All Seasons Construction, Inc. v. Mansfield Housing Authority

920 So. 2d 413, 2006 La. App. LEXIS 69, 2006 WL 167660
CourtLouisiana Court of Appeal
DecidedJanuary 25, 2006
DocketNo. 40,490-CA
StatusPublished
Cited by1 cases

This text of 920 So. 2d 413 (All Seasons Construction, Inc. v. Mansfield Housing Authority) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
All Seasons Construction, Inc. v. Mansfield Housing Authority, 920 So. 2d 413, 2006 La. App. LEXIS 69, 2006 WL 167660 (La. Ct. App. 2006).

Opinion

STEWART, J.

hAU Seasons Construction, Inc. (“ASC”) filed suit against the Mansfield Housing Authority (“MHA”) to recover $22,200 withheld as liquidated damages under a construction contract between the two parties. MHA asserted a reconventional demand seeking damages, costs, and attorney fees for ASC’s alleged failure to perform its contractual obligations. The pertinent issue was the date of substantial completion of the project, which the trial [415]*415court resolved in ASC’s favor. MHA appealed the judgment ordering it to pay damages. Finding no manifest error, we affirm.

FACTS

The parties entered a contract on November 18, 1999, requiring ASC to re-roof and replace the fascia and soffit on 28 buildings, each a duplex, at a contract price of $116,725. The contract provided for the date of commencement to be fixed in a “Notice to Proceed” letter, required the contractor to achieve substantial completion of the work not later than 120 calendar days from the “Notice to Proceed” date, and provided for liquidated damages in the amount of $200 per day for each day beyond the completion date. The “Notice to Proceed” letter was issued on December 20, 1999. Although the initial completion date was April 18, 2000, the completion date was extended ten days by agreement to April 28, 2000. A change order also increased the contract price to $118,137.

On April 18, 2000, Edward Angel, ASC’s owner and president, wrote to Ronnie Du-vall, the construction inspector on behalf of MHA’s architect, Alliance Inc., stating that the project was “100% complete,” other than | ¡punch list items which had not yet been received. Angel requested a certificate of substantial completion. By letter dated May 2, 2000, Duvall informed Angel that he could not determine the project to be substantially complete, and he included a punch list of items to be completed before issuance of a certificate of substantial completion. The letter informed Angel that the third pay application was being withheld and that “the amended contract completion date of April 28, 2000 has passed.”

The record includes a number of punch lists introduced into evidence by the parties as a joint exhibit. The first is a handwritten punch list dated April 18, 2000, covering 18 of the buildings. The second is a typed punch list dated May 2, 2000, which lists 10 general items (including cleaning debris, providing warranties, submitting payroll records, painting louvers, caulking, fixing gaps at electrical pole risers, and fitting holes around porch light fixtures) and two specific items (reconfiguring the “birdboxes” where the soffit line meets the eave to prevent water from seeping into the sub-frame and tucking the J-mold into the fascia at intersecting soffit fines) to be addressed on most of the buildings. The third is a typed punch fist dated April 18, 2000, of specific items applicable to thé 18 buildings covered on the handwritten fist. Monetary values are assigned for each item on the fist. The fourth is a typed list dated April 28, 2000, of specific items for the remaining 10 buildings with monetary values assigned for each item. The most significant items on the fists are the reconfiguration of the birdboxes and replacement of wavy fascia on a number of the buildings. The fifth and final fist is one-page dated August 18, 2000.

| ¡Additional correspondence in the record reflects a dispute between the parties over the substantial completion date, work on the punch fists, and the cause of the wavy fascia. ASC maintained that the wavy fascia was due to the age of the existing construction, while MHA attributed the problem to exposure of the sub-frame to the elements while awaiting replacement of the fascia. The certificate of substantial completion was finally issued on August 18, 2000, along with the final one-page punch fist. In the final payment to ASC, MHA deducted liquidated damages in the amount of $22,200 for the 111 days from the contract completion date of April 28, 2000, to August 18, 2000.

[416]*416ASC filed this suit to recover the amount deducted for liquidated damages. In its answer, MHA filed a reconventional demand for damages, costs, and attorney fees for ASC’s alleged failure to fulfill its contractual obligations. A bench trial took place, after which the trial court rendered judgment in favor of ASC upon determining that the work was substantially complete by the contractual deadline. This appeal by MHA followed.

DISCUSSION

MHA asserts that the trial court erred in concluding that substantial completion occurred on April 28, 2000, the contractual deadline, rather than on August 18, 2000, when the certificate for substantial completion was finally issued. MHA also asserts that the trial court failed to address its reconventional demand for damages. MHA argues that the trial court did not consider Duvall’s field reports which show problems and lack of progress over the course of the construction period. MHA also argues that |4the punch lists prepared by Duvall show that significant work remained on the project past the contract completion date. According to MHA, the 111 days it took ASC to complete the punch lists shows that substantial completion was not achieved on April 28, 2000.

ASC contends that the trial court correctly found substantial completion by the contract deadline. According to ASC, the issuance of the punch lists with dollar amounts listed for the items to be addressed indicated that substantial completion had been achieved. Moreover, ASC describes the items on the punch lists as minor and cosmetic in nature. ASC attributes the length of the lists to the number of buildings.

Article 9.8.1 of the General Conditions of the Contract for Construction defines substantial completion as “the stage in the progress of the Work when the Work or designated portion thereof is sufficiently complete in accordance with the Contract Documents so the Owner can occupy or utilize the Work for its intended use.” La. R.S. 38:2241.1 similarly defines substantial completion applicable to public contracts as follows:

“Substantial completion” is defined for the purpose of this Chapter, as the finishing of construction, in accordance with the contract documents as modified by any change orders agreed to by the parties, to the extent that the public entity can use or occupy the public works or use or occupy the specified area of the public works for the use for which it was intended.

The first circuit in O & M Construction, Inc. v. State of Louisiana, Div. of Administration, 576 So.2d 1030 (La. App. 1st Cir.1991), writ denied, 581 So.2d 691 (La. 1991), explained that substantial completion, | ¿referred to also as substantial performance, can result even though deficiencies exist. The extent of the defect or non-performance, the degree to which the purpose of the contract is defeated, the ease of correction, and the use or benefit of the work performed to the owner are all factors that may be considered to determine when substantial completion occurred. The contractor bears the burden of proving substantial completion.

The determination of when substantial completion occurred is a question of fact and is subject to the manifest error standard of review on appeal. Utley-James of Louisiana, Inc. v. State of Louisiana, Div. of Admin., Dept. of Facility Planning & Control, 94,2504 (La.App. 1st Cir.10/6/95), 671 So.2d 473; O & M Construction, Inc., v. State of Louisiana, Div. of Administration, supra.

[417]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
920 So. 2d 413, 2006 La. App. LEXIS 69, 2006 WL 167660, Counsel Stack Legal Research, https://law.counselstack.com/opinion/all-seasons-construction-inc-v-mansfield-housing-authority-lactapp-2006.