Unity School District, Plaintiff v. Vaughn Associates, Inc., and Scott Vaughn, Defendants v. School Administrative Unit #6, Excel Mechanical, Inc., Superior Walls of Hudson Valley, Inc., and Town of Unity, Third-Party Defendants

2019 DNH 195
CourtDistrict Court, D. New Hampshire
DecidedNovember 19, 2019
Docket15-cv-155-SM
StatusPublished
Cited by1 cases

This text of 2019 DNH 195 (Unity School District, Plaintiff v. Vaughn Associates, Inc., and Scott Vaughn, Defendants v. School Administrative Unit #6, Excel Mechanical, Inc., Superior Walls of Hudson Valley, Inc., and Town of Unity, Third-Party Defendants) is published on Counsel Stack Legal Research, covering District Court, D. New Hampshire primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Unity School District, Plaintiff v. Vaughn Associates, Inc., and Scott Vaughn, Defendants v. School Administrative Unit #6, Excel Mechanical, Inc., Superior Walls of Hudson Valley, Inc., and Town of Unity, Third-Party Defendants, 2019 DNH 195 (D.N.H. 2019).

Opinion

UNITED STATES DISTRICT COURT

DISTRICT OF NEW HAMPSHIRE

Unity School District, Plaintiff

v. Case No. 15-cv-155-SM Opinion No. 2019 DNH 195 Vaughn Associates, Inc., and Scott Vaughn, Defendants

v.

School Administrative Unit #6, Excel Mechanical, Inc., Superior Walls of Hudson Valley, Inc., and Town of Unity, Third-Party Defendants

O R D E R

In 2010, the Unity School District hired Vaughn Associates

and Scott Vaughn (collectively, “Vaughn”) to design and oversee

construction of a new elementary school in Unity, New Hampshire.

The project did not proceed as the School District had

envisioned. Construction was beset with delays and forced work

stoppages (by, for example, the state fire marshal) and costs

ballooned from the $4.7 million that Vaughn had promised to more

than $9 million. Eventually, Vaughn’s contracts with the School

District were terminated and the School District sued Vaughn for

damages. Those claims were settled and, in April of 2017, the School District’s suit against Vaughn was dismissed, by

agreement of the parties. See Stipulation of Dismissal

(document no. 100).

What remain are Vaughn’s third-party claims against two

subcontractors on the project: Excel Mechanical, Inc., and

Superior Walls of the Hudson Valley, Inc. Pending before the

court is Excel Mechanical’s motion for summary judgment, in

which Excel asserts that it is entitled to judgment as a matter

of law as to each of the three state law claims Vaughn advances

against it. Vaughn objects.

For the reasons discussed, Excel’s motion for summary

judgment is granted.

Standard of Review

When ruling on a motion for summary judgment, the court is

“obliged to review the record in the light most favorable to the

nonmoving party, and to draw all reasonable inferences in the

nonmoving party’s favor.” Block Island Fishing, Inc. v. Rogers,

844 F.3d 358, 360 (1st Cir. 2016) (citation omitted). Summary

judgment is appropriate when the record reveals “no genuine

dispute as to any material fact and the movant is entitled to

judgment as a matter of law.” Fed. R. Civ. P. 56(a). In this

2 context, a factual dispute “is ‘genuine’ if the evidence of

record permits a rational factfinder to resolve it in favor of

either party, and ‘material’ if its existence or nonexistence

has the potential to change the outcome of the suit.” Rando v.

Leonard, 826 F.3d 553, 556 (1st Cir. 2016) (citation omitted).

Consequently, “[a]s to issues on which the party opposing

summary judgment would bear the burden of proof at trial, that

party may not simply rely on the absence of evidence but,

rather, must point to definite and competent evidence showing

the existence of a genuine issue of material fact.” Perez v.

Lorraine Enters., 769 F.3d 23, 29–30 (1st Cir. 2014). In other

words, “a laundry list of possibilities and hypotheticals” and

“[s]peculation about mere possibilities, without more, is not

enough to stave off summary judgment.” Tobin v. Fed. Express

Corp., 775 F.3d 448, 451–52 (1st Cir. 2014). See generally

Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 249 (1986).

Background

The factual background of this case has been set forth in

prior orders of the court. See, e.g., Order on Third-Party

Defendants’ Motion to Dismiss (document no. 42); Order on

Defendants’ Motion for Summary Judgment (document no. 55). It

need not be recounted again in detail. It is sufficient to note

the following. In 2010, the Unity School District entered into

3 two contracts with Vaughn to design and oversee construction of

a new elementary school. Construction began in late 2011.

Then, in August of 2012, the Unity School District hired Excel

Mechanical to perform rough and finish plumbing services. On

the same date, the School District entered into a separate

contract with William Knight, d/b/a LSE (“LSE”), to perform HVAC

and mechanical work on the project. LSE, in turn, entered into

a subcontract with Excel to provide “design drawings with

engineer’s stamp for both plumbing and mechanical.”

The upshot of all of this is the following: Vaughn had two

contracts with the Unity School District. It did not, however,

have any contractual relationship with Excel; Excel’s contracts

were with the School District itself, and with LSE. Moreover,

Excel’s contractual obligation to provide mechanical drawings

stamped by a licensed engineer - the critical element of

Vaughn’s claims - ran to LSE, not Vaughn. See AIA Standard

Agreement between Contractor and Subcontractor (document no.

139-7) at Article 8, and “Notes and Clarifications” to Contract

(document no. 139-8) at 3.

In its third-party complaint, Vaughn alleges that it

sustained compensable damages when it relied, both reasonably

and to its detriment, upon allegedly false and material

4 misstatements made by Excel concerning the presence of an in-

house mechanical engineer. Specifically, Vaughn alleges:

Excel represented to VAI [Vaughn] that it had a mechanical engineer who could complete the mechanical components of design and construction drawings.

Excel did not, in fact, have a mechanical engineer who fulfilled this role.

Excel’s purported engineering documents were produced in house by an unregistered engineering school graduate and then stamped by a licensed engineer who was not principally responsible for production of the engineering documents.

Excel knew or should have known that its representations were false when made.

Excel had a duty to VAI as agent for USD to be truthful in describing the scope of its abilities.

Excel made the representations in an effort to convince VAI to recommend that USD use Excel as the mechanical contractor on the project.

The representations were material.

VAI relied on the representations of Excel in recommending their use on the project and in not partnering with a separate mechanical engineer.

Excel’s failure to provide accurate stamped engineering drawings and/or to have a mechanical engineer on staff caused significant delays and costs on the project including but not limited to shutdowns from the various government agencies.

The representations of Excel constitute material, intentional misrepresentations.

Third Party Complaint (document no. 8) at paras. 178-87

(emphasis supplied). See also id. at paras. 76-78.

5 According to Vaughn, Excel’s allegedly false and material

misstatements about having an in-house mechanical engineer

prompted Vaughn to recommend to the School District (and/or LSE)

that it contract with Excel, contributed to delays in completing

the project, and caused “reputational damages” to Vaughn, which

ultimately contributed to the School District’s decision to

terminate Vaughn as the project’s architect and construction

manager. See, e.g., Deposition of Scott Vaughn (document no.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
2019 DNH 195, Counsel Stack Legal Research, https://law.counselstack.com/opinion/unity-school-district-plaintiff-v-vaughn-associates-inc-and-scott-nhd-2019.