United States v. Tulare Lake Canal Co.
This text of 535 F.2d 1093 (United States v. Tulare Lake Canal Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinions
OPINION
BROWNING, Circuit Judge:
This action was brought by the United States to determine two questions regarding the application of the reclamation laws, and particularly section 46 of the Omnibus Adjustment Act of 1926,1 to private lands receiving irrigation benefits from the Pine Flat Dam, a multiple-purpose dam on the Kings River, which flows into the San Joaquin River Basin in the Central Valley of California.
Section 46 of the 1926 Act bars delivery of reclamation project water to private land in excess of 160 acres in one ownership unless the owner executes a recordable contract with the Secretary of the Interior obligating him to sell the excess land at a price excluding incremental value resulting from the existence of the project. Section 46 also requires the United States to enter into contracts with irrigation districts organized under state law in the area to be served by the reclamation project. In exchange for the government’s promise to supply water, the districts undertake to reimburse the United States for an allocated portion of the cost of constructing the project and to withhold water from excess lands within their boundaries for which recordable contracts have not been executed.
The requirement that the owner of private land within a reclamation project agree to dispose of any excess over 160 acres at ex-project prices was intended to serve much the same purposes as the historic restriction on the amount of public land an entryman may obtain from the United States under the homestead acts, the original reclamation act, and other public land laws. As explained in more detail in Part II of this opinion, these purposes are to open private land to settlement by farmers of modest means, to insure wide distribution of the benefits of the federal investment in the reclamation project, and to prevent private landowners from realizing a disproportionate windfall advantage from enhanced productivity and land values because of the project.
Construction of Pine Flat Dam was authorized by the Flood Control Act of 1944,2 and substantially completed by 1954. Efforts to negotiate repayment contracts pursuant to section 46 for the portion of construction costs allocated to irrigation were unsuccessful. Private owners of excess lands contended that the Flood Control Act of 1944 exempted the Kings River project from the reclamation laws, including section 46. They also contended that even if those laws applied, owners of more than 160 acres of project land could avoid executing a recordable contract for the sale of their excess holdings and receive water for those lands if construction charges were repaid.
Opposition to the acreage limitations came primarily from large landowners in [1095]*1095the Tulare Lake Basin, a flat, low-lying region. The Basin contains about 20 percent of the one million acres in the Kings River service area — the area supplied with Kings River water from Pine Plat Dam. It includes the bulk of the service area’s more than 280,000 acres of excess holdings. More than 157,000 of the 188,000 acres within the boundaries of the Tulare Lake Basin Water Storage District, which covers most of the Basin, are held in tracts of more than 160 acres. These excess holdings average 2,600 acres each, including one tract of more than 60,000 acres owned by a single company.
In 1957, Elmer F. Bennett, Solicitor of the Department of the Interior, formally determined that the reclamation laws were applicable to lands served by Pine Flat Dam, rejecting the landowners’ argument that the Flood Control Act of 1944 exempted Pine Flat from these laws. 65 I.D. 525 (1957). Attorney General William P. Rogers rendered a formal opinion to the same effect in the following year. 41 Op.A.G. 377 (1958).
By 1957 Interior Department officials had negotiated a repayment contract with the Kings River Conservation District, a service-area-wide entity created to contract with the United States. On the advice of Solicitor Bennett, 64 I.D. 273 (1957), the Secretary of the Interior declined to sign the contract because it would have relieved individual landowners of the section 46 requirement that they execute recordable contracts to dispose of excess lands if they paid all construction costs allocated to their individual holdings.
Negotiations were then resumed between the United States and the various irrigation and water storage districts and canal companies in the Kings River service area. Under contracts proposed in 1961, owners of excess land would have been relieved of the recordable contract requirement if the irrigation district or canal company through which they received project water exercised an option to repay the share of overall construction costs allocated to the landowners served by the district or company. Solicitor Barry concluded that the requirements of section 46 could not be avoided in that manner. 68 I.D. 372 (1961). His opinion on the repayment issue was submitted to the Department of Justice by the Secretary of the Interior and was formally approved by Attorney General Robert F. Kennedy in December 1961. As a result, the proposed contracts were not executed.
