Urtis v. Comm'r

2013 T.C. Memo. 66, 105 T.C.M. 1428, 2013 Tax Ct. Memo LEXIS 64
CourtUnited States Tax Court
DecidedMarch 5, 2013
DocketDocket No. 21203-11.
StatusUnpublished
Cited by2 cases

This text of 2013 T.C. Memo. 66 (Urtis v. Comm'r) is published on Counsel Stack Legal Research, covering United States Tax Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Urtis v. Comm'r, 2013 T.C. Memo. 66, 105 T.C.M. 1428, 2013 Tax Ct. Memo LEXIS 64 (tax 2013).

Opinion

JAMES M. URTIS AND GAETANA R. URTIS, Petitioners v. COMMISSIONER OF INTERNAL REVENUE, Respondent
Urtis v. Comm'r
Docket No. 21203-11.
United States Tax Court
T.C. Memo 2013-66; 2013 Tax Ct. Memo LEXIS 64; 105 T.C.M. (CCH) 1428;
March 5, 2013, Filed
*64

Decision will be entered for petitioners.

James M. Urtis and Gaetana R. Urtis, Pro se.
Grubert Roger Markley, for respondent.
GOEKE, Judge.

GOEKE
MEMORANDUM FINDINGS OF FACT AND OPINION

GOEKE, Judge: Respondent determined a deficiency in petitioners' 2007 Federal income tax of $52,9441 as a result of his determination that they improperly claimed a $188,070 theft loss deduction. Respondent also determined *67 an accuracy-related penalty under section 6662(a)2 of $10,589. The issues remaining for decision are:

(1) whether petitioners are entitled to the $188,070 theft loss deduction under section 165. We hold that they are; and

(2) whether petitioners are liable for the 20% accuracy-related penalty under section 6662(a). Because petitioners are entitled to the theft loss deduction, no accuracy-related penalty applies.

FINDINGS OF FACT

At the time the petition was filed, petitioners resided in Illinois.

At the relevant times Mr. Urtis was a lawyer and Mrs. *65 Urtis was a homemaker. During the latter half of 2005 Mrs. Urtis was pregnant with petitioners' sixth child, and petitioners decided to expand the size of their house. On October 25, 2005, they entered into a contract with Onyks Construction & Remodeling (Onyks Construction), under which they would pay a total of $400,000 for Onyks Construction to destroy an existing portion of their house and construct an addition in place of the destroyed portion. Onyks Construction was *68 owned and operated by Dariusz Potok, who would oversee the construction at petitioners' house.

The $400,000 contract price was to be paid in installments upon Onyks Construction's completion of certain construction milestones. Onyks Construction was required under the contract not just to construct the exterior portion of the addition, but also to complete the necessary wiring, plumbing, air-conditioning, and heating upgrades. During the many months of construction petitioners' house was uninhabitable; petitioners and their children stayed in an apartment above the residence of Mrs. Urtis' mother and father during this time.

Onyks Construction began work on the project in November 2005 by demolishing the specified *66 portion of petitioners' house. Petitioners often saw a number of Onyks Construction employees and subcontractors at the site. By January 2006 the project was progressing, and petitioners had made several payments to Onyks Construction/Mr. Potok. However, in February 2006 the demolition portion of the project was complete, and Mr. Potok began demanding that petitioners make payments to him before completion of associated project milestones. Mr. Potok claimed that he needed the payments early for construction-related reasons (such as payment of subcontractors or payment for supplies) and told petitioners that if he did not receive the payments early he would have to *69 delay the project. Petitioners were eager to move back into their home as soon as possible (partially because Mrs. Urtis gave birth in February 2006) and made the requested payments.

Mr. Potok's requests for early payments continued for the next several months. Petitioners continued to make the requested payments but attempted to protect their money by increasingly making payments directly to subcontractors and suppliers instead of Mr. Potok/Onyks Construction. Petitioners were concerned by Mr. Potok's requests, although *67 their concerns were somewhat alleviated by the fact that they saw signs of progress when they visited the home. However, some of the apparent progress was actually an illusion, part of Mr. Potok's ruse. For example, Mr. Potok showed Mr. Urtis portions of the wiring in the addition under construction and claimed that the wiring portion of the project had been completed. In fact, the wiring had not been completed. Not being experts in construction, petitioners were unable to detect that Mr. Potok was lying to them about some aspects of the construction which he claimed to have completed.

Construction was running behind schedule when on July 29, 2006, Mr. Potok suddenly died at the age of 30. Petitioners were alerted to Mr. Potok's death and went to his wake to try and find out what would happen with regard to *70 the construction.3 At the wake, petitioners discovered that many of Mr. Potok's subcontractors were not being paid and that Mr. Potok was involved in several other construction projects which were undergoing financial difficulty. As a result of their conversations with others at the wake, petitioners also came to believe that Mr. Potok had a drug problem which may have contributed *68 to his financial problems and subsequent death.4

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
2013 T.C. Memo. 66, 105 T.C.M. 1428, 2013 Tax Ct. Memo LEXIS 64, Counsel Stack Legal Research, https://law.counselstack.com/opinion/urtis-v-commr-tax-2013.