United States v. United States Cartridge Co.

95 F. Supp. 384, 1950 U.S. Dist. LEXIS 2016
CourtDistrict Court, E.D. Missouri
DecidedNovember 21, 1950
Docket2486
StatusPublished
Cited by14 cases

This text of 95 F. Supp. 384 (United States v. United States Cartridge Co.) is published on Counsel Stack Legal Research, covering District Court, E.D. Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. United States Cartridge Co., 95 F. Supp. 384, 1950 U.S. Dist. LEXIS 2016 (E.D. Mo. 1950).

Opinion

95 F.Supp. 384 (1950)

UNITED STATES
v.
UNITED STATES CARTRIDGE CO.

No. 2486.

United States District Court E. D. Missouri, E. D.

November 21, 1950.

*385 *386 H. G. Morison, Asst. Atty. Gen., Drake Watson, U. S. Atty., of New London, Mo., William V. O'Donnell, Asst. U. S. Atty., of St. Louis, Mo., Joseph M. Friedman, Chief, Frauds Section, and J. Gregory Bruce, George W. Meuth and Charles W. Tayler, Attorneys, Department of Justice, all of Washington, D. C., for plaintiff.

R. H. McRoberts, Marion S. Francis, and Bryan, Cave, McPheeters & McRoberts, all of St. Louis, Mo., for defendant.

HULEN, District Judge.

I.

Plaintiff sues to recover forfeitures and double damages (by brief plaintiff asks judgment for $214,878,725.12) under the fraudulent claims statutes, U.S.Code Annotated, Title 31, § 231, based on payments for ammunition delivered by defendant to plaintiff between "February 1, 1942 and October 31, 1943", on a cost plus fixed fee contract dated December 5, 1940.

Defendant denies receiving any money from plaintiff by presenting "false" claims; further it denies that its representatives having supervisory authority of the manufacturing plant "as a whole" did personally fail "to exercise good faith" or usual care in execution of the contract, which defendant claims to be a condition precedent to fixing liability under the contract. The trial, before the Court by jury waiver, represents over three thousand pages of record, plus six hundred and seven exhibits, many of which are voluminous in themselves.

The amended complaint contains eight assignments of fraud directed to specific instances in either the manufacturing, inspecting processes, or packing and delivery *387 of small arms ammunition, under the contract.

The answer pleads (third defense) plaintiff sustained no pecuniary loss; (4) defendant was entitled to its fixed fees under the terms of the contract; (5) no representatives of defendant having supervision of the plant as a whole had knowledge of any of the acts complained of; (6) no agent of defendant having any duty in connection with the preparation of the claims had any knowledge of any of the acts complained of; (7) repeats the fifth defense by way of pleading estoppel under the terms of the contract; (8) alleges conduct of defendant met terms of contract and that plaintiff by the contract has waived and released defendant from any claim under it; (9) settlement of all claims under the contract requiring submission of all disputes to plaintiff's contracting officers; (10) plaintiff has administratively determined defendant performed the contract; (11) the contract requires arbitration of all disputes; (12) settlement of all claims by subsequent contract for sufficient consideration; (13) release; (14) accord and satisfaction; (15) bar by virtue of release; (16) bar by settlement of all claims between the parties. Defenses 9 to 16, inclusive, were stricken on motion. See 78 F.Supp. 81.

Twenty-five vouchers representing claims by defendant, on which plaintiff made payments under the contract, are identified in paragraph 6 of the amended complaint. These vouchers cover the period February, 1942 to September, 1943. By amendment to the amended complaint it is charged that due to the specific acts of fraud described, each of the vouchers constituted a false claim under the statute. Plaintiff charges that due to avoidance of inspection requirements defendant "on numerous occasions between February 1942 and October 1943 * * * permitted defective" ammunition to flow into production and become a part of lots of ammunition accepted by plaintiff.

The issues: First, is defendant guilty of fraud under the purview of the false claims statute; second, if so do the terms of the contract relieve defendant of liability.

II.

