US for Use of Falco Const. v. Summit Gen. Contr.

760 F. Supp. 1004
CourtDistrict Court, E.D. New York
DecidedMarch 21, 1991
Docket89-CV-2931
StatusPublished

This text of 760 F. Supp. 1004 (US for Use of Falco Const. v. Summit Gen. Contr.) is published on Counsel Stack Legal Research, covering District Court, E.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
US for Use of Falco Const. v. Summit Gen. Contr., 760 F. Supp. 1004 (E.D.N.Y. 1991).

Opinion

760 F.Supp. 1004 (1991)

UNITED STATES of America for the Use and Benefit of FALCO CONSTRUCTION CORPORATION, Plaintiff,
v.
SUMMIT GENERAL CONTRACTING CORPORATION and The Fireman's Fund Insurance Company, Defendants.

No. 89-CV-2931.

United States District Court, E.D. New York.

March 21, 1991.

*1005 Birnbaum & Birnbaum, Mineola, N.Y. (Harris Birnbaum, of counsel), for plaintiff.

Thomas Welby, White Plains, N.Y., for defendant Summit General Contracting Corp.

Hart & Hume, New York City (Eugene F. Brady, of counsel), for defendant Fireman's Fund Ins. Co.

MEMORANDUM and ORDER

BARTELS, District Judge.

BACKGROUND

In this Miller Act[1] case Falco Construction Corporation ("Falco"), the use plaintiff and subcontractor, seeks to recover monetary damages from Summit General Contracting Corporation ("Summit"), the general contractor, and Fireman's Fund Insurance Company, Summit's surety on its payment bond (jointly, the "defendants"). Falco commenced this action after Summit failed to pay $97,515.00, monies Falco alleged it was owed for services Falco rendered Summit pursuant to a written proposal (the "proposal" or "sub-contract") to drive test and production piles for a Naval Telecommunications Center ("NTCC") on Staten Island that Summit was constructing for the Department of the Navy (the "Navy"). Falco's demand for $97,515.00 included a claim for (a) $83,845.00 for eighty-nine (89) piles driven from March 8, 1989 through May 19, 1989; (b) $3,240.00 for costs associated with eleven (11) obstructed or broken piles; (c) $1,170.00 for costs associated with spudding[2] thirty-nine (39) piles; and (d) $9,080.00[3] for costs associated *1006 with driving additional piles on July 13, 1989. The defendants counterclaimed alleging they suffered $14,000.00 in damages on account of Falco's negligent, improper and delayed performance.

In December 1989, after finding that there were triable issues of fact regarding Falco's claim for obstructed piles, spudding and additional work performed on July 13, 1989, and defendants' counterclaim, the Court awarded Falco partial summary judgment in the amount of $69,045.00 plus interest, leaving in dispute a total of $28,470.00. See Memorandum and Order of this Court dated December 6, 1989. Thereafter, the defendants moved pursuant to Fed.R.Civ.P. 15(a) to amend their counterclaim alleging that as a result of Falco's delayed and improper performance they actually suffered $229,590.00[4] in damages. The Court granted defendants' motion.

This action was bifurcated and tried without a jury over an eight day period.

CONTENTIONS OF THE PARTIES

A. Falco's Claim

Falco maintains that (1) it is entitled to be reimbursed for spudding, admittedly extra work done without written authorization, notwithstanding the fact that the subcontract contains a contrary provision; (2) under the terms of the sub-contract Summit is responsible for extra costs associated with obstructed piles; and (3) the work performed on July 13, 1989 was pursuant to a separate oral agreement associated with the project that the parties entered into in June 1989.

B. Defendants' Counterclaim

In their counterclaim the defendants contend that Falco (1) provided non-conforming materials; to wit: production piles less than sixty (60) feet long; and (2) did not substantially perform its obligations under the sub-contract by April 17, 1989, thereby breaching the terms of the sub-contract. In essence, the defendants argue that Falco's failure to drive production piles that were a minimum of sixty (60) feet long set off a chain reaction that ultimately delayed construction of the NTCC by fifteen (15) weeks, from April 17, 1989 to August 2, 1989. At the heart of the defendants' counterclaim is an allegation, which Falco denies, that the piles which Falco maintains broke during the course of driving were in fact not broken and were only belatedly denoted as such simply to obscure the fact that the pile driving inspector rejected those piles because they were too short to satisfy the Navy's pile driving criteria.

After due deliberation and full consideration of all of the pleadings, testimony and other evidence the Court makes the following findings of fact and conclusions of law pursuant to Rule 52 of the Federal Rules of Civil Procedure.

