United Structures v. G.R.G. Engineering

CourtCourt of Appeals for the First Circuit
DecidedNovember 18, 1993
Docket93-1354
StatusPublished

This text of United Structures v. G.R.G. Engineering (United Structures v. G.R.G. Engineering) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United Structures v. G.R.G. Engineering, (1st Cir. 1993).

Opinion

USCA1 Opinion


UNITED STATES COURT OF APPEALS

FOR THE FIRST CIRCUIT

____________________

No. 93-1354

UNITED STRUCTURES OF AMERICA, INC. AND
UNITED STATES OF AMERICA FOR THE USE OF
UNITED STRUCTURES OF AMERICA, INC.,

Plaintiffs, Appellees,

v.

G.R.G. ENGINEERING, S.E.
AND NEW HAMPSHIRE INSURANCE COMPANY,

Defendants, Appellants.

____________________

APPEAL FROM THE UNITED STATES DISTRICT COURT

FOR THE DISTRICT OF PUERTO RICO

[Hon. Juan M. Perez-Gimenez, U.S. District Judge]
___________________

____________________

Before

Breyer, Chief Judge,
___________
Selya and Stahl, Circuit Judges.
______________

____________________

John E. Mudd with whom Cordero, Miranda & Pinto was on brief for
_____________ ________________________
appellants.
Mark S. Finkelstein with whom Elizabeth D. Alvarado, Shannon,
____________________ ______________________ ________
Martin, Finkelstein & Sayre, David P. Freedman, and O'Neill & Borges
____________________________ _________________ ________________
were on brief for appellee United Structures of America, Inc.

____________________

November 18, 1993
____________________

BREYER, Chief Judge. The plaintiff, having
____________

supplied steel to a now bankrupt subcontractor, has sued the

general contractor, seeking to recover payment for the steel

from the bond that a federal statute, the Miller Act,

requires certain general contractors to provide. 40 U.S.C.

270a-270b. The general contractor says the steel was

defective, and it wants to deduct from the promised purchase

price the amount that it says it had to spend to cure the

defects. The district court, relying upon a Ninth Circuit

case, United States ex rel. Martin Steel Constructors v.
__________________________________________________

Avanti Steel Constructors, 750 F.2d 759 (9th Cir. 1984),
__________________________

cert. denied sub nom. Harvis Construction v. United States
______________________ ___________________ _____________

ex rel. Martin Steel Constructors, 474 U.S. 817 (1985), held
_________________________________

that where the supplier has a contract with a subcontractor

but not with the general contractor, the Miller Act forbids

the general contractor from taking such "offsetting"

deductions. We disagree with the Ninth Circuit. We

therefore vacate the district court's judgment.

I

Background
__________

The Miller Act requires general contractors

working on federal government projects to furnish a payment

bond "for the protection of all persons supplying labor and

material" to the project. 40 U.S.C. 270a(a)(2). It

permits a supplier who has a "direct contractual

relationship with a subcontractor but no contractual

relationship . . . with the contractor furnishing" the bond

to sue on the bond for "the balance . . . unpaid at the time

of institution" of the suit, and to recover "judgment for

the sum or sums justly due him," as long as he complies with

certain notice requirements. Id. 270b(a). Puerto Rico's
___

"Little Miller Act" sets up a similar scheme for work on

projects undertaken by the Puerto Rican government. 22

L.P.R.A. 47, 51.

The plaintiff, United Structures of America

("United"), supplied steel to a subcontractor on two

projects, one for the United States government at Roosevelt

Roads Naval Station, the other for the Puerto Rican

government at Hato Rey Police Headquarters. Defendant

G.R.G. Engineering ("GRG") was the general contractor on

both projects. The subcontractor did not pay United in

full. When the subcontractor went bankrupt, United gave GRG

proper notice, and then sued GRG (and GRG's insurer) on the

payment bond for the amounts it believed were still due,

approximately $105,000 for the Roosevelt Roads project and

$177,000 for the police station project.

-3-
3

United moved for summary judgment, attaching

various bills and receipts in support of its claims. GRG

opposed the summary judgment motion. An affidavit (and a

few working papers) of Luis Marin Aponte, a GRG partner and

licensed engineer, constituted GRG's only effort to "set

forth specific facts showing that there is a genuine issue"

that might warrant a trial, Fed. R. Civ. P. 56(e). Marin's

affidavit said that GRG did not owe United any money because

(1) United engaged in a fraudulent billing practice known as

"front loading"; (2) GRG had to spend "$88,887 . . . due to"

United's "non-compliance with the specifications of the

equipment supplied" for the Roosevelt Roads project; and (3)

GRG had to spend an additional "$107,622 . . . to correct

defects and/or deficiencies in the materials" that United

"furnished" for the police station project.

The district court granted summary judgment in

favor of United, holding (1) that this affidavit failed to

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
United Structures v. G.R.G. Engineering, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-structures-v-grg-engineering-ca1-1993.