Defendant is a wholly owned subsidiary of the Western Cartridge Company[1], now Olin Industries, Inc. In 1940 plaintiff solicited Western, through John M. Olin, President of Western, to undertake the manufacture of small arms ammunition. Western was one of two major industrial organizations in this country with substantial experience in the field of production of ammunition for war purposes. Mr. Olin was reluctant to have Western undertake the enterprise because its production capacity was then extended. While in Washington in the latter part of 1940, Mr. Olin learned of the serious weakness in the arms reserves of this country due in part to shortage of ammunition resulting from furnishing England with arms and ammunition after the lifting of the English and French armies at Dunkirk. Negotiations followed which resulted in execution, on December 5, 1940, of the contract for operation of the St. Louis Ordnance Plant for plaintiff by defendant.

The St. Louis Ordinance Plant was located in the City of St. Louis, a location influenced by the problem of securing personnel for its operation. Over four million square feet of floor space was provided in three hundred separate buildings on a large site of several hundred acres.

Burdett E. Bassett was general manager of the St. Louis Ordnance Plant. He had been general superintendent of Western's plant at East Alton. As general manager he was given authority by the officers of the defendant company to carry out the terms of its contract with plaintiff. With a skeleton force of trained employees obtained from Western, defendant through Mr. Bassett took over the St. Louis Ordnance Plant from its inception, installing equipment and securing and increasing production as individual buildings on the site were completed. The men obtained from Western were used to instruct new employees. Training schools for this purpose *388 were set up. There were over 80,000 employees engaged, at various times, in operation of the plant during the war period. Of these less than fifty had experience in manufacture of small arms.

Defendant experienced difficult problems in securing proper machine tools and getting them adjusted and running properly. That was only part of their troubles. Many people hired left during the training period, others before they were assigned to jobs, and others soon after they went on the production line. In securing and retaining personnel, defendant competed with other war and commercial industries in the City of St. Louis and manpower calls by the Armed Services. Many of the employees were without previous experience in any manufacturing. Some were engaging in salaried work or factory routine for the first time. Some were actuated solely by patriotic motives to help in the war effort.

We are concerned with a period of grave national crisis. Both plaintiff and defendant sought to impress the employees with the importance of their work in the successful waging of war, and the imperative need of the Armed Forces for the product of the plant. Armed guards patrolled the grounds. They were at every gate. Sabotage warnings were posted throughout the plant. Many of the employees had members of their immediate families in the Armed Forces, some serving overseas.

These circumstances together with outside influence, present when a nation is at war, tended to create an atmosphere of suspense. There was keen alertness, in the furtherance of what was considered a patriotic duty, to discover evidence of irregularity in production of ammunition. Some employees made reports to the Federal Bureau of Investigation. An investigation followed. On December 21, 1943 eleven employees were indicted for violating Title 18, Section 88,[2] and Title 50, Section 103[3]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Hercules, Inc.
929 F. Supp. 1418 (D. Utah, 1996)
O'Brien Gear & Machine Co. v. United States
591 F.2d 666 (Court of Claims, 1979)
United States v. Hangar One, Inc.
406 F. Supp. 60 (N.D. Alabama, 1975)
Paul O. Johnson v. United States
410 F.2d 38 (Eighth Circuit, 1969)
United States v. Schmidt
204 F. Supp. 540 (E.D. Wisconsin, 1962)
General American Life Insurance Company v. Cole
195 F. Supp. 867 (E.D. Missouri, 1961)
Herrera-Roca v. Barber
150 F. Supp. 492 (N.D. California, 1957)
United States v. National Wholesalers
126 F. Supp. 357 (S.D. California, 1954)
Rolland v. United States
200 F.2d 678 (Fifth Circuit, 1953)
United States v. United States Cartridge Co.
198 F.2d 456 (Eighth Circuit, 1952)
United States v. Park Motors, Inc.
107 F. Supp. 168 (E.D. Tennessee, 1952)
American Fire Ins. v. Cinnamon
100 F. Supp. 217 (W.D. Missouri, 1951)

Cite This Page — Counsel Stack

Bluebook (online)
95 F. Supp. 384, 1950 U.S. Dist. LEXIS 2016, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-united-states-cartridge-co-moed-1950.