Unity School District v. Vaughn Associates, Inc.

CourtDistrict Court, D. New Hampshire
DecidedNovember 19, 2019
Docket1:15-cv-00155
StatusUnknown

This text of Unity School District v. Vaughn Associates, Inc. (Unity School District v. Vaughn Associates, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. New Hampshire primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Unity School District v. Vaughn Associates, Inc., (D.N.H. 2019).

Opinion

UNITED STATES DISTRICT COURT

DISTRICT OF NEW HAMPSHIRE

Unity School District, Plaintiff

v. Case No. 15-cv-155-SM Opinion No. 2019 DNH 195 Vaughn Associates, Inc., and Scott Vaughn, Defendants

v.

School Administrative Unit #6, Excel Mechanical, Inc., Superior Walls of Hudson Valley, Inc., and Town of Unity, Third-Party Defendants

O R D E R

In 2010, the Unity School District hired Vaughn Associates and Scott Vaughn (collectively, “Vaughn”) to design and oversee construction of a new elementary school in Unity, New Hampshire. The project did not proceed as the School District had envisioned. Construction was beset with delays and forced work stoppages (by, for example, the state fire marshal) and costs ballooned from the $4.7 million that Vaughn had promised to more than $9 million. Eventually, Vaughn’s contracts with the School District were terminated and the School District sued Vaughn for damages. Those claims were settled and, in April of 2017, the School District’s suit against Vaughn was dismissed, by agreement of the parties. See Stipulation of Dismissal (document no. 100).

What remain are Vaughn’s third-party claims against two subcontractors on the project: Excel Mechanical, Inc., and Superior Walls of the Hudson Valley, Inc. Pending before the court is Excel Mechanical’s motion for summary judgment, in which Excel asserts that it is entitled to judgment as a matter of law as to each of the three state law claims Vaughn advances against it. Vaughn objects.

For the reasons discussed, Excel’s motion for summary judgment is granted.

Standard of Review When ruling on a motion for summary judgment, the court is “obliged to review the record in the light most favorable to the nonmoving party, and to draw all reasonable inferences in the nonmoving party’s favor.” Block Island Fishing, Inc. v. Rogers, 844 F.3d 358, 360 (1st Cir. 2016) (citation omitted). Summary judgment is appropriate when the record reveals “no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.” Fed. R. Civ. P. 56(a). In this context, a factual dispute “is ‘genuine’ if the evidence of record permits a rational factfinder to resolve it in favor of either party, and ‘material’ if its existence or nonexistence

has the potential to change the outcome of the suit.” Rando v. Leonard, 826 F.3d 553, 556 (1st Cir. 2016) (citation omitted). Consequently, “[a]s to issues on which the party opposing summary judgment would bear the burden of proof at trial, that party may not simply rely on the absence of evidence but, rather, must point to definite and competent evidence showing the existence of a genuine issue of material fact.” Perez v. Lorraine Enters., 769 F.3d 23, 29–30 (1st Cir. 2014). In other words, “a laundry list of possibilities and hypotheticals” and “[s]peculation about mere possibilities, without more, is not enough to stave off summary judgment.” Tobin v. Fed. Express Corp., 775 F.3d 448, 451–52 (1st Cir. 2014). See generally

Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 249 (1986).

Background The factual background of this case has been set forth in prior orders of the court. See, e.g., Order on Third-Party Defendants’ Motion to Dismiss (document no. 42); Order on Defendants’ Motion for Summary Judgment (document no. 55). It need not be recounted again in detail. It is sufficient to note the following. In 2010, the Unity School District entered into two contracts with Vaughn to design and oversee construction of a new elementary school. Construction began in late 2011. Then, in August of 2012, the Unity School District hired Excel

Mechanical to perform rough and finish plumbing services. On the same date, the School District entered into a separate contract with William Knight, d/b/a LSE (“LSE”), to perform HVAC and mechanical work on the project. LSE, in turn, entered into a subcontract with Excel to provide “design drawings with engineer’s stamp for both plumbing and mechanical.”

The upshot of all of this is the following: Vaughn had two contracts with the Unity School District. It did not, however, have any contractual relationship with Excel; Excel’s contracts were with the School District itself, and with LSE. Moreover, Excel’s contractual obligation to provide mechanical drawings

stamped by a licensed engineer - the critical element of Vaughn’s claims - ran to LSE, not Vaughn. See AIA Standard Agreement between Contractor and Subcontractor (document no. 139-7) at Article 8, and “Notes and Clarifications” to Contract (document no. 139-8) at 3.

In its third-party complaint, Vaughn alleges that it sustained compensable damages when it relied, both reasonably and to its detriment, upon allegedly false and material misstatements made by Excel concerning the presence of an in- house mechanical engineer. Specifically, Vaughn alleges:

Excel represented to VAI [Vaughn] that it had a mechanical engineer who could complete the mechanical components of design and construction drawings.

Excel did not, in fact, have a mechanical engineer who fulfilled this role.

Excel’s purported engineering documents were produced in house by an unregistered engineering school graduate and then stamped by a licensed engineer who was not principally responsible for production of the engineering documents.

Excel knew or should have known that its representations were false when made.

Excel had a duty to VAI as agent for USD to be truthful in describing the scope of its abilities.

Excel made the representations in an effort to convince VAI to recommend that USD use Excel as the mechanical contractor on the project.

The representations were material.

VAI relied on the representations of Excel in recommending their use on the project and in not partnering with a separate mechanical engineer.

Excel’s failure to provide accurate stamped engineering drawings and/or to have a mechanical engineer on staff caused significant delays and costs on the project including but not limited to shutdowns from the various government agencies.

The representations of Excel constitute material, intentional misrepresentations.

Third Party Complaint (document no. 8) at paras. 178-87 (emphasis supplied). See also id. at paras. 76-78. According to Vaughn, Excel’s allegedly false and material misstatements about having an in-house mechanical engineer prompted Vaughn to recommend to the School District (and/or LSE)

that it contract with Excel, contributed to delays in completing the project, and caused “reputational damages” to Vaughn, which ultimately contributed to the School District’s decision to terminate Vaughn as the project’s architect and construction manager. See, e.g., Deposition of Scott Vaughn (document no. 139-3) at 197 (alleging that “Excel’s delay and this issue with the engineer caused delays on the project and costs increased.”); id. at 197-98 (“What specifically relates here and why they [Excel] are a piece of the puzzle is that their nonperformance and failure to perform directly impacted the credibility of Vaughn Associates, and the credibility of Vaughn Associates was important in terms of the confidence on the

project and the belief that I could get this done. . . . [T]heir failure injured my reputation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Scott v. Harris
550 U.S. 372 (Supreme Court, 2007)
Solis v. Lorraine Enterprises, Inc.
769 F.3d 23 (First Circuit, 2014)
Tobin Ex Rel. L. v. Federal Express Corp.
775 F.3d 448 (First Circuit, 2014)
Rando v. Leonard
826 F.3d 553 (First Circuit, 2016)
Block Island Fishing, Inc. v. Rogers
844 F.3d 358 (First Circuit, 2016)
Jaswell Drill Corp. v. General Motors Corp.
529 A.2d 875 (Supreme Court of New Hampshire, 1987)
Patch v. Arsenault
653 A.2d 1079 (Supreme Court of New Hampshire, 1995)
Dunn v. CLD Paving, Inc.
663 A.2d 104 (Supreme Court of New Hampshire, 1995)
Gray v. Leisure Life Industries
77 A.3d 1117 (Supreme Court of New Hampshire, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
Unity School District v. Vaughn Associates, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/unity-school-district-v-vaughn-associates-inc-nhd-2019.