Central Electric Co. of Alexandria v. England Economic & Industrial Development District

CourtLouisiana Court of Appeal
DecidedNovember 28, 2012
DocketCA-0012-0302
StatusUnknown

This text of Central Electric Co. of Alexandria v. England Economic & Industrial Development District (Central Electric Co. of Alexandria v. England Economic & Industrial Development District) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Central Electric Co. of Alexandria v. England Economic & Industrial Development District, (La. Ct. App. 2012).

Opinion

STATE OF LOUISIANA

COURT OF APPEAL, THIRD CIRCUIT

(NOT FOR PUBLICATION)

12-302

CENTRAL ELECTRIC COMPANY OF ALEXANDRIA, INC.

VERSUS

ENGLAND ECONOMIC & INDUSTRIAL DEVELPOMENT DISTRICT

********** APPEAL FROM THE NINTH JUDICIAL DISTRICT COURT PARISH OF RAPIDES, DOCKET NO. 210,104 HONORABLE GEORGE C. METOYER, DISTRICT JUDGE **********

SYLVIA R. COOKS JUDGE

**********

Court composed of Judges Sylvia R. Cooks, Marc T. Amy, and Phyllis M. Keaty.

AFFIRMED.

Kracht Frazier Madison, LLP Scott E. Frazier 5149 Bluebonnet Blvd. Baton Rouge, LA 70809 (225) 293-4568 ATTORNEY FOR PLAINTIFF/APPELLANT Central Electric Company of Alexandria, Inc.

Provosty, Sadler, Delauny, Fiorenza & Sobel, APC Ronald J. Fiorenza John D. Ryland Matthew J. Guy P.O. Drawer 1791 Alexandria, LA 71309-1791 (318) 445-3631 ATTORNEY FOR DEFENDANT/APPELLEE England Economic & Industrial Development District

2 Cooks, Judge FACTS AND PROCEDURAL HISTORY

Central Electric Company of Alexandria, Inc. (Central) was the successful

public bidder for an airport electrical construction project at the Alexandria

International Airport in Alexandria, Louisiana in June of 1999. The public bid was

solicited by England Economic & Industrial Development District (EEIDD). URS

Corporation (URS) provided the engineering design and project administration

with Hutchinson & Hutchinson, Professional Engineers (Hutchinson) hired as the

local professional engineer for the project. EEIDD began using the newly

constructed system in June of 2000. URS certified the project as substantially

complete with an effective date of July 28, 2000, after addressing multiple items on

several punch lists submitted by EEIDD. EEIDD has never acknowledged that the

project was substantially complete and refused to sign the certificate prepared by

URS.

The original bid for the project was $737,859.60. Additions and deletions in the

contract, which included the addition of approximately 200,000 feet of new cable

and several line-item credits, resulted in an additional net cost of $13,582.20,

making the final cost of the project $751,441.80. Approximately one year after

URS certified the project as substantially complete, EEIDD made a $500,000.00

payment to Central bringing the total payments made to $650,236.52. At the time

of this sizeable payment, EEIDD had been using the runway daily for over a year.

EEIDD admitted it retained the sum of $36,892.98 to cover disputed claims for

work EEIDD claimed was either not performed in accordance with the contract or

not performed satisfactorily. The total amount remaining unpaid to Central

according to Central‟s calculations is $101,205.28, which it claims include

additional work performed outside the contract requested by EEIDD. Central attempted to satisfy the items listed on multiple punch lists submitted by

EEIDD but eventually became frustrated with the continuing multiple requests for

items they believed went beyond the contracted services. EEIDD continued to

insist that the contract specifications had not been fulfilled and refused to make any

further payments. EEIDD attempted to have more new wire installed at no

additional cost but Central refused to comply with this request for which no change

order was given.

Central filed suit on August 30, 2002, seeking recovery of what it claimed was

the unpaid balance for its work. EEIDD reconvened asserting it was entitled to

damages in an amount equal to the cost of completely redoing the entire original

electrical project. The airport has operated the runway worked on by Central for

over ten years without interruption, fully certified by the FAA (Federal Aviation

Administration), despite the claims made by EEIDD alleging Central‟s work on the

electrical project for this runway was wholly inadequate.

