Urban's Ceramic Tile, Inc. v. McLain

113 So. 3d 477, 2013 WL 1442159, 2013 La. App. LEXIS 724
CourtLouisiana Court of Appeal
DecidedApril 10, 2013
DocketNo. 47,955-CA
StatusPublished
Cited by1 cases

This text of 113 So. 3d 477 (Urban's Ceramic Tile, Inc. v. McLain) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Urban's Ceramic Tile, Inc. v. McLain, 113 So. 3d 477, 2013 WL 1442159, 2013 La. App. LEXIS 724 (La. Ct. App. 2013).

Opinion

MOORE, J.

|! Urban’s Ceramic Tile Inc., d/b/a/ Bob Moss Carpet One (“Urban”), the subcontractor, appeals a writ of mandamus directing it to deliver a request to cancel a claim or privilege under the Private Works Act, and an order for Urban to pay attorney fees to John and Kristi McClain,1 the owners. For the reasons expressed, we affirm.

Factual and Procedural Background

The McClains bought a 5.7-acre lot on Dogwood Trail in Minden and, in April 2010, hired Mustang Homes to build a house on it. Neither Mustang nor the McClains filed notice of contract in the public records of Webster Parish or posted a bond to secure the payment of subcontractors. Mustang subcontracted the carpet, flooring and ceramic tile work to [479]*479Urban; the McClains never had any interaction with Urban.

According to testimony at trial, Mustang fell into financial difficulty and later declared bankruptcy; by late November 2010, Mustang was not answering the McClains’ phone calls and faxes. The McClains sent a paper letter to Mustang via express mail, received on December 8, 2010, which complained that the house “has not been constructed in a timely manner,” requested a “10-day completion of our home,” and attached a punch list of 43 items still to be completed. Mustang never responded in any way.

Mustang failed to pay Urban for its materials and labor, a total of $15,411.62. On February 16, 2011, Urban filed a statement of “lien and privilege” in the public records of Webster Parish, and on September 19, 2011, it filed the instant petition for amounts due and to enforce its privilege funder the Private Works Act.

The McClains answered, showing that the claimant must file its statement of claim or privilege within 60 days of substantial completion of the work, under La. R.S. 9:4822C(2); despite their earlier letter to Mustang, they alleged that the house was substantially completed by December 8, 2010. By an accompanying memo, they argued that on that date they changed the locks on the doors; the punch list contained only minor items to be remedied, not affecting substantial completion as defined by La. R.S. 9:4822H(2). They alleged that Urban’s statement of claim and privilege, filed February 16, 2011, was over 60 days after December 8, 2010, the date of substantial completion, not timely and thus invalid. They also moved for writ of mandamus directing Urban to deliver a written request to the clerk of court of Webster Parish to cancel the claim or privilege under La. R.S. 9:4833 B, and a request for attorney fees under La. R.S. 9:4833C.

Trial Testimony and Action of District Court

At trial in April .2012, Mr. McClain testified that the house was “just about finished” by late October 2010. He identified a receipt showing the last major delivery to the house, the major appliances, on November 2. The punch list, he explained, was just for minor touch-ups which he himself performed after December 8, when he took possession of the house by changing the locks. He introduced photos date-marked December 19, showing the kitchen in use by then. On cross-examination, he agreed that his family did not actually move into the house until early 2011,2 but |amaintained it was ready to occupy by December 8. Questioned by the court, he described the punch list items he actually performed (such as bolting the dishwasher to the frame, installing the garage door and laying the attic insulation) and those he simply left undone (such as placing shutters on the outside windows and installing a shower door in the master bath — he hung a shower curtain instead). He added that he was at the house almost every day he was not out deer hunting.

Urban’s first witness, Nugent, a carpet layer who sub-subcontracted work from Urban, testified that he finished his part of the job in early November. At that time, the house looked “pretty much complete.”

Urban’s other witness, Ms. Floyd, had been a design consultant for Mustang Homes at the time of these events and was a carpet salesman for Urban at the time of trial. She testified that she tried to help [480]*480the McClains finish the house after “the builder quit.” In fact, she furnished the punch list to the McClains on October 26; she described it as “a long list of small things,” the most serious being the attic insulation.

The district court ruled orally that by December 8, 2010, when the McClains changed the locks on the house and started going there daily, they exercised possession (if not occupation) of the house. The court accepted Nugent’s testimony that the house looked complete by sometime in November, and Ms. Floyd’s testimony that the punch list comprised only small things. The court found that the statement of claim and privilege, filed February 26, 2011, was untimely. The court granted the writ, directing |4the clerk of court to erase Urban’s statement of claim and privilege, and ordered Urban to pay the McClains an attorney fee of $3,000. Urban has appealed.

Applicable Law

The Private Works Act, La. R.S. 9:4801-4855, creates a privilege on an immovable to secure the owner’s obligation arising out of work on the immovable. La. R.S. 9:4801. The privilege is in favor of, inter alia, subcontractors for the price of their work. La. R.S. 9:4802 A(l); First Thrift & Loan LLC v. Griffin, 41,666 (LaApp. 2 Cir. 3/14/07), 954 So.2d 269. When no notice of contract has been filed, the preservation of claims and privileges is regulated by La. R.S. 9:4822C:

C. Those persons granted a claim and privilege by R.S. 4802 for work arising out of a general contract, notice of which is not filed, * * * shall file a statement of their respective claims and privileges within sixty days after:
(1) The filing of a notice of termination of the work; or
(2) The substantial completion or abandonment of the work, if a notice of termination is not filed.
Substantial completion is defined in La. R.S. 9:4822H:
H. A work is substantially completed when:
(1) The last work is performed on, or materials are delivered to the site of the immovable or to that portion or area with respect to which a notice of partial termination is filed; or
(2) The owner accepts the improvement, possesses or occupies the immovable, or that portion or area of the immovable with respect to which a notice of partial termination is filed, although minor or inconsequential matters remain to be finished or minor defects or errors in the work are to be remedied.

|fiAny statement of claim and privilege filed over 60 days after substantial completion is invalid. E. Smith Plumbing Inc. v. Manuel, 11-1277 (La. App. 3 Cir. 3/28/12), 88 So.3d 1209; Norman H. Voelkel Const. Inc. v. Recorder of Mortgages, 2002-1153 (LaApp. 1 Cir. 6/27/03), 859 So.2d 9, writs denied, 2003-1962, 2003-2133 (La.10/31/03), 857 So.2d 486, 488; C & S Safety Systems Inc. v. SSEM Corp., 2002-1780 (LaApp. 4 Cir. 3/19/03), 843 So.2d 447. The determination of when substantial completion occurred is a question of fact and subject to the manifest error standard of review on appeal. All Seasons Const. Inc. v. Mansfield Housing Auth., 40,490 (LaApp. 2 Cir. 1/25/06), 920 So.2d 413, and citations therein.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cupp Drug Store, Inc. v. Blue Cross
201 So. 3d 319 (Louisiana Court of Appeal, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
113 So. 3d 477, 2013 WL 1442159, 2013 La. App. LEXIS 724, Counsel Stack Legal Research, https://law.counselstack.com/opinion/urbans-ceramic-tile-inc-v-mclain-lactapp-2013.