Ursula Gardner v. Des Moines Stucco, LLC

CourtCourt of Appeals of Iowa
DecidedOctober 1, 2025
Docket23-2088
StatusPublished

This text of Ursula Gardner v. Des Moines Stucco, LLC (Ursula Gardner v. Des Moines Stucco, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ursula Gardner v. Des Moines Stucco, LLC, (iowactapp 2025).

Opinion

IN THE COURT OF APPEALS OF IOWA

No. 23-2088 Filed October 1, 2025

URSULA GARDNER, Plaintiff-Appellant,

vs.

DES MOINES STUCCO, LLC, Defendant-Appellee. ________________________________________________________________

Appeal from the Iowa District Court for Howard County, Alan Heavens,

Judge.

A plaintiff appeals the district court’s judgment on her breach-of-contract

claim. AFFIRMED.

Kevin E. Schoeberl of Story, Schoeberl & Seebach L.L.P., Cresco, for

appellant.

Mark R. Hinshaw of The Law Offices of Mark R. Hinshaw, West Des Moines,

for appellee.

Considered without oral argument by Schumacher, P.J., and Buller and

Langholz, JJ. 2

LANGHOLZ, Judge.

This is a contract dispute between Ursula Gardner and Des Moines

Stucco, LLC, the contractor she hired to install a stucco-like exterior to her newly

built home. After a bench trial, the district court found that Des Moines Stucco

breached the contract when it stopped work after completing only the first of two

coats of stucco. But the court also found that Gardner failed to mitigate her

damages because she did not hire a new contractor to complete the second coat

for over eighteen months, causing the first coat to deteriorate and requiring the

new contractor to do two more coats rather than just one. And so, in calculating

the damages award, the court found that Gardner could have reduced her

expenses with the new contractor by half if she had mitigated. The court also

awarded only $1 in nominal damages—rather than the $5000 she requested—for

Gardner’s loss of the warranty she was originally promised under the contract

because she failed to prove the value of the warranty. And the court denied

Gardner’s request for common-law attorney fees.

On appeal, Gardner challenges each of these adverse rulings. But this case

was tried at law, so we are bound by the district court’s factual findings if they are

supported by substantial evidence. That sets a high bar on appeal that Gardner

has not cleared. Substantial evidence supports the court’s finding that Gardner

failed to mitigate her damages and its calculation of the damages that could have

been mitigated. So too does it support the court’s finding that Gardner failed to

prove the value of her lost warranty. And nothing in the record comes close to the

egregious behavior needed to support Gardner’s extraordinary request for

common-law attorney fees. We thus affirm the district court’s judgment. 3

I. Background Facts and Proceedings

Gardner retired from the Army in 2018 and planned to build her dream home

on part of her family farm in Cresco, Iowa. Gardner envisioned a Mediterranean-

style home with a vineyard out back. And she had the goal of opening a bed and

breakfast in the future.

As part of the construction process, Gardner contracted with Des Moines

Stucco in May 2019 to install a stucco-like exterior on her home. Under the

contract, Des Moines Stucco would install a stucco-like “exterior insulated finish

system” that is made up of two coats: a base coat of foam and mesh and a finish

coat. And Gardner would pay a total of $64,784 in three installments of

$21,594.67—one payment up front for materials, another after application of the

base coat, and the final payment after completion of the project. Gardner made

the first and second payments without controversy.

But the relationship between Gardner and Des Moines Stucco broke down

before the installation of the final coat. So in late June 2019, Des Moines Stucco

emailed Gardner to request 90% of the final payment before it would return to

install the final coat to complete the project. Gardner rejected the proposed

modification of the contract. And the next day, Des Moines Stucco gave Gardner

two options: modify the contract as it had proposed or end the relationship.

Gardner responded by suggesting Des Moines Stucco may be in breach of their

contract and highlighting that if it refused to complete the work she would have “an

additional expense to bring[] in another contractor.”

With the impasse still unresolved on July 9, 2019, Gardner issued an

ultimatum that “if the crew does not return by July 24th to begin completing the 4

project, a district court case will be filed for the amount already received plus any

other fees as no company is going to warranty Des Moines Stucco’s work.” Des

Moines Stucco responded the same day, again summarizing its “many concerns”

with returning and explaining that it does “everything possible to make every single

customer we work with extremely happy” and that it felt it had “gone out of our way

to do that for you but it is just not possible.” Gardner’s July 24 deadline came and

went without Des Moines Stucco returning to complete the project.

It was another four months before Gardner filed this lawsuit. During that

time, Gardner’s attorney sent two letters to Des Moines Stucco demanding that it

complete work on the project. In the second letter, sent on August 15, the attorney

gave Des Moines Stucco until August 26 to complete the project and threatened

that if it did not do so, Gardner would sue. Des Moines Stucco never returned to

complete the project. And in mid-November, Gardner sued, asserting claims for

(1) specific performance; (2) breach of contract; (3) breach of implied warranty of

fitness for particular purpose; (4) breach of implied warranty of merchantability;

and (5) breach of duty of good faith and fair dealing.

In March 2021—sixteen months after filing suit and nineteen after her final

deadline for Des Moines Stucco to return to work—Gardner finally hired a new

contractor to complete the installation of the stucco-like exterior. Gardner had first

contacted two other potential contractors but did not reach an agreement with

either of them to perform the work. Because of the condition of the already-applied

base coat, the new contractor had to apply two more coats rather than just the one

finish coat intended under the original contract between Des Moines Stucco and

Gardner. Gardner thus paid the new contractor $52,400—significantly more than 5

the final payment of $21,594.67 she would have paid under the original contract.

The new contractor completed the installation in June 2021—two years after Des

Moines Stucco left it unfinished. And the same month, Gardner dismissed her

specific-performance claim—two days before it was set to be tried to the court.

After a one-day bench trial on the remaining claims in November 2023, the

district court found that Des Moines Stucco breached its contract with Gardner and

entered judgment in her favor on her breach of contract claim. But the court

awarded Gardner only $18,861.33 of the $50,060.13 in damages that she

requested. The court disagreed with two aspects of her request.1

First, the court found that Gardner failed to mitigate her damages by

unreasonably delaying in hiring a new contractor to complete the project. The

court found that her new contractor “had to put two coats on instead of just the final

coat” because “the cold weather over the winter of 2019 and then the winter of

2020 ruined the work that Des Moines Stucco had already done.” And it reasoned

that she “knew after July 24, 2019 that Des Moines Stucco was not coming back

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tim O'Neill Chevrolet, Inc. v. Forristall
551 N.W.2d 611 (Supreme Court of Iowa, 1996)
RET Corp. v. Frank Paxton Co., Inc.
329 N.W.2d 416 (Supreme Court of Iowa, 1983)
Natkin & Company v. RF Ball Construction Company
123 N.W.2d 415 (Supreme Court of Iowa, 1963)
Kuehl v. Freeman Bros. Agency, Inc.
521 N.W.2d 714 (Supreme Court of Iowa, 1994)
Van Oort Construction Co. v. Nuckoll's Concrete Service, Inc.
599 N.W.2d 684 (Supreme Court of Iowa, 1999)
Basic Chemicals, Inc. v. Benson
251 N.W.2d 220 (Supreme Court of Iowa, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
Ursula Gardner v. Des Moines Stucco, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ursula-gardner-v-des-moines-stucco-llc-iowactapp-2025.