University of Louisiana Monroe Facilities, Inc. v. JPI Apartment Development, L.P.

151 So. 3d 126, 2014 La. App. LEXIS 2417, 2014 WL 5002182
CourtLouisiana Court of Appeal
DecidedOctober 8, 2014
DocketNos. 49,148-CW, 49,156-CW, 49,307-CA
StatusPublished
Cited by5 cases

This text of 151 So. 3d 126 (University of Louisiana Monroe Facilities, Inc. v. JPI Apartment Development, L.P.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
University of Louisiana Monroe Facilities, Inc. v. JPI Apartment Development, L.P., 151 So. 3d 126, 2014 La. App. LEXIS 2417, 2014 WL 5002182 (La. Ct. App. 2014).

Opinion

MOORE, J.

Lin these consolidated cases, University of Louisiana Monroe Facilities Inc. (“ULMFI”) appeals a judgment dismissing its claim against Continental Casualty Company (“Continental”), the issuer of a performance bond, on Continental’s exception of prescription; ULMFI seeks supervisory review of a ruling denying its motion to compel arbitration of claims; and several defendants (collectively, “the roofing contractors”) seek supervisory review of a judgment denying their exceptions of insufficient service and citation, lack of procedural capacity, no right of action and prescription. For the reasons expressed, we affirm the judgment that granted Continental’s exception of prescription on the performance bond; we grant ULMFI’s writ application, make it peremptory, and remand the case to the district court to order arbitration of claims; and grant the roofing contractors’ writ application and remand to the district court to refer their exceptions to arbitration.

Factual and Procedural Background

In 2004, ULMFI, as owner, executed a $21 million design/build contract with JPI Apartment Development LP (“JPI”), as general contractor, to renovate nearly 500 dorm rooms, demolish two dorm buildings, and build six new apartment-style buildings and a new student health center on the ULM campus. The design/build contract contained an arbitration clause 1|2and [128]*128required the general contractor to have a performance bond.2 JPI bought a performance bond from Continental with a two-year claims limit.3 JPI hired a number of subcontractors, including Central Roofing Inc. (“CRI”). The standard-form subcontract with CRI also included an arbitration clause.4

Construction of Phase 1 was completed in July 2006; Phase 2 was completed in December 2007. During this time, CRI merged into a different entity, Central Roofing LLC (“CRLLC”); in October 2008, CRLLC changed its name to West Monroe Roofing LLC (“WMR”); and WMR formally dissolved on June 22, 2009.

Also in 2009, ULM personnel began to notice “water intrusion” that was causing structural and external damage to the new buildings. An inspection showed that the roof, stucco, walls and flooring deviated from the contract specifications and industry standards. Filings in this record show that in April 2010, ULMFI began emailing JPI to request mediation or arbitration of these claims, but by then JPI had collapsed, was merely wrapping up creditors’ claims, had no reserves to defend ULM-FI’s claim or |spay a judgment, and thus it would not participate in arbitration.5

ULMFI filed this suit on November 26, 2011, naming JPI and its unknown insurer as defendants. The petition alleged that the general contract provided for mediation or arbitration; “however, when ULM-FI attempted to resolve this issue through mediation/arbitration, JPI refused to participate. As such, the arbitration provision is deemed waived and the instant lawsuit is procedurally proper.” By amended petition, ULMFI joined as defendants Continental, which had issued JPI’s performance bond, and CRI. By subsequent amendments, ULMFI also joined as defendants CRI’s successor entities, CRLLC and WMR (“the roofing contractors”), and their liability insurers.6

Continental filed a peremptory exception of prescription, asserting the two-year claims limit in its performance bond. It alleged that work was completed in De[129]*129cember 2007, but ULMFI did not file suit until October 2011 or join Continental on the performance bond until March 2012. ULMFI countered that the bond contained an illegal attempt to shorten the statutory prescriptive period.

