E. Smith Plumbing, Inc. v. Manuel

88 So. 3d 1209, 11 La.App. 3 Cir. 1277, 2012 WL 1020130, 2012 La. App. LEXIS 414
CourtLouisiana Court of Appeal
DecidedMarch 28, 2012
DocketNos. 11-1277, 11-1278, 11-1279
StatusPublished
Cited by3 cases

This text of 88 So. 3d 1209 (E. Smith Plumbing, Inc. v. Manuel) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
E. Smith Plumbing, Inc. v. Manuel, 88 So. 3d 1209, 11 La.App. 3 Cir. 1277, 2012 WL 1020130, 2012 La. App. LEXIS 414 (La. Ct. App. 2012).

Opinion

COOKS, Judge.

bFACTS AND PROCEDURAL HISTORY

Joshua Paul Manuel (Joshua) and Cora Elizabeth Monier Manuel (Cora) engaged the services of Drake Fontenot (Fontenot) to build a home in Evangeline Parish, Louisiana. Fontenot was hired to build Joshua and Cora’s residence on the basis of his reputation as a home builder in their area and based upon his bid proposal. Fonte-not submitted a contract to Joshua and Cora, but neither one of them signed the contract. Cora made changes to lower the overall cost of the project and discussed these changes with Fontenot. Fontenot agreed to proceed under the revised figures and commenced the building of Joshua and Cora’s home.

Cora handled the negotiations with Fon-tenot, and she worked directly with him and various subcontractors throughout the construction of their home. Joshua had little direct involvement in the day-to-day dealings with Fontenot or any of the subcontractors. Cora handled the financial record keeping and the delivery of payments to Fontenot and others involved in the construction of their home.

Throughout the project, and to its completion, Fontenot charged Joshua and Cora for carpenter labor, which included himself, his workers, a per-hour fee for [1212]*1212each worker as part of Fontenot’s fee, and for the cost of materials purchased by him. Fontenot did not add any amount to materials he purchased for the project nor did he add any amount to any of the subcontractors’ bills for their labor and materials. This was true for all subcontractors, including the Plaintiffs. The three Plaintiff/Subcontractors sent invoices to Fonte-not indicating he was the contractor on the job building Joshua and Cora’s home. Cora usually made payments to Fontenot when requested throughout the project to pay him, his workers, and subcontractors, and, on some occasions, paid certain subcontractors directly.

|2The three Plaintiffs/Subcontractors herein all provided materials and/or services in the construction of Joshua and Cora’s home. All three Plaintiffs had a long-standing relationship with Fontenot as a general contractor building homes in their area. Fontenot chose each of the Plaintiffs/Subcontractors to perform work on Joshua and Cora’s home. Each testified that they entered into agreement with Fontenot to provide their respective services as subcontractors relying on their past experience with Fontenot. None of the parties had any contractual agreement directly with Joshua or Cora. After completing work on Joshua and Cora’s home each of the Plaintiffs were left with an outstanding balance owed for services and/or materials provided.

All parties stipulated to the amount owed each of the three Plaintiffs. Joshua and Cora do not dispute that the Plaintiffs actually performed the work for which they invoiced Fontenot, and they do not assert that any of the Plaintiffs’ work was improperly done. Joshua and Cora further acknowledged that these subcontractors have not been paid the outstanding balances claimed. Joshua and Cora maintain they held back the money owed to Plaintiffs, at the end of the project, because they believe Fontenot overcharged them for his labor. They assert they feared if they paid the amount owed to Plaintiffs directly to Fontenot he would not pay these subcontractors because he claimed he was owed additional money on the project for his labor, and had an outstanding bill for his unpaid labor. Cora represented to Plaintiffs, and maintained both before and during trial, that she and her husband owed each of the Plaintiffs for their outstanding bills and promised these debts would be paid.