The United States and the landowners agreed to submit the disputed issues to the courts. Tulare Lake Canal Company entered into a repayment contract with the United States in which it agreed to withhold delivery of project water from all lands in excess of 160 acres in single ownership unless the owner had executed a recordable contract for the sale of the excess land. However, the repayment contract provided that the recordable contract requirement would be void if it were determined in the test case that the Kings River project is exempt from section 46, or that section 46 may be avoided by repayment of construction charges. To enable it to test the latter theory, the Canal Company paid its share of the total irrigation cost of the Pine Flat Dam. The other districts and canal companies in the Kings River service area agreed to be bound by the outcome of the test case.
The United States then brought this suit, seeking an injunction prohibiting defendant Tulare Lake Canal Company from delivering “project water”3 to excess holdings unless the owners executed recordable contracts to sell such excess holdings in accordance with section 46.
The district court denied relief. The district court held that the reclamation laws [1096]*1096do not apply to the Kings River project, and that, even if they did, owners of excess land receiving water from the Tulare Lake Canal Company were relieved of the recordable contract requirement of section 46 when the company repaid its share of construction charges allocated to irrigation. United States v. Tulare Lake Canal Co., 340 F.Supp. 1185 (E.D.Cal.1972). We disagree with the district court on both issues.
We first consider the contention that the Kings River project is wholly exempt from the operation of section 46.
I
Appellees urge this court to hold that in passing the Flood Control Act of 1944 Congress intended to exclude Pine Flat Dam from the acreage limitations imposed by the reclamation laws. Such a holding (1) could not be reconciled with the holding in Turner v. Kings River Conservation District, 360 F.2d 184 (9th Cir.
Free access — add to your briefcase to read the full text and ask questions with AI
OPINION
BROWNING, Circuit Judge:
This action was brought by the United States to determine two questions regarding the application of the reclamation laws, and particularly section 46 of the Omnibus Adjustment Act of 1926,1 to private lands receiving irrigation benefits from the Pine Flat Dam, a multiple-purpose dam on the Kings River, which flows into the San Joaquin River Basin in the Central Valley of California.
Section 46 of the 1926 Act bars delivery of reclamation project water to private land in excess of 160 acres in one ownership unless the owner executes a recordable contract with the Secretary of the Interior obligating him to sell the excess land at a price excluding incremental value resulting from the existence of the project. Section 46 also requires the United States to enter into contracts with irrigation districts organized under state law in the area to be served by the reclamation project. In exchange for the government’s promise to supply water, the districts undertake to reimburse the United States for an allocated portion of the cost of constructing the project and to withhold water from excess lands within their boundaries for which recordable contracts have not been executed.
The requirement that the owner of private land within a reclamation project agree to dispose of any excess over 160 acres at ex-project prices was intended to serve much the same purposes as the historic restriction on the amount of public land an entryman may obtain from the United States under the homestead acts, the original reclamation act, and other public land laws. As explained in more detail in Part II of this opinion, these purposes are to open private land to settlement by farmers of modest means, to insure wide distribution of the benefits of the federal investment in the reclamation project, and to prevent private landowners from realizing a disproportionate windfall advantage from enhanced productivity and land values because of the project.
Construction of Pine Flat Dam was authorized by the Flood Control Act of 1944,2 and substantially completed by 1954. Efforts to negotiate repayment contracts pursuant to section 46 for the portion of construction costs allocated to irrigation were unsuccessful. Private owners of excess lands contended that the Flood Control Act of 1944 exempted the Kings River project from the reclamation laws, including section 46. They also contended that even if those laws applied, owners of more than 160 acres of project land could avoid executing a recordable contract for the sale of their excess holdings and receive water for those lands if construction charges were repaid.
Opposition to the acreage limitations came primarily from large landowners in [1095]*1095the Tulare Lake Basin, a flat, low-lying region. The Basin contains about 20 percent of the one million acres in the Kings River service area — the area supplied with Kings River water from Pine Plat Dam. It includes the bulk of the service area’s more than 280,000 acres of excess holdings. More than 157,000 of the 188,000 acres within the boundaries of the Tulare Lake Basin Water Storage District, which covers most of the Basin, are held in tracts of more than 160 acres. These excess holdings average 2,600 acres each, including one tract of more than 60,000 acres owned by a single company.
In 1957, Elmer F. Bennett, Solicitor of the Department of the Interior, formally determined that the reclamation laws were applicable to lands served by Pine Flat Dam, rejecting the landowners’ argument that the Flood Control Act of 1944 exempted Pine Flat from these laws. 65 I.D. 525 (1957). Attorney General William P. Rogers rendered a formal opinion to the same effect in the following year. 41 Op.A.G. 377 (1958).