The roofing contractors filed exceptions of insufficient service and citation, lack of procedural capacity and no right of action. They showed that ULMFI never effected service on CRI or CRLLC; it served WMR | /‘through Mary McLaughlin, its agent for service,” but by that time, WMR had officially dissolved; also by that time, all the roofing contractors were out of existence, so they had no procedural capacity to be sued. They argued that because the entities are extinct, ULMFI had no right of action to sue them. Continental, as WMR’s liability carrier, later filed an exception of prescription, urging that after WMR’s dissolution on July 22, 2009, ULMFI had exactly three years to file suit, under La. R.S. 12:1338 D; since ULMFI did not join WMR until August 8, 2012, its action was prescribed.

On July 26, 2013, the roofing contractors applied for a temporary restraining order to enjoin ULMFI from seeking arbitration. They conceded that JPI’s general contract and CRI’s subcontract both called for arbitration of claims, but argued that ULMFI had no “privity of contract” with them. They also argued that ULMFI judicially confessed a waiver of arbitration in its original and amended petitions. The court granted the TRO; it was extended and remained in effect until the hearing.

On August 9, 2013, ULMFI filed the instant motion to compel arbitration and stay litigation. It argued that the only reason it “deemed” arbitration waived was that JPI was defunct and refused to participate, but that there was no intent to waive arbitration. It also argued that all subcontractors were bound to arbitration.

Action of the District Court

At a hearing on October 22, 2013, the court heard Continental’s exception of prescription. The court applied the two-year claims limit in the .performance bond, sustaining the exception without reasons. ULMFI has 1 ¿appealed this judgment (No. 49,307-CA).

At a hearing on October 25, 2013, the court heard all the remaining exceptions and ULMFI’s motion to compel arbitration. Although the court initially stated, “It’s clear to me there is some agreement to arbitrate here,” it then accepted the roofing contractors’ argument that the subcontract did not define “owner” to be ULMFI: “I find your argument convincing. * * * I’m walking in and reverse [sic] myself.” The court denied the motion to compel arbitration, and ULMFI took a writ to challenge this (No. 49,156-CW). Without stating reasons, the court also denied all exceptions. The roofing contractors and their liability carriers took a writ to challenge this (No. 49,148-CW).

This court granted the writ applications and ordered them consolidated with the appeal on February 27, 2014.

Discussion: Two-Year Limitation on Performance Bond

By its appeal, ULMFI urges the court erred in applying the two-year claims limit stated in the performance bond instead of the standard 10-year limit for personal actions stated in La. C.C. art. .3499. It shows that a juridical act cannot make “the requirements of prescription more onerous,” La. C.C. art. 3471, and contends that shortening the prescriptive period is a nullity. Cameron v. Bruce, 42,873 (La.App. 2 Cir. 4/23/08), 981 So.2d 204, unit denied, 2008-1127 (La.9/19/08), 992 So.2d 940; Prestridge v. Bank of Jena, 05-545 (La.App. 3 Cir. 3/8/06), 924 So.2d 1266, writ denied, 2006-0836 (La.6/2/06), 929 So.2d [130]*1301261. It also contends that La. C.C. art. 3040, which permits a surety agreement to be “qualified, conditioned, or | limited in any lawful manner,” does not exempt sureties from Art. 3471, and that cases appearing to do so are unpersuasive because they do not mention Art. 3471. Finally, it urges the theory of contra non valentem

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Traders' Mart, Inc. v. AOS, Inc.
268 So. 3d 420 (Louisiana Court of Appeal, 2019)
Law Enforcement District of Jefferson Parish v. Mapp Construction, LLC
196 So. 3d 896 (Louisiana Court of Appeal, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
151 So. 3d 126, 2014 La. App. LEXIS 2417, 2014 WL 5002182, Counsel Stack Legal Research, https://law.counselstack.com/opinion/university-of-louisiana-monroe-facilities-inc-v-jpi-apartment-lactapp-2014.