University Commons-Urbana, Ltd. v. Universal Constructors, Inc.

301 F. Supp. 2d 1297, 2004 U.S. Dist. LEXIS 1794, 2004 WL 237723
CourtDistrict Court, N.D. Alabama
DecidedFebruary 5, 2004
DocketCIV.A. CV99AR1992S, CIV.A. CV00AR3149S
StatusPublished

This text of 301 F. Supp. 2d 1297 (University Commons-Urbana, Ltd. v. Universal Constructors, Inc.) is published on Counsel Stack Legal Research, covering District Court, N.D. Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
University Commons-Urbana, Ltd. v. Universal Constructors, Inc., 301 F. Supp. 2d 1297, 2004 U.S. Dist. LEXIS 1794, 2004 WL 237723 (N.D. Ala. 2004).

Opinion

MEMORANDUM OPINION

ACKER, District Judge.

The factual disputes presented by the above two consolidated cases were submitted to an advisory jury on January 29, 2004, after a five day trial. The first filed case was entitled University Commons-Urbana, Ltd. (“University Commons”) and Capstone Development Corporation (“Capstone Development”) v. Universal Constructors, Inc. (“Universal Constructors”) and Reliance Insurance Company (“Reliance”), CV-99-AR-1992-S. It was filed originally in this court on July 30, 1999, and was assigned to the Honorable Sam C. Pointer, Jr. Plaintiffs, as owners of a student apartment project at the University of Illinois, sought damages from defendants, the general contractor and its performance bonding company, for the alleged breach of the construction contract. When an arbitration clause in the contract was invoked by defendants, preempting the jurisdiction of this court, Judge Pointer stayed the case pending arbitration. His order concluded as follows:

The Court retains jurisdiction for the purpose of confirming any arbitration award. This case, although stayed, is administratively terminated, and the stay can be lifted and the case brought to the active calendar of the Court upon motion of any of the parties.

There was no taxation of costs.

For reasons unknown to this court, the dispute was not arbitrated in Birmingham, Alabama, but in Atlanta, Georgia, before a panel of three arbitrators who were selected and who operated under the auspices of the American Arbitration Association. On August 17, 2000, after nineteen days of hearings, broken into three sessions, the three arbitrators unanimously entered an award in the amount of $2,248,648, plus interest at 12% per annum from August 15, 2000, in favor of the owners and against the general contractor and its bonding company. The owners thereupon asked this court to reactivate CV-99-AR-1992-S and to confirm and enforce the award. Contemporaneously, Universal Constructors, the contractor, and Reliance, its bonding company, filed a separate suit in the United States District Court for the Northern District of Georgia, the district in which the arbitration award had been entered. They invoked 9 U.S.C. § 10, attacking the award as having been tainted by the “evident partiality” of Edward Meyerson (“Meyerson”), one of the three arbitrators. The district court in Atlanta transferred that case to this court. The transferred case, styled Universal Constructors, Inc. and Reliance Insurance Company v. University Commons-Urbana, Ltd. and Capstone Development Corporation, CV-00-AR-3149-S, was consolidated with CV-99-AR-1992-S, and both cases were assigned to the undersigned.

Without allowing the extensive discovery sought by the contractor and its bonding company, and without holding a full scaled *1299 evidentiary hearing, this court confirmed the arbitration award, whereupon the contractor and bonding company appealed.

In University Commons-Urbana, Ltd. v. Universal Constructors, Inc., 304 F.3d 1331 (11th Cir.2002), the Court of Appeals for the Eleventh Circuit reversed this court and remanded the case for the evi-dentiary hearing deemed necessary for arriving at a final answer to the charge by Universal Constructors and Reliance, using the critical words of 9 U.S.C. § 10(a)(2), that “there was evident partiality or corruption in the arbitrators, or either [sic] of them.” Universal Constructors and Reliance did not charge “corruption,” limiting themselves to a single statutory ground for setting aside the award, namely, that Meyerson was guilty of “evident partiality.” The opinion of the Eleventh Circuit contains a more complete procedural history than is recited herein. It sets forth enough undisputed and disputed facts to provide a full background for the controversy. It also, of course, provides the Eleventh Circuit’s rationale for requiring an evidentiary hearing.

After the remand, discovery was reopened, and rather lengthy and contentious discovery ensued. Universal Constructors and Reliance belatedly demanded a jury trial. The court declined to grant a dispositive trial by jury. Instead, the court, in an exercise of its discretion under Rule 39(c), F.R.Civ.P., ordered that an advisory jury be empaneled.

Because Universal Constructors and Reliance conceded that the burden of proof was theirs, they were designated for trial purposes as “plaintiffs”, and University Commons and Capstone Development were designated as “defendants.” At the conclusion of plaintiffs’ evidence, defendants offered a motion of judgment as a matter of law, invoking alternatively, Rule 50(a) and Rule 52(c), F.R.Civ.P., the former applying to jury trials and the latter applying to non-jury trials. A trial with an advisory jury is somewhere in between. The court took the motion under advisement. At the conclusion of all of the evidence, both defendants and plaintiffs made motions for judgment as a matter of law, and the court also took them under advisement. After closing arguments and the court’s charge to the jury, the court submitted tp the jury the following three special interrogatories, to which the jury gave the answers hereinafter reflected:

1. Did .Universal Constructors, Inc. and Reliance Insurance Company prove by a preponderance of the evidence that Edward Meyerson, while acting as an arbitrator in the arbitration, proceeding involving the .dispute with University Commons-Urbana, Ltd. and Capstone Development Corporation, was aware of facts comprising, one or more potential conflicts?
YES_ NO _JL_
2. ONLY IF THE JURY HAS ANSWERED ‘YES” TO QUESTION NO. 1,
did Universal Constructors, Inc. and Reliance Insurance Company prove by a preponderance' of the evidence that the potential conflict or conflicts found to have existed by you in answer to Question No. 1 was or were of the kind that a reasonable person would recognize as a potential conflict?
YES_. NO__
3. ONLY IF THE JURY HAS ANSWERED' “YES” TO QUESTIONS •NO. 1 AND NO. 2,
did Universal Constructors, Inc. and Reliance Insurance Company prove by a preponderance of the evidence that Mr. Meyerson failed, to timely disclose enough information for a reasonable person to realize that a potential conflict or conflicts existed?
*1300 YES_ NO_

These three interrogatories were lifted virtually verbatim from the following expression in the Eleventh Circuit opinion found at 304 F.3d at 1341:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
301 F. Supp. 2d 1297, 2004 U.S. Dist. LEXIS 1794, 2004 WL 237723, Counsel Stack Legal Research, https://law.counselstack.com/opinion/university-commons-urbana-ltd-v-universal-constructors-inc-alnd-2004.