Urata & Sons Concrete, Inc. v. Gilbane Federal

CourtDistrict Court, E.D. California
DecidedNovember 6, 2019
Docket2:17-cv-02635
StatusUnknown

This text of Urata & Sons Concrete, Inc. v. Gilbane Federal (Urata & Sons Concrete, Inc. v. Gilbane Federal) is published on Counsel Stack Legal Research, covering District Court, E.D. California primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Urata & Sons Concrete, Inc. v. Gilbane Federal, (E.D. Cal. 2019).

Opinion

1 2 3 4 5 6 7 8 UNITED STATES DISTRICT COURT 9 EASTERN DISTRICT OF CALIFORNIA 10 11 UNITED STATES OF AMERICA for the No. 2:17-cv-02635-MCE-AC Use and Benefit of URATA & SONS 12 CONCRETE, INC., 13 Use-Plaintiff / Plaintiff, MEMORANDUM AND ORDER 14 v. 15 GILBANE FEDERAL, a California corporation; and TRAVELERS 16 CASUALTY AND SURETY COMPANY OF AMERICA, a Connecticut 17 corporation, 18 Defendants. 19 20 Through this action, the United States of America for the Use and Benefit of Urata 21 & Sons Concrete, Inc., and Urata & Sons Concrete Inc. (“Plaintiff”) seek confirmation 22 and enforcement of an arbitration award against Defendants Gilbane Federal (“Gilbane”) 23 and Travelers Casualty and Surety Company of America (collectively, “Defendants”). 24 Presently before the Court is Plaintiff’s Motion for Order Lifting Stay, Confirming Final 25 Arbitration, and Entry of Judgment. ECF No. 15. Plaintiff also moves for attorney’s fees 26 and costs. Concurrently before the Court is Defendants’ Counter-Motion to Vacate 27 /// 28 /// 1 Arbitration Award. ECF No. 17. For the reasons set forth below, Plaintiff’s Motion is 2 GRANTED and Defendants’ Counter-Motion is DENIED.1 3 4 BACKGROUND2 5 6 In 2014, Gilbane entered into a written design-build construction contract with the 7 United States Army Corps of Engineers (“USACE”) for the construction of a general 8 purpose warehouse at the Defense Distribution Depot in Tracy, California (the “Project”). 9 In May 2015, Plaintiff and Gilbane entered into a written subcontract whereby Plaintiff 10 agreed to provide and install specific concrete work according to Gilbane’s plans and 11 specifications (the “Subcontract”). The Subcontract further provided that Plaintiff “shall 12 perform all Work required to complete the Project in strict accordance with the 13 [Statement of Work documents]” and that Plaintiff “agrees to be fully bound by all 14 [Statement of Work] Documents to be later provided.” Ex. 1, ECF No. 1, at 15. The 15 original Project specifications did not require the use of air entrained concrete. After the 16 Subcontract was executed, Gilbane provided Plaintiff with revised specifications, which 17 were changed to require air entrained concrete. At the same time, a note was included 18 stating that “[e]ntrained air should not be used for concrete to be given a smooth, dense, 19 hard-troweled finish because blistering and delamination may occur.” In December 20 2015, Gilbane provided Plaintiff with its Issued for Construction (“IFC”) specifications, 21 which required Plaintiff to install the warehouse slab on grade with a “smooth, dense 22 hard-trowel finish, along with the placement of air entrained concrete,” thus creating a 23 design conflict. See Arbitration Award, ECF No. 15-2, at 20. 24 /// 25 /// 26 1 Having determined that oral argument would not be of material assistance, the Court ordered this 27 matter submitted on the briefs in accordance with E.D. Local Rule 230(g).

