Urena v. Capano Homes, Inc.

901 A.2d 145, 2006 WL 1727577
CourtSuperior Court of Delaware
DecidedJune 6, 2006
DocketC.A. 04C-11-018 SCD
StatusPublished
Cited by3 cases

This text of 901 A.2d 145 (Urena v. Capano Homes, Inc.) is published on Counsel Stack Legal Research, covering Superior Court of Delaware primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Urena v. Capano Homes, Inc., 901 A.2d 145, 2006 WL 1727577 (Del. Ct. App. 2006).

Opinion

OPINION

DEL PESCO, J.

Defendants have filed motions for summary judgment, contending that the factual record does not support the claims against them for negligence, and for negligent hiring. I have concluded that no factual issues preclude summary judgment as to Muirfield and Capano Homes. There are factual issues related to Rising Sun which preclude summary judgment.

FACTS

In 1999, the construction of 139 single-family lots began at the Preserve at Lafayette Hills (“the Preserve”) by Capano Homes, Inc. (“Capano Homes”). 1 Capano Homes was retained by landowner, Muir-field Associates, LLC (“Muirfield”) to complete the construction project and act as general construction manager of the Preserve. Joseph M. Capano (“Capano”) is 99% owner of both Capano Homes and Muirfield.

Capano Homes’s construction manager for the Preserve was Raymond Worrall (‘Worrall”). Worrall worked for Capano Homes for almost six years prior to the commencement of the Preserve project. 2 He was responsible for all construction paperwork including permits, drawings, fieldwork, as well as bids and subcontracts. Worrall was responsible for hiring subcontractors with input and/or approval from Capano.

Initially, Capano Homes hired Martin Contractors (“Martin”), a subcontractor, to perform roofing and siding work at the Preserve. Martin soon became unable to handle the workload at the Preserve. Worrall contacted Mun Seok Lee (“Lee”), owner of Rising Sun Contractors (“Rising Sun”), to take over the roofing and siding work. Lee testified that he received a message from Worrall one evening in October 2002, and was asked to report to the Preserve the next day. 3 Worrall stated that prior to hiring Rising Sun, he inquired with ARK Contractors and S.G. Williams, two companies that previously had worked *148 with Rising Sun, as to Rising Sun’s reputation for workmanship and as to whether it had appropriate insurance coverage for construction work. 4 Safety was not a part of this inquiry. Capano Homes had not previously hired and/or worked with Rising Sun.

On November 10, 2002, Worrall, on behalf of Capano Homes, signed a subcontract with Lee, on behalf of Rising Sun, to complete all siding and roofing projects at the Preserve. Rising Sun agreed to provide all materials and labor for the roofing project, and to be solely responsible for supervising its employees working at the Preserve. The subcontract delegated responsibility for Federal, OSHA and EEO safety compliance to Rising Sun. 5 The Contract contained the following relevant terms:

1. The SUBCONTRACTOR agrees that all work and/or materials will be in compliance with all state and local codes, ordinances and regulations, including but not restricted to Federal, OSHA and EEO Requirements.
5. It is agreed that the SUBCONTRACTOR while having to comply with all requirements and conditions set forth in this agreement, is an independent contractor in all respects. As such the SUBCONTRACTOR is solely responsible for his employees, including payroll taxes, benefits and insurance. The SUBCONTRACTOR is also responsible for all of his materials and equipment brought on the job site.
9. The SUBCONTRACTOR shall procure and maintain during the life of the Contract, the insurance coverage’s outline in Section # 10 — Insurance Requirements. A Certificate evidencing such insurance coverage must be submitted to the CONTRACTOR prior to authorization to start work.

More than two years prior to signing the contract with Capano Homes, Rising Sun had executed a written contract with Jose Felix Hernandez (“Hernandez”) to provide all labor, supervision and tools to perform roofing and siding jobs acquired by Rising Sun. This written agreement between Rising Sun and Hernandez was dated January 30, 2000. Capano Homes was unaware of the contractual relationship between Rising Sun and Hernandez. 6

The Preserve Worksite

Various supervisors, from each of the contracting parties herein, were present at the Preserve. 7 The most consistently present supervisor on site was Charles Chambers (“Chambers”). Chambers worked for Capano Homes as the superintendent assigned to the Preserve. Chambers described his job capacity as overseeing the quality of construction, compliance with specifications, payroll issues, overall safety and scheduling subcontractors. Chambers, Worrall and Capano each testified that Chambers was also responsible *149 for overall safety oversight. 8 That is, Chambers was to ensure that subcontractors were working safely and in compliance with OSHA standards. 9

On several occasions Chambers observed roofers, employed by Rising Sun, working without fall protection. Chambers reported these observations to Wor-rall, his supervisor. Worrall told Chambers he would take care of the problem. After Chambers contacted Worrall a second time to report his observations of unsafe behavior by the roofers, he also contacted Chang Soo “Jason” Son (“Son”), Lee’s field assistant at the Preserve. After noting no change in safety procedures, Chambers again contacted Son and threatened to fire Rising Sun if his workers did not comply with safety standards. 10

Lee hired Son as a field assistant at the Preserve to ensure OSHA compliance by the roofing laborers. Son recalls being told by Chambers that workers were not wearing their harnesses and that non-compliance with the use of fall protection would result in Rising Sun’s termination from the site. Son immediately informed Miguel Romero (“Romero”), Hernandez’s on-site job supervisor, that workers were to weai’ their safety harnesses. Son testified that he never saw a worker without a safety harness while he was working at the Preserve. Plaintiff, Pablo Cesar Urena’s (“Urena” or “plaintiff’) co-worker, Ricardo Picado Meza (“Meza”), testified that Son was regularly on the job site and would observe the workers and instruct them as to how to do their job. 11 Both Urena and Meza testified that the roofers never wore safety harnesses at this job site.

The Accident

On January 21, 2003, plaintiff fell from a rooftop at the Preserve’s Construction Project and sustained serious injuries. 12 At that time, plaintiff, a Costa Rican national, was a twenty-two year-old illegal alien. 13 He had been employed as a roofer for approximately six years. 14 Prior to the accident, plaintiff had worked for Hernandez for three years doing various roofing jobs. 15

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Andino v. Nexius Solutions
Superior Court of Delaware, 2026
N.K.S. Distributors, Inc.
Superior Court of Delaware, 2014
Hauptman v. WMC, INC.
224 P.3d 1175 (Court of Appeals of Kansas, 2010)
Dye v. WMC, INC.
172 P.3d 49 (Court of Appeals of Kansas, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
901 A.2d 145, 2006 WL 1727577, Counsel Stack Legal Research, https://law.counselstack.com/opinion/urena-v-capano-homes-inc-delsuperct-2006.