By 1957 Interior Department officials had negotiated a repayment contract with the Kings River Conservation District, a service-area-wide entity created to contract with the United States. On the advice of Solicitor Bennett, 64 I.D. 273 (1957), the Secretary of the Interior declined to sign the contract because it would have relieved individual landowners of the section 46 requirement that they execute recordable contracts to dispose of excess lands if they paid all construction costs allocated to their individual holdings.
Negotiations were then resumed between the United States and the various irrigation and water storage districts and canal companies in the Kings River service area. Under contracts proposed in 1961, owners of excess land would have been relieved of the recordable contract requirement if the irrigation district or canal company through which they received project water exercised an option to repay the share of overall construction costs allocated to the landowners served by the district or company. Solicitor Barry concluded that the requirements of section 46 could not be avoided in that manner. 68 I.D. 372 (1961). His opinion on the repayment issue was submitted to the Department of Justice by the Secretary of the Interior and was formally approved by Attorney General Robert F. Kennedy in December 1961. As a result, the proposed contracts were not executed.
The United States and the landowners agreed to submit the disputed issues to the courts. Tulare Lake Canal Company entered into a repayment contract with the United States in which it agreed to withhold delivery of project water from all lands in excess of 160 acres in single ownership unless the owner had executed a recordable contract for the sale of the excess land. However, the repayment contract provided that the recordable contract requirement would be void if it were determined in the test case that the Kings River project is exempt from section 46, or that section 46 may be avoided by repayment of construction charges. To enable it to test the latter theory, the Canal Company paid its share of the total irrigation cost of the Pine Flat Dam. The other districts and canal companies in the Kings River service area agreed to be bound by the outcome of the test case.
The United States then brought this suit, seeking an injunction prohibiting defendant Tulare Lake Canal Company from delivering “project water”3 to excess holdings unless the owners executed recordable contracts to sell such excess holdings in accordance with section 46.
The district court denied relief. The district court held that the reclamation laws [1096]*1096do not apply to the Kings River project, and that, even if they did, owners of excess land receiving water from the Tulare Lake Canal Company were relieved of the recordable contract requirement of section 46 when the company repaid its share of construction charges allocated to irrigation. United States v. Tulare Lake Canal Co., 340 F.Supp. 1185 (E.D.Cal.1972). We disagree with the district court on both issues.
We first consider the contention that the Kings River project is wholly exempt from the operation of section 46.
I
Appellees urge this court to hold that in passing the Flood Control Act of 1944 Congress intended to exclude Pine Flat Dam from the acreage limitations imposed by the reclamation laws. Such a holding (1) could not be reconciled with the holding in Turner v. Kings River Conservation District, 360 F.2d 184 (9th Cir. 1966), which binds this panel; and (2) would be contrary to the intent of Congress underlying the 1944 Act authorizing the construction of Pine Flat Dam.
A.
Turner v. Kings River Conservation District
In Turner this court held as follows (360 F.2d at 192):
Section 8 of the Flood Control Act of 19444 authorizes the Secretary of the Interior to operate and maintain structures such as Pine Flat dam “under the provisions of the Federal Reclamation Laws (Act of June 17, 1902, 32 Stat. 388 and Acts amendatory or supplementary thereto),” thus making section 7 of the Reclamation Act of 1902, 32 Stat. 389, 43 U.S.C.A. § 421, applicable to the irrigation features of the Pine Flat project.
The strict holding of the court was that section 7 of the 1902 Act, authorizing the Secretary of the Interior to acquire by condemnation rights needed to carry out the reclamation laws, was applicable to the Pine Flat project. As is evident from the passage quoted, however, the premise for this holding was that section 8 of the Flood Control Act of 1944 authorized the Secretary to operate and maintain the Pine Flat project “under the provisions of the Federal Reclamation laws,” which include section 7 of the 1902 Act. Since the “Federal Reclamation laws” also include section 46 of the 1926 Act, the premise of Turner requires a holding that the recordable contract requirement of section 46 also applies to the Pine Flat project.
Appellees seek to escape this conclusion by arguing that the quoted passage is not a holding but an assumption, made for the purposes of the decision but not essential to it. An examination of the structure of the [1097]*1097Turner opinion and the proceedings relating to the disposition of the petition for rehearing in that ease demonstrates that the court intended to and did hold that the reclamation laws apply to Pine Flat project.
