Ursula Gardner v. Des Moines Stucco, LLC

Court of Appeals of Iowa·Decided October 1, 2025·No. 23-2088·Published

Opinion

IN THE COURT OF APPEALS OF IOWA

No. 23-2088

Filed October 1, 2025

URSULA GARDNER, Plaintiff-Appellant,

vs.

DES MOINES STUCCO, LLC, Defendant-Appellee.

Appeal from the Iowa District Court for Howard County, Alan Heavens, Judge.

A plaintiff appeals the district court’s judgment on her breach-of-contract claim. AFFIRMED.

Kevin E. Schoeberl of Story, Schoeberl & Seebach L.L.P., Cresco, for appellant.

Mark R. Hinshaw of The Law Offices of Mark R. Hinshaw, West Des Moines, for appellee.

Considered without oral argument by Schumacher, P.J., and Buller and Langholz, JJ.

LANGHOLZ, Judge.

This is a contract dispute between Ursula Gardner and Des Moines Stucco, LLC, the contractor she hired to install a stucco-like exterior to her newly built home. After a bench trial, the district court found that Des Moines Stucco breached the contract when it stopped work after completing only the first of two coats of stucco. But the court also found that Gardner failed to mitigate her damages because she did not hire a new contractor to complete the second coat for over eighteen months, causing the first coat to deteriorate and requiring the new contractor to do two more coats rather than just one. And so, in calculating the damages award, the court found that Gardner could have reduced her expenses with the new contractor by half if she had mitigated. The court also awarded only $1 in nominal damages—rather than the $5000 she requested—for Gardner’s loss of the warranty she was originally promised under the contract because she failed to prove the value of the warranty. And the court denied Gardner’s request for common-law attorney fees.

On appeal, Gardner challenges each of these adverse rulings. But this case was tried at law, so we are bound by the district court’s factual findings if they are supported by substantial evidence. That sets a high bar on appeal that Gardner has not cleared. Substantial evidence supports the court’s finding that Gardner failed to mitigate her damages and its calculation of the damages that could have been mitigated. So too does it support the court’s finding that Gardner failed to prove the value of her lost warranty. And nothing in the record comes close to the egregious behavior needed to support Gardner’s extraordinary request for common-law attorney fees. We thus affirm the district court’s judgment.

I. Background Facts and Proceedings Gardner retired from the Army in 2018 and planned to build her dream home on part of her family farm in Cresco, Iowa. Gardner envisioned a Mediterranean- style home with a vineyard out back. And she had the goal of opening a bed and breakfast in the future.

As part of the construction process, Gardner contracted with Des Moines Stucco in May 2019 to install a stucco-like exterior on her home. Under the contract, Des Moines Stucco would install a stucco-like “exterior insulated finish system” that is made up of two coats: a base coat of foam and mesh and a finish coat. And Gardner would pay a total of $64,784 in three installments of $21,594.67—one payment up front for materials, another after application of the base coat, and the final payment after completion of the project. Gardner made the first and second payments without controversy.

But the relationship between Gardner and Des Moines Stucco broke down before the installation of the final coat. So in late June 2019, Des Moines Stucco emailed Gardner to request 90% of the final payment before it would return to install the final coat to complete the project. Gardner rejected the proposed modification of the contract. And the next day, Des Moines Stucco gave Gardner two options: modify the contract as it had proposed or end the relationship. Gardner responded by suggesting Des Moines Stucco may be in breach of their contract and highlighting that if it refused to complete the work she would have “an additional expense to bring[] in another contractor.”

With the impasse still unresolved on July 9, 2019, Gardner issued an ultimatum that “if the crew does not return by July 24th to begin completing the

project, a district court case will be filed for the amount already received plus any other fees as no company is going to warranty Des Moines Stucco’s work.” Des Moines Stucco responded the same day, again summarizing its “many concerns” with returning and explaining that it does “everything possible to make every single customer we work with extremely happy” and that it felt it had “gone out of our way to do that for you but it is just not possible.” Gardner’s July 24 deadline came and went without Des Moines Stucco returning to complete the project.

It was another four months before Gardner filed this lawsuit. During that time, Gardner’s attorney sent two letters to Des Moines Stucco demanding that it complete work on the project. In the second letter, sent on August 15, the attorney gave Des Moines Stucco until August 26 to complete the project and threatened that if it did not do so, Gardner would sue. Des Moines Stucco never returned to complete the project. And in mid-November, Gardner sued, asserting claims for (1) specific performance; (2) breach of contract; (3) breach of implied warranty of fitness for particular purpose; (4) breach of implied warranty of merchantability; and (5) breach of duty of good faith and fair dealing.

In March 2021—sixteen months after filing suit and nineteen after her final deadline for Des Moines Stucco to return to work—Gardner finally hired a new contractor to complete the installation of the stucco-like exterior. Gardner had first contacted two other potential contractors but did not reach an agreement with either of them to perform the work. Because of the condition of the already-applied base coat, the new contractor had to apply two more coats rather than just the one finish coat intended under the original contract between Des Moines Stucco and Gardner. Gardner thus paid the new contractor $52,400—significantly more than

the final payment of $21,594.67 she would have paid under the original contract. The new contractor completed the installation in June 2021—two years after Des Moines Stucco left it unfinished. And the same month, Gardner dismissed her specific-performance claim—two days before it was set to be tried to the court.

After a one-day bench trial on the remaining claims in November 2023, the district court found that Des Moines Stucco breached its contract with Gardner and entered judgment in her favor on her breach of contract claim. But the court awarded Gardner only $18,861.33 of the $50,060.13 in damages that she requested. The court disagreed with two aspects of her request.1 First, the court found that Gardner failed to mitigate her damages by unreasonably delaying in hiring a new contractor to complete the project. The court found that her new contractor “had to put two coats on instead of just the final coat” because “the cold weather over the winter of 2019 and then the winter of 2020 ruined the work that Des Moines Stucco had already done.” And it reasoned that she “knew after July 24, 2019 that Des Moines Stucco was not coming back to finish the project” and her “decision to wait that long was not reasonable and undeniably made the project more expensive to complete.” So the court found that Gardner could have reduced her expenses with the new contractor by half—from $52,400 to $26,200—if she had mitigated. And it calculated her damage award using that lower number.2

1 The court agreed with the rest of her request, awarding another $14,255 in damages that are not at issue on appeal. 2 The court subtracted the $21,594.67 that Gardner would have had to pay Des

Moines Stucco under the contract resulting in an award of $4605.33 to cover Gardner’s completion costs. Gardner does not dispute this part of the calculation.

Free access — add to your briefcase to read the full text and ask questions with AI

Ursula Gardner v. Des Moines Stucco, LLC, (iowactapp 2025).

Ursula Gardner v. Des Moines Stucco, LLC (Ursula Gardner v. Des Moines Stucco, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Tim O'Neill Chevrolet, Inc. v. Forristall
551 N.W.2d 611 (Supreme Court of Iowa, 1996)
RET Corp. v. Frank Paxton Co., Inc.
329 N.W.2d 416 (Supreme Court of Iowa, 1983)
Natkin & Company v. RF Ball Construction Company
123 N.W.2d 415 (Supreme Court of Iowa, 1963)
Kuehl v. Freeman Bros. Agency, Inc.
521 N.W.2d 714 (Supreme Court of Iowa, 1994)
Van Oort Construction Co. v. Nuckoll's Concrete Service, Inc.
599 N.W.2d 684 (Supreme Court of Iowa, 1999)
Basic Chemicals, Inc. v. Benson
251 N.W.2d 220 (Supreme Court of Iowa, 1977)