Unity School District v. Vaughn Associates, Inc.

District Court, D. New Hampshire·Decided July 20, 2020·No. 1:15-cv-00155·Unknown

Opinion

UNITED STATES DISTRICT COURT

DISTRICT OF NEW HAMPSHIRE

Unity School District, Plaintiff

v. Case No. 15-cv-155-SM Opinion No. 2020 DNH 128 Vaughn Associates, Inc., and Scott Vaughn, Defendants

v.

Superior Walls of Hudson Valley, Inc., Third-Party Defendant

O R D E R After one of the third-party defendants, Superior Walls of Hudson Valley, failed to appear or file a dispositive motion, the court entered a default. See Entry of Default (document no. 36). Third-party plaintiffs (collectively, “Vaughn”) now move the court to enter a default judgment in their favor and award them the sum of $1,441,095.96. That motion is denied.

As this court has previously noted, “After default is entered and when the amount at issue is not a sum certain, the party must apply to the court for a default judgment. Although a defaulting party admits the factual basis of the claims asserted against it, the defaulting party does not admit the legal sufficiency of those claims. To recover on a motion for default judgment, the claimant must state a legally valid claim for relief. Therefore, before entering default judgment, the court must determine whether the admitted facts state actionable claims.” Bradley v. Wells Fargo Bank, N.A., No. 12-CV-127-PB,

2015 WL 12851708, at *1 (D.N.H. Dec. 21, 2015), report and recommendation approved, 2016 WL 7383772 (D.N.H. Jan. 13, 2016) (emphasis supplied) (citations and internal punctuation omitted).

The broader factual background to this case has been discussed numerous times in prior orders of the court and need not be recounted. The specific factual claims Vaughn asserts against Superior Walls are set forth in paragraphs 49 through 60 of Vaughn’s Third Party Complaint (document no. 8). In short, Vaughn did not have a contract with Superior Walls. Nevertheless, says Vaughn, Superior Walls promised to

manufacture and deliver to the project a “precast foundation wall and interior wall system” at some unspecified time. According to Vaughn, “Superior made representations to [Vaughn] that its prefabricated concrete components would be available to be used in the construction of the new Unity Elementary School in a timely manner.” Id. at para. 146 (emphasis supplied). But, says Vaughn, in April of 2012, when it attempted to order the precast walls from Superior, “Superior informed [Vaughn] that it would not be able to deliver the anticipated wall panels within the time necessary for the orderly progress of the work, in fact the anticipated delay was 6-12 months.” Id. at para. 52 (emphasis supplied). See also Id. at paras 151-52 (“After the

design was complete, [Vaughn] attempted to order Superior’s prefabricated concrete components for inclusion in the new Unity Elementary School. [Vaughn] was informed by Superior that its prefabricated concrete products would not be available for up to a year.”).

Those are the factual allegations against Superior: it promised it could deliver a precast wall system in a “timely” manner, but when Vaughn went to place an order for that wall system, it learned that it would take 6-12 months to manufacture – outside of the timeframe Vaughn needed it. Based upon those factual claims, Vaughn advanced four causes of action against

Superior Walls: intentional misrepresentation; negligent misrepresentation, statutory contribution under N.H. Rev. Stat. Ann. (“RSA”) 507:7-f, and implied common law indemnity. The court has discussed those causes of action and their essential elements in detail in prior orders. See, e.g., Order on Town of Unity’s Motion to Dismiss (document no. 42); Order on Excel’s Motion for Summary Judgment (document no.145). See generally Gray v. Leisure Life Indus., 165 N.H. 324 (2013); Johnson v. Capital Offset Co., No. 11-CV-459-JD, 2013 WL 5406619, at *8, 2013 DNH 127 (D.N.H. Sept. 25, 2013); Dunn v. CLD Paving, Inc., 140 N.H. 120 (1995). Those discussions need not be repeated.

It is sufficient to note that Vaughn’s factual claims are so vague that, had Superior Walls appeared and filed a motion to dismiss for failure to state a claim, that motion almost certainly would have been granted. Nowhere does Vaughn allege that Superior Walls promised, but failed to meet, a specific lead time for production of the wall system. Indefinite terms and phrases like “timely” and “within the time necessary” are insufficient to state a viable claim that Superior Walls promised to deliver its product by a date certain (or within so many weeks after an actual order had been placed) and then failed to honor that commitment. If, as alleged, Vaughn communicated with Superior Walls about using its product, Vaughn

subsequently incorporated that product into its design plans, and Vaughn then called to place an order for that product, it is not surprising that it might take Superior Walls six months (or more) to fulfill that order. Any actual “wrongdoing” on the part of Superior Walls is entirely absent from Vaughn’s narrative. I. Failure to State a Viable Claim Vaughn has broken down its claimed damages (and corresponding theories of recovery) into three broad categories:

1. $425,000.00, representing “the amount [Vaughn’s] insurance company was required to pay to resolve this lawsuit with the USD;” and

2. $908,095.96, representing “fees [Vaughn] was not paid by the Unity School District” under the contract between Vaughn and the School District; and

3. $108,000.00, representing the “6 months in which [Scott Vaughn] worked 50 hours per week to redesign the Project.”

Affidavit of Scott Vaughn (document no. 149-1) at para. 3.

A. Contribution and Indemnity. With respect to the first category of damages – the amount paid to settle the claims advanced by the Unity School District (“USD”) against Vaughn – Vaughn asserts that it is entitled to recover from Superior Walls on theories of implied common law indemnity and statutory contribution under RSA 507:7-f. Those two theories of recovery can be quickly dispatched.

Vaughn’s insurance company may have a claim for reimbursement of those sums. But, there is no indication that Vaughn is acting on behalf of the insurance company. Moreover, and largely for the reasons set forth in the court’s order discussing Vaughn’s claims against Excel Mechanical (document no. 142), Vaughn’s claims against Superior Walls for common law indemnity and statutory contribution fail to state the essential elements of viable claims.

According to Vaughn, it and Superior Walls are joint tortfeasors with joint and several liability. Plaintiff’s memorandum (document no. 149) at 3 (“Accordingly, [Vaughn] is entitled to recover from Superior Walls as a joint tortfeasor with join and several liability the $425,000 it [actually, its insurer] paid to USD to extinguish USD’s claims against Superior Walls . . ..”) (emphasis supplied). Two facts bear noting. First, in its complaint, Unity School District did not advance any claims against Superior Walls. Second, there are no allegations in the Vaughn’s Third Party Complaint that would support the notion that Superior Walls is a tortfeasor with

respect to the School District. Indeed, the Third Party Complaint suggests that the School District did not believe it had been harmed by Superior Walls’ conduct. See Third Party Complaint at para. 56-60 (alleging that Vaughn notified two different attorneys for the School District of Superior Walls’ alleged conduct, yet they did nothing to “preserve the School District’s rights” against Superior Walls). So, even if Vaughn were permitted to recover the settlement amount on behalf of its insurer, it has failed to demonstrate (or even allege) that Superior Walls owed and breached any cognizable common law duties to the School District that proximately caused the injuries for which the School District

Free access — add to your briefcase to read the full text and ask questions with AI

Unity School District v. Vaughn Associates, Inc., (D.N.H. 2020).

Unity School District v. Vaughn Associates, Inc. (Unity School District v. Vaughn Associates, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Dunn v. CLD Paving, Inc.
663 A.2d 104 (Supreme Court of New Hampshire, 1995)
Gray v. Leisure Life Industries
77 A.3d 1117 (Supreme Court of New Hampshire, 2013)