The parties agreed to a bench trial. The trial court ruled from the bench stating:

This court notes and finds that the Plaintiff has failed to prove his claim for unpaid funds for the work done according to the contract. Testimony reveals that the work was lacking in its completeness or compliance with all of the specifications and plans.

The court further notes that the Plaintiff‟s claim for unpaid funds is dismissed.

That the work was substantially completed and that Plaintiffs in Reconvention cannot claim a rebate for work that is still functioning for its intended purpose, even after 10 years later.

Thus, the Plaintiff‟s claim in reconvention is dismissed.

Cost is to be equally split.

LEGAL ANALYSIS

Both parties have appealed. Central asserts the trial court erred as a matter of

law in failing to award damages for additional payments after finding the work was 2 substantially complete, and in finding EEIDD has used the runway for over ten

years without interruption since the date Central completed the work. EEIDD

asserts the trial court manifestly erred in finding the work was substantially

complete, and in failing to award damages for remediation.

Contracts with public entities like EEIDD are subject to the provisions of

LA.R.S. 38:2241.1, which provides in pertinent part:

„Substantial completion‟ is defined for the purpose of this Chapter, as the finishing of construction, in accordance with the contract documents as modified by any change orders agreed to by the parties, to the extent that the public entity can use or occupy the public works or use or occupy the specified area of the public works for the use for which it was intended. The recordation of an acceptance in accordance with the provisions of this Section upon substantial completion shall be effective as an acceptance for all purposes under this Chapter. (emphasis added)

There is no recorded acceptance of this project as EEIDD refused to sign such

an acceptance. The determination of whether there has been “substantial

completion” on a public works project, as defined in La.R.S. 38:2241.1, is a

question of fact left to the broad discretion of the trier of fact and will not be

disturbed on appeal absent manifest error. See Ortego v. Dupont, 611 So.2d 792

(La.App. 3 Cir. 1992).

Factual determinations in civil cases are reviewed under the manifest error-clearly wrong standard of review. Rando v. Anco Insulations, Inc., 08-1163, 08-1169 (La.5/22/09), 16 So.3d 1065. This standard „precludes the setting aside of the [trial] court‟s finding of fact unless that finding is clearly wrong in light of the record reviewed in its entirety.‟ Id. at 1087.

Review of credibility determinations under the manifest error standard requires that where there is conflict in the testimony, reasonable evaluations of credibility and reasonable inferences of fact should not be disturbed upon review, even though the appellate court may feel that its own evaluations and inferences are as reasonable. Hebert v. Rapides Parish Police Jury, 06-2001, 06-2164 (La.4/11/07), 974 So.2d 635. Unless documents or objective evidence so contradict the witness‟s story or the story itself is so internally inconsistent or implausible on its face that a reasonable fact finder would not credit the witness‟s story, a fact finder‟s determination that is based on a 3 credibility determination can virtually never be manifestly erroneous or clearly wrong. Rosell v. ESCO, 549 So.2d 840 (La. 1989).

Hannie v. Guidry, 10-216, pp. 9-10 (La.App. 3 Cir. 10/6/10), 48 So. 3d 396, 403.

In Gala v. Harris, 11-654, p. 3, (La.App. 3 Cir.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rando v. Anco Insulations Inc.
16 So. 3d 1065 (Supreme Court of Louisiana, 2009)
Walter Lafargue Real Estate, Inc. v. Raines
420 So. 2d 1309 (Louisiana Court of Appeal, 1982)
Hebert v. Rapides Parish Police Jury
974 So. 2d 635 (Supreme Court of Louisiana, 2008)
Rosell v. Esco
549 So. 2d 840 (Supreme Court of Louisiana, 1989)
Ortego v. Dupont
611 So. 2d 792 (Louisiana Court of Appeal, 1992)
Hannie v. Guidry
48 So. 3d 396 (Louisiana Court of Appeal, 2010)
Gala v. Harris
77 So. 3d 1065 (Louisiana Court of Appeal, 2011)
Boydstun v. Johnson
401 So. 2d 629 (Louisiana Court of Appeal, 1981)
All Seasons Construction, Inc. v. Mansfield Housing Authority
920 So. 2d 413 (Louisiana Court of Appeal, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
Central Electric Co. of Alexandria v. England Economic & Industrial Development District, Counsel Stack Legal Research, https://law.counselstack.com/opinion/central-electric-co-of-alexandria-v-england-economic-industrial-lactapp-2012.