In Turner, claimants of rights under state law to use Kings River water on riparian and overlying lands sought to enjoin officials of the Department of the Interior and the Corps of Engineers from operating Pine Flat Dam in such a way as to interfere with these rights. The district court dismissed the action as one against the sovereign without consent. This court concluded that the action could be maintained if the defendant government officers had exceeded their statutory authority. Plaintiffs argued that defendants had exceeded their authority because the 1944 Act, authorizing the construction of Pine Flat Dam, did not authorize the officials to interfere with plaintiffs’ water rights. In answer to this argument we held, in the passage quoted, that the officials did have authority to interfere with plaintiffs’ water rights in operating Pine Flat Dam because, under section 8 of the 1944 Act, Pine Flat Dam was to be operated pursuant to the reclamation laws, and those laws included the power to take private rights conferred by section 7 of the 1902 Act. We went on to hold that no other provision of the 1944 Act excepted Pine Flat Dam from the grant of eminent domain in section 7 of the 1902 Act.
Appellees contend that this court merely assumed without deciding that section 8 of the 1944 Act applied to Pine Flat Dam. They point out that plaintiffs had alleged that section 8 applied and that certain provisions of reclamation law invoked by that section prohibited defendant officials from interfering with plaintiffs’ water rights. Appellees argue that since this court was reviewing the dismissal of a complaint for failure to state a claim, it was required to accept these allegations of the complaint as true; and that it did no more. The obvious answer is that while allegations of fact are to be regarded as true, allegations of law are not. See 2A Moore’s Federal Practice ¶ 12.08, at 2267-69. Whether section 8 of the 1944 Act made the reclamation laws applicable to Pine Flat project was a question of law. The resolution of this question of law was essential to the decision of the case. If the defendant officers were not authorized to take plaintiffs’ water rights, they were acting unlawfully and the suit to enjoin their unlawful conduct was not barred as a suit against the United States. This court found the necessary authority to condemn in section 7 of the 1902 Act, and the availability of section 7 of the 1902 Act required the holding that section 8 of the 1944 Act made the reclamation laws applicable to Pine Flat Dam.
Moreover, the Turner court was specifically asked to modify its opinion to state that the applicability of the reclamation laws was not decided but only assumed, as appellees in this case now argue. The court refused to do so.
As the opinion in Turner was originally filed, the passage quoted above stated that section 8 of the 1944 Act made “all of the provisions and limitations of the Reclamation law applicable to the irrigation features of the Pine Flat project.” Slip opinion at 10. The Kings River Conservation District, among others, filed a “Petition for Rehearing or, in the Alternative, for Modification or Clarification of the Court’s Opinion.” The petition requested the court to modify the passage quoted to indicate that the court was only assuming and not deciding that section 8 of the 1944 Act made reclamation law applicable to Pine Flat. The revision suggested by petitioners was as follows (Petition for Modification at 10-11):
If we assume that Section 8 of the Flood Control Act of 1944 authorizes the Secretary of the Interior to operate and maintain structures such as Pine Flat Dam “under the provisions of the Federal Reclamation laws (Act of June 17, 1902, 32 Stat. 388 and Acts amendatory or supplementary thereto),” and thus makes all of the provisions and limitations of the Reclamation law applicable to the irrigation features of the Pine Flat project, the appellee officials would nevertheless be [1098]*1098authorized to interfere with appellants’ rights in the manner alleged in the complaint.
The court did not adopt the suggested language. The revision the court did adopt, quoted earlier, necessarily involved rejection of the suggestion that the court restate, as an assumption rather than as a holding, the court’s premise that section 8 of the 1944 Act made the reclamation laws applicable to Pine Flat.
