Us Ex Rel. Edwin P. Harrison v. Westinghouse Savannah River Company, United States of America, Amicus Supporting Us Ex Rel. Edwin P. Harrison v. Westinghouse Savannah River Company, United States of America, Amicus Supporting

352 F.3d 908, 2003 U.S. App. LEXIS 25789
CourtCourt of Appeals for the Fourth Circuit
DecidedDecember 19, 2003
Docket02-2020
StatusPublished

This text of 352 F.3d 908 (Us Ex Rel. Edwin P. Harrison v. Westinghouse Savannah River Company, United States of America, Amicus Supporting Us Ex Rel. Edwin P. Harrison v. Westinghouse Savannah River Company, United States of America, Amicus Supporting) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Us Ex Rel. Edwin P. Harrison v. Westinghouse Savannah River Company, United States of America, Amicus Supporting Us Ex Rel. Edwin P. Harrison v. Westinghouse Savannah River Company, United States of America, Amicus Supporting, 352 F.3d 908, 2003 U.S. App. LEXIS 25789 (4th Cir. 2003).

Opinion

352 F.3d 908

US Ex Rel. Edwin P. HARRISON, Plaintiff-Appellee,
v.
WESTINGHOUSE SAVANNAH RIVER COMPANY, Defendant-Appellant.
United States of America, Amicus Supporting Appellee.
US Ex Rel. Edwin P. Harrison, Plaintiff-Appellant,
v.
Westinghouse Savannah River Company, Defendant-Appellee.
UNITED STATES of America, Amicus Supporting Appellant.

No. 02-2020.

No. 02-0292.

United States Court of Appeals, Fourth Circuit.

Argued: September 25, 2003.

Decided: December 19, 2003.

COPYRIGHT MATERIAL OMITTED ARGUED: Daniel J. Westbrook, NELSON, MULLINS, RILEY & SCARBOROUGH, L.L.P., Columbia, South Carolina, for Appellant.

Michael David Granston, Appellate Staff, Civil Division, UNITED STATES DEPARTMENT OF JUSTICE, Washington, D.C., for Amicus Curiae.

Richard E. Miley, North Augusta, South Carolina, for Appellee.

ON BRIEF: Jeffrey S. Patterson, NELSON, MULLINS, RILEY & SCARBOROUGH, L.L.P., Columbia, South Carolina, for Appellant.

Robert D. McCallum, Jr., Assistant Attorney General, J. Strom Thurmond, Jr., United States Attorney, Douglas N. Letter, Sambhav N. Sankar, Appellate Staff, Civil Division, UNITED STATES DEPARTMENT OF JUSTICE, Washington, D.C., for Amicus Curiae.

Before WILLIAMS and SHEDD, Circuit Judges, and HAMILTON, Senior Circuit Judge.

Affirmed by published opinion. Judge SHEDD wrote the opinion, in which Judge WILLIAMS and Senior Judge HAMILTON joined.

OPINION

SHEDD, Circuit Judge.

In this False Claims Act case, Edwin Harrison, the qui tam relator, alleged that Westinghouse Savannah River Company (Westinghouse or WSRC) falsely certified to the Department of Energy (DOE) that no organizational conflicts of interest (OCI) existed between Westinghouse and General Physics Corporation (GPC) relating to a proposed $2.75 million government subcontract. After a combined jury and bench trial, the district court entered judgment in favor of Harrison. Westinghouse appeals, and Harrison cross-appeals. We affirm.

I.

Westinghouse is the management and operations contractor for many of DOE's activities at the Savannah River Site near Aiken, South Carolina.1 In the 1980s and 1990s, Westinghouse attempted to develop a $500 million In-Tank Precipitation (ITP) facility to store radioactive waste at the Savannah River Site. As part of this project, Westinghouse began developing a training program for the employees who would eventually operate the ITP facility. By 1992, the training program was behind schedule. James Smith, an experienced Westinghouse manager, was put in charge of developing a Recovery Plan to get the training program back on schedule. Before Westinghouse could subcontract the work, however, it had to obtain approval from DOE.

Smith had several people working for him in developing the Recovery Plan. One of these individuals, Michael Kirkpatrick, was a GPC employee who was working at Westinghouse under a contractual agreement known as a Basic Ordering Agreement (BOA). Westinghouse relied heavily on BOAs from GPC and other off-site firms in developing the Recovery Plan. Ultimately, Smith's team decided that Westinghouse should hire a subcontractor to design and implement the training program even though cost estimates showed that Westinghouse could have done the work in-house for less money than it would cost to hire a subcontractor.