28 2 The following statement of facts is taken, sometimes verbatim, from the Complaint. ECF No. 1. 1 In March 2016, Plaintiff submitted air entrained concrete mix designs to Gilbane, 2 who approved those designs for use in areas with a hard trowel finish such as the 3 warehouse slab on grade. Plaintiff notified Gilbane of additional costs associated with 4 the changed concrete specifications, and alerted Gilbane to the design conflict between 5 the requirements for air entrained concrete and the hard trowel finish, which Gilbane 6 acknowledged. Gilbane communicated with USACE about removing air entrainment 7 from the concrete mix design. See Arbitration Award, ECF No. 15-2, at 9. 8 In August 2016, Plaintiff and Gilbane executed Change Order No. 1 to the 9 Subcontract, which included the increased cost for air entrained concrete in the areas 10 that did not require a hard trowel finish. Based on their prior discussions and written 11 memorialization, Plaintiff and Gilbane excluded from Change Order No. 1 the cost for the 12 air entrained concrete in the warehouse slab on grade, reserving the issue for future 13 adjustment if the specification requirement was not changed by USACE. 14 Plaintiff was scheduled to perform its concrete work from December 2016 to 15 February 2017. Having not received any notice or revisions to the specifications that 16 deleted the air entrainment requirement from the warehouse slab on grade, Plaintiff 17 began performing its work in accordance with the specifications, including those 18 requiring the use of air entrained concrete with a hard trowel finish for the warehouse 19 slab on grade. Gilbane was responsible for quality control on the Project and was fully 20 aware that Plaintiff was placing the warehouse slab on grade in accordance with the 21 specifications and the approved mix design and participated in that placement by, 22 among other things, testing the concrete at the time of delivery for compliance with the 23 approved mix design and signing off on the placement of the concrete for the warehouse 24 slab on grade. After completion, Plaintiff billed Gilbane for this concrete installation, and 25 Gilbane paid Plaintiff for its work, excluding retention. 26 It was not until after work under the Subcontract was complete that Plaintiff 27 learned USACE actually approved a design change deleting the air entrainment from the 28 warehouse slab on grade prior to the execution of Change Order No. 1; Gilbane never 1 conveyed or provided any such approval or design change to Plaintiff in any form. 2 Further, USACE alerted Gilbane to the occurrence of delamination of the warehouse 3 slab on grade due to the air entrainment. Gilbane issued cure notices to Plaintiff, stating 4 the delamination resulted from Plaintiff’s unauthorized use of air entrained concrete for 5 the warehouse slab on grade and Plaintiff must remedy its non-compliance by replacing 6 the entire warehouse slab on grade. Plaintiff denied responsibility for the issues, and 7 Gilbane refused to pay Plaintiff amounts due for work completed. 8 On December 18, 2017, Plaintiff filed this action against Defendants for, among 9 other things, breach of contract and Miller Act violations. ECF No. 1. Subsequently, this 10 Court entered an order staying the action pending arbitration, pursuant to the parties’ 11 stipulation. ECF No. 8. Kenneth C. Gibbs (the “Arbitrator”) served as the arbitrator for 12 this dispute, and arbitration took place on November 12-14, 2018. ECF No. 15-1. On 13 March 21, 2019, the Arbitrator issued the Final Award (the “Award”), which concluded 14 that Plaintiff’s installation of the air entrained concrete constituted performance, or, 15 alternatively, that Plaintiff was excused from performing under the Subcontract. See 16 Arbitration Award, ECF No. 15-2, at 19-24. Plaintiff was awarded the sum of 17 $2,669,018.13, which consisted of: (1) the principal amount of $2,097,055.00; 18 (2) interest of $311,906.53 at the per annum rate of 10%, equivalent to a daily rate of 19 $574.54; (3) costs of $94,959.60; and (4) attorneys’ fees pursuant to the Subcontract in 20 the amount of $165,097.00. Id. at 33. 21 22 STANDARD 23 24 It is well established that a federal court’s review of an arbitrator’s decision is 25 “extremely narrow.” Stead Motors v. Auto. Machinists Lodge, 886 F.2d 1200, 1208 n.2 26 (9th Cir. 1990) (emphasis in original), cert. denied, 495 U.S. 946. Courts may vacate an 27 arbitration decision if the “arbitrators exceeded their powers.” 9 U.S.C. § 10(a)(4) 28 (2006). “Arbitrators exceed their powers . . . not when they merely interpret or apply the 1 governing law incorrectly, but when the award is completely irrational, or exhibits a 2 manifest disregard of the law.” Schoenduve Corp. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Urata & Sons Concrete, Inc. v. Gilbane Federal, Counsel Stack Legal Research, https://law.counselstack.com/opinion/urata-sons-concrete-inc-v-gilbane-federal-caed-2019.