The court did, however, narrow its conclusion to the precise necessities of the case by substituting “section 7 of the Reclamation Act of 1902” for the broader phrase, “all of the provisions and limitations of the Reclamation law.” The reason is clear. It is apparent that the Turner court had concluded that section 8 of the 1944 Act made all the provisions and limitations of the reclamation laws applicable to Pine Flat, for the opinion initially stated as much and the authorities cited were to that effect.5 The petition for modification of the Turner opinion also appeared to concede that if section 8 made the reclamation laws applicable to Pine Flat at all, it made those laws applicable in their entirety, including acreage limitations.6 However, the petition, in a footnote, did reserve the argument that even if reclamation laws were generally applicable to Pine Flat, the provisions regarding acreage limitation were not;7 and argued that this narrow issue should not be definitely resolved until the court had the benefit of a fuller presentation that would be available in the present litigation, then only recently filed. It is apparent that the purpose of the modifications of the Turner opinion limiting the specific reference to section 7 of the 1902 Act was solely to preserve the opportunity for appellees in this case to make the promised demonstration that although section 8 applies to the Pine Flat Dam, the acreage limitation provisions of the reclamation laws do not. Appellees have not attempted to make this showing. Instead they have argued that the reclamation laws are entirely inapplicable to this project. This position was rejected in Turner8
Nonetheless, in view of the importance of the question, and the opportunity this case has given to examine it more fully, we have reconsidered the legislative history of the Flood Control Act of 1944 at some length. That re-examination reveals that section 8 was conceived and considered by Congress with the Pine Flat Dam and other nearby projects in the Sacramento-San Joaquin River Basin specifically in mind, and that the application of the excess land provisions to these projects was the principal issue in controversy. The legislative history leaves no doubt that the 160-acre limitation was [1099]*1099intended to apply in the Kings River service area.
B.
Legislative History of Flood Control Act of 1944
In Ivanhoe Irrigation District v. McCracken, 357 U.S. 275, 78 S.Ct. 1174, 2 L.Ed.2d 1313 (1958), the Supreme Court declined to imply an exception to the acreage limitation provision found in section 5 of the 1902 Act, substantially re-enacted in section 46 of the 1926 Act, stating, “Significantly, where a particular project has been exempted because of its peculiar circumstances, the Congress has always made such exemption by express enactment.” 357 U.S. at 292, 78 S.Ct. at 1184, 2 L.Ed.2d at 1326.9 There is no “exemption by express enactment” of the Kings River project from acreage limitations in the 1944 Act or any other statute. The argument for exemption rests instead upon indirect implications drawn from the text of the 1944 Act and scattered incidents in the legislative history. In light of Ivanhoe and the important public interests underlying the historical policy of acreage limitations in reclamation law, it is questionable whether it would be appropriate to base exemption upon such a foundation. In any event, the legislative history of the 1944 Act demonstrates that an implied exemption would be wholly unjustified.
It may be helpful to begin with a brief summary of the legislative history of the 1944 Act as it relates to the Kings River project.
Mention should be made at the outset of a significant factor in the historical context in which Congress considered the 1944 Act. A proposal to expressly exempt the Central Valley project from acreage limitations was under consideration by Congress at the time that Congress was considering the 1944 Act. The proposal for express exemption was defeated after vigorous congressional debate. See Ivanhoe Irrigation District v. McCracken, supra, 357 U.S. at 292-93, 78 S.Ct. at 1184, 2 L.Ed.2d at 1326.
An almost identical debate took place during consideration of the Flood Control Act regarding whether the reclamation laws, and especially acreage limitations, should be applicable to the Pine Flat Dam and other projects authorized for construction in the Sacramento-San Joaquin River Basin. These projects were to be adjacent to the Central Valley project; the Administration argued they should be integrated into it. Under these circumstances, it is highly unlikely that the same Congress that rejected an express exemption for the Central Valley project intended, sub silentio, to exclude the Pine Flat Dam from acreage limitations. The legislative history confirms that it did not.
The proceedings directly concerned with the 1944 Act were marked by a continuing controversy over two distinct issues: (1) whether Pine Flat Dam should be constructed by the Corps of Engineers or the Bureau of Reclamation; and (2) whether the acreage limitation should apply to the project once built. The controversy may fairly be characterized as a power struggle between Kings River water users and the Roosevelt Administration. The water users needed the dam for flood protection and a regulated water flow. They were willing to pay for irrigation benefits, but did not wish to become subject to the reclamation laws, especially acreage restrictions. The Administration, represented by President Roosevelt, Secretary of the Interior Ickes, and Commissioner Bashore of the Bureau of Reclamation, was equally insistent that the acreage restrictions should apply to the Kings River project. The Administration was not willing to accept reimbursement of the costs attributable to irrigation benefits as a substitute for those limitations. In the Administration’s view, the interests of the United States were not merely financial. They included such social purposes as wide [1100]*1100dispersion of the public subsidy, avoidance of speculation, and provision of family homes and farms, especially for soldiers who would soon be returning from the war.
Both sides of the controversy were exhaustively presented before congressional committees and on the floor of the House and the Senate. Neither side emerged wholly victorious. The California interests prevailed on the issue of which agency should construct Pine Flat Dam — Congress decided that Pine Flat Dam should be built by the Corps of Engineers. They lost on the issue of whether acreage limitations should apply — Congress decided that these limitations should apply to the Kings River project. The California interests emerged from the House with no more than a colorable argument on the latter issue, based upon equivocal statements in committee hearings and floor debate; but the proceedings in the Senate, particularly in the consideration of the conference report, make it clear beyond question that the struggle against acreage limitations was ultimately lost. What is now section 8 of the 1944 Act was redrafted in the Senate to conform to the wishes of the Secretary of the Interior, who was adamant in his insistence that the reclamation laws should apply to the Kings River project. The Senate rejected an amendment specifically designed to exempt dams in the Sacramento-San Joaquin River Basin, especially those on the Kings and Kern Rivers, from the operation of section 8. A colloquy between Senator Overton, floor manager of the bill, and Senator Hill, Acting Majority Leader, at the close of debate on the conference report, was intended to and did remove any doubt that section 8 was applicable to the California projects.
Soon after the President signed the Flood Control Bill, California interests attempted to regain their position by securing an administrative determination that the Secretary of War was authorized to negotiate with water users for repayment without regard to reclamation law. Again they lost. The contemporaneous interpretation of the 1944 Act by the President, the Secretary of War, and the Secretary of the Interior was that irrigation uses of the Pine Flat Dam were subject to reclamation law. This has been the consistent interpretation of the 1944 Act by the Department of the Interior since 1944. It was confirmed in 1958 by a formal opinion of the Attorney General. 41 Op.A.G. 377 (1958).
We turn to a more detailed consideration of the legislation and administrative background of the 1944 Act.
In 1940 both the Corps of Engineers and the Bureau of Reclamation submitted reports to Congress recommending construction of a dam on the Kings River. Specifications for the dam were similar. Both proposals predicted that the flood control and irrigation benefits would be about equal.10 The proposals differed, however, as to who should build the dam and operate it. The Corps of Engineers proposed that the Corps build the dam and that local interests operate it under regulations prescribed by the Secretary of War. The Bureau of Reclamation proposed that the dam be built and operated by the Bureau.11 The recommended schedule for payment of allocable irrigation construction costs by water users also differed. The Bureau recommended annual installments to be paid over 40 years (the usual repayment period under reclamation law). The Corps recommended payment of a lump sum representing the discounted present value of the 40 annual installments.12
President Roosevelt concluded that the project was “dominantly an irrigation undertaking and is suited to operation and maintenance under the reclamation law.” He endorsed the Interior Department’s proposals that the Bureau of Reclamation construct, operate, and maintain the Kings [1101]*1101River project and that repayment be made in 40 annual installments under prevailing reclamation policy.13
Hearings on the proposals were held before the House Flood Control Committee in 1940 and 1941. Local water users opposed the Bureau’s proposal and endorsed that of the Corps of Engineers. The Kings River-Pine Flat Association was especially concerned that Bureau control over release of water might result in interference with their vested water rights.14 Acreage limitations were not discussed.
Out of deference to the President’s position that the Kings River project should be built by the Bureau, this project was not included in the comprehensive flood control bill reported by the House Flood Control Committee in 1941. The committee issued a separate report recommending construction of the dam by the Corps of Engineers,15 but no further action was taken.
Hearings before the House Flood Control Committee resumed in 1943 and continued in 1944. In 1944 President Roosevelt wrote to Congressman Whittington, chairman of the committee, modifying the Administration’s earlier position. The President reaffirmed his view that the Kings River and Kern River projects were predominantly for irrigation and should therefore be built and operated by the Bureau of Reclamation — a view that had been rejected by the committee in its 1941 report. However, the President added a new suggestion, namely, that Congress provide for multiple-agency administration of multiple-purpose projects. The President proposed that whatever agency constructed a multiple-purpose project, each agency having an interest in the project should be given responsibility for administering its interest in accordance with its own legislation and policies. “For example,” the President wrote, “the Bureau of Reclamation in the Department of the Interior should administer, under the Reclamation laws and its general policies, those irrigation benefits and phases of projects built by the Corps of Engineers.”16
[1102]*1102It is important to note that this suggestion was directed specifically to Pine Flat Dam on the Kings River and to the adjacent Kern River project.17 It provided the basis for the compromise eventually reflected in section 8 of the 1944 Act.
Thus, the Administration sought