FINDINGS OF FACT

1. In September 1988, the Navy awarded Summit a contract to construct the NTCC (the "prime contract"). Falco was not a party to the prime contract and is not bound by its terms. Thereafter, Summit solicited Falco's bid to drive test and production piles for the NTCC and forwarded a copy of the specifications, the pile foundation plan and results of pertinent soil borings[5] to Falco.

2. The specifications, which, parenthetically, are extremely detailed, do not establish a specific length for production piles not does it indicate a time for performance. Pile length is mentioned in only two contexts: First, with respect to bidding on the project, the contractor is advised that the bid length is sixty (60) feet; and second, test pile length is set at sixty-five (65) feet.

3. According to the specifications, the length of production piles would be determined based upon pile driving criteria which the Navy would establish after the *1007 test piles had been driven and load tested.[6]

4. The specifications also provide (a) a mechanism for adjusting the price of the prime contract in the event that pile length differed from that specified as the basis for bidding; (b) that spudding, a common pile driving practice, was permitted provided the Navy's representative on the job site approved; (c) the Navy could waive the pile driving criteria under certain circumstances;[7] and (d) the costs associated with spudded and redriven piles (piles driven to replace piles that were damaged, mislocated or driven out of alignment) are to be borne by the Contractor, in this case Summit, not the Navy.

5. Based on the soil borings, the foundation plan and the specifications Falco's engineer K.K. Ramamurthy ("KK") drafted the proposal[8] which provided in pertinent part that: (a) Falco would "furnish and install 81 creososted [sic] wood piles driven to 30 ton design load in conformance with NYCB [New York City Building] code" ("NYCBC"); (b) Summit would pay Falco an additional sum if piles longer than sixty (60) feet were driven and Falco would credit Summit if piles shorter than sixty (60) feet were used; (c) "all costs due to redesign together with associated costs for remedial work on account of pile deviation, broken piles, etc." were excluded from the price; and (d) any alteration or deviation from the basic proposal which involved extra costs required a separate written agreement.

6. The sub-contract, which embodied all the terms of the parties' agreement, did not specify the time of performance, nor did it contain a damage penalty clause. Furthermore, the subcontract did not incorporate by reference the terms of the prime contract.[9]

7. On December 1, 1988, George Vrettos ("Vrettos"), Summit's project manager, orally accepted the proposal, provided that the price was reduced from $87,500 to $85,000.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pantone, Inc. v. Esselte Letraset, Ltd.
878 F.2d 601 (Second Circuit, 1989)
Libra Bank Ltd. v. Banco Nacional De Costa Rica, S.A.
570 F. Supp. 870 (S.D. New York, 1983)
S. Leo Harmonay, Inc. v. Binks Manufacturing Co.
597 F. Supp. 1014 (S.D. New York, 1984)
Pantone, Inc. v. Esselte Letraset Ltd.
691 F. Supp. 768 (S.D. New York, 1988)
HOWDY JONES CONSTR. CO., INC. v. Parklaw Realty, Inc.
421 N.E.2d 846 (New York Court of Appeals, 1981)
Slatt v. Slatt
477 N.E.2d 1099 (New York Court of Appeals, 1985)
Tantleff v. Truscelli
505 N.E.2d 623 (New York Court of Appeals, 1987)
Clark-Fitzpatrick, Inc. v. Long Island Rail Road
516 N.E.2d 190 (New York Court of Appeals, 1987)
Zev v. Merman
533 N.E.2d 669 (New York Court of Appeals, 1988)
Davis Accoustical Corp. v. National Surety Corp.
27 A.D.2d 624 (Appellate Division of the Supreme Court of New York, 1966)
Savin Brothers, Inc. v. State
62 A.D.2d 511 (Appellate Division of the Supreme Court of New York, 1978)
Webster's Red Seal Publications, Inc. v. Gilberton World-Wide Publications, Inc.
67 A.D.2d 339 (Appellate Division of the Supreme Court of New York, 1979)
Howdy Jones Construction Co. v. Parklaw Realty, Inc.
76 A.D.2d 1018 (Appellate Division of the Supreme Court of New York, 1980)
Carpenter v. Machold
86 A.D.2d 727 (Appellate Division of the Supreme Court of New York, 1982)
Tantleff v. Truscelli
110 A.D.2d 240 (Appellate Division of the Supreme Court of New York, 1985)
Young v. Whitney
111 A.D.2d 1013 (Appellate Division of the Supreme Court of New York, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
760 F. Supp. 1004, Counsel Stack Legal Research, https://law.counselstack.com/opinion/us-for-use-of-falco-const-v-summit-gen-contr-nyed-1991.