of contract, .and unjust enrichment. As described below, the Buhler parties repeatedly contested Buhler International’s party status.

Before the arbitration hearing, U.S. West filed two suits. First, with respect to the inducement of its loan to Reuter, it asserted against both Buhler parties claims of negligent misrepresentation, fraud, and promissory estoppel. Second, as assignee of Reuter’s legal rights, and in response to Buhler International’s resistance to inclusion in the arbitration, it alleged against Buhler International substantially the same claims that it had raised against both Buhler parties in its arbitration complaint. 2

The arbitration hearing was held in November 1996 and lasted 17 days. At its conclusion, the panel decided: “Claimant is awarded no damages from Respondents on any of its claims.” Appellant’s Add. at 26. The caption of the award notice included, both Buhler parties.

The Buhler parties moved for summary judgment in both federal actions, on grounds of res judicata and collateral estoppel. They also sought confirmation of the panel’s decision in a state court, pursuant to 9 U.S.C. § 9 (1994) and Minn.Stat. Ann. § 572.18 (West 1988). U.S. West removed the confirmation action to federal court and sought to vacate or modify the award, as applied to Buhler International only, pursuant to' 9 U.S.C. §§ 10 and 11 (1994). The District Court confirmed the award as to both Buhler parties. In the assignee action, it granted summary judgment in favor of Buhler International, on grounds of res judicata. In the lender action, it granted summary judgment in favor of both Buhler parties, on the ground that there were no material facts in dispute.

II. ,

U.S. West challenges the District Court’s application of res judicata to its assignee action against Buhler International. It argues that Buhler International was not a party and, therefore, that the arbitration award was not a final decision on the merits of its claims against Buhler International. We affirm.

We assess the preclusive effect of the arbitration award on U.S. West’s assign-ee action under Minnesota law. See Mandich v. Watters, 970 F.2d 462, 465 (8th Cir.1992). Under Minnesota law, “ ‘[a] judgment on the merits constitutes an absolute bar to a second suit for the same cause of action, and is conclusive between parties and priv-ies_’ ” Dorso Trailer Sales, Inc. v. American Body & Trailer, 482 N.W.2d 771, 774 (Minn.1992) (quoting Mattsen v. Packman, 358 N.W.2d 48, 49 (Minn.1984) (citations omitted)). The doctrine “should not be rigidly applied; rather, it focuses on whether its application results in an injustice against the party to be precluded.” Sondel v. Northwest Airlines, 56 F.3d 934, 938 (8th Cir.1995) (citing Houlihan v. Fimon, 454 N.W.2d 633, 635 (Minn.App.1990)). A final arbitration award, unless it is set aside for a legally sufficient reason, has the same preclusive effect as a judgment.

The procedural history of the arbitration supports the District Court’s finding that Buhler International was a party. U.S. West named Buhler International as a respondent in its arbitration complaint and attempted to serve the complaint on it. U.S. West never asked to dismiss Buhler International formally, and in fact opposed Buhler International’s counsel’s proposal to do so. As a formal matter, then, from the time that Buhler International was named as an arbitration party to the time when it was included in the arbitration award’s caption, its party status never changed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
150 F.3d 929, Counsel Stack Legal Research, https://law.counselstack.com/opinion/us-west-financial-services-inc-v-buhler-inc-ca8-1998.