Kirkpatrick, in particular, helped prepare some of the briefing papers that Smith used to convince DOE to allow Westinghouse to subcontract the training program. Kirkpatrick was Smith's "right-hand man." J.A. 563. Mitchell Frank, a Westinghouse employee, expressed concern to Smith that Kirkpatrick was intimately involved in preparing procurement sensitive documents. Frank also told Smith that he was concerned that any subcontractor with access to such information would have an unfair advantage over other subcontractors bidding for the training subcontract.

Westinghouse submitted the subcontracting proposal to DOE for approval. Westinghouse estimated that the subcontract would be short term and would cost $2.75 million. DOE approved Westinghouse's proposal to subcontract the training program.

Westinghouse next prepared a Request for Proposal (RFP) and sought bids from fourteen firms. Only four firms returned bids on time, one of which was GPC. Kirkpatrick helped GPC prepare its bid. As part of its proposal, GPC submitted a certification to Westinghouse attesting that it had no OCIs in connection with the potential award of the subcontract. An OCI is, in part, a relationship or situation in which an entity bidding on a government subcontract receives an unfair competitive advantage relating to the work to be performed.

Smith was one of three Westinghouse employees who reviewed the four bids. Based on this review, Westinghouse selected GPC to receive the training subcontract even though another bidder submitted a lower bid. Before awarding the subcontract to GPC, however, Westinghouse was required to obtain approval from DOE.

William Bowers, a Westinghouse procurement specialist, was responsible for submitting the Procurement Under Review (PUR) package to DOE recommending that DOE approve subcontracting the training program to GPC. Bowers included in the PUR package GPC's bid and certifications, including GPC's certification that no OCIs existed between GPC and Westinghouse.

In September 1992, DOE approved awarding the training subcontract to GPC. The original purchase order was approved for just under $2.5 million. DOE thereafter approved twenty-five additional invoices submitted by Westinghouse. Ultimately, DOE paid more than $9 million for the work performed by GPC on the ITP training program.

II.

Harrison, formerly a vice president at GPC, brought this qui tam action against Westinghouse alleging several violations of the Federal Civil False Claims Act (FCA), 31 U.S.C. §§ 3729-33. The government investigated Harrison's claims but declined to intervene.2

Harrison's original complaint alleged at least ten different claims. He alleged that Westinghouse falsely proposed to DOE that it would be prudent to subcontract the training program rather than do it in-house; falsely certified that GPC had no OCIs; understated the original scope of the work; affixed a false signature on a purchase requisition form; breached its fiduciary duty; allowed GPC to understate its overhead costs; allowed GPC to inflate labor costs; directed GPC to circumvent normal procurement systems to inflate the cost of supplies; failed to effectively manage the subcontract to safeguard against theft, fraud, and waste; and conspired with GPC to defraud the government.

The district court dismissed the complaint in its entirety. It ruled that no false claim had been made either because Harrison's complaint constituted allegations of inefficiency rather than fraud or because the alleged false statements did not relate to a "claim" as contemplated under the FCA.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States Ex Rel. Marcus v. Hess
317 U.S. 537 (Supreme Court, 1943)
United States v. Gaudin
515 U.S. 506 (Supreme Court, 1995)
Neder v. United States
527 U.S. 1 (Supreme Court, 1999)
United States v. TDC Management Corp.
288 F.3d 421 (D.C. Circuit, 2002)
United States v. Alvin Michael Maher
582 F.2d 842 (Fourth Circuit, 1978)
Grand Union Company v. United States
696 F.2d 888 (Eleventh Circuit, 1983)
United States v. Bank of New England, N.A.
821 F.2d 844 (First Circuit, 1987)
Konkel v. Bob Evans Farms Inc.
165 F.3d 275 (Fourth Circuit, 1999)
McGeary v. McGeary
3 A. 22 (Supreme Court of Pennsylvania, 1886)
Winant v. Bostic
5 F.3d 767 (Fourth Circuit, 1993)
Daly v. Hill
790 F.2d 1071 (Fourth Circuit, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
352 F.3d 908, 2003 U.S. App. LEXIS 25789, Counsel Stack Legal Research, https://law.counselstack.com/opinion/us-ex-rel-edwin-p-harrison-v-westinghouse-savannah-river-company-united-ca4-2003.