Joshua and Cora moved into their new home on July 25, 2009. E. Smith Plumbing, Inc. (Smith Plumbing) submitted a letter into evidence informing Joshua hand Cora that they owed $18,556.00, and if it remained unpaid a lien would be filed on “October 1st.” Smith Plumbing filed a lien in Evangeline Parish on October 2, 2009, and Smith Air Conditioning, Inc. (Smith A.C.) filed a lien in Evangeline Parish on October 5, 2009. Smith A.C. and Smith Plumbing thereafter sent a certified letter to Joshua and Cora, return receipt requested, dated October 14, 2009. This letter informed Joshua and Cora that the liens had been filed, and also stated that the letter should be considered a written demand for payment in the amount of $7,618.00 for Smith A.C., and $18,566.00 for Smith Plumbing. A copy of the letter was sent to Fontenot. The third Plaintiff, Ville Platte Concrete Service, Inc. (Concrete Service) did not file a lien though their bill was not paid.

Smith A.C. and Smith Plumbing filed suit against Joshua, Cora, and Fontenot in December, 2009, for the amounts owed, plus attorney fees and legal interest from date of judicial demand. Both of these Plaintiffs alleged in their suits “some of the balance due is an open account owed by the Manuel’s (Joshua and Cora), with a [1213]*1213portion being contractual and being owed by Drake Fontenot.” The petition does not allege what portion is owed by each of the named parties. Joshua and Cora filed a third-party demand against Fontenot, alleging Fontenot overcharged them in the amount of $20,595.00 and alleging that they “paid Drake Fontenot over $300,000.00 and he should have paid the plaintiff[s] in full from the money he received.” The total bid price for the job was $327,151.00.

Joshua and Cora also filed a reconven-tional demand against Smith A.C. and Smith Plumbing for damages and attorney fees for improperly filing liens and refusing to cancel the liens after written request to cancel within ten days of the notice.

|4Concrete Service sent a demand letter to Joshua and Cora dated February 4, 2010, return receipt requested, stating it was owed “on an open account” the sum of $7,030.50. The demand letter was addressed to Fontenot, Joshua, and Cora. Because the amount went unpaid, Concrete Service filed a suit on open account on March 5, 2010, against Joshua, Cora, and Fontenot. Joshua and Cora filed a third party demand against Fontenot alleging he was the general contractor, and that if they owed Concrete Service any sum they were entitled to indemnity by Fontenot for any such amount.

By letter dated April 27, 2010, Joshua and Cora’s attorney informed Plaintiffs’ attorney that the liens were improperly filed and requested the hens be cancelled “within ten days” failing which, Joshua and Cora would sue Plaintiffs for damages and attorney fees. The liens were not can-celled until September 28, 2010.

Following a bench trial, the trial court rendered judgment in favor of the Plaintiffs awarding each the stipulated amount owed on open account; attorney fees for each in the amount of $2,500.00; all costs of court; and legal interest from date of judicial demand. This part of the judgment was against Joshua and Cora. The trial court dismissed all of Joshua and Cora’s reconventional and third-party demands at their cost. The trial court thereafter signed an amended judgment which dismissed: all claims by Plaintiffs against Drake Fontenot; Joshua and Cora’s third-party demands against Drake Fontenot; and Drake Fontenot’s reconventional demand against Joshua and Cora. Joshua and Cora appeal the original judgment of the trial court and expressly state in their brief to this court that they have not appealed the amended judgment. No other parties have answered the appeal nor have they appealed the judgment or amended judgment. Therefore, the amended judgment is final. Thus, the third-party demands by | r,Joshua and Cora against Fon-tenot, and all of the Plaintiffs’ claims against Fontenot are dismissed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Accusess Environmental, Inc. v. Walker
185 So. 3d 69 (Louisiana Court of Appeal, 2015)
Urban's Ceramic Tile, Inc. v. McLain
113 So. 3d 477 (Louisiana Court of Appeal, 2013)
Kaylin Renee Celestine, Etc. v. Brenda Dugas
Louisiana Court of Appeal, 2013

Cite This Page — Counsel Stack

Bluebook (online)
88 So. 3d 1209, 11 La.App. 3 Cir. 1277, 2012 WL 1020130, 2012 La. App. LEXIS 414, Counsel Stack Legal Research, https://law.counselstack.com/opinion/e-smith-plumbing-inc-v-manuel-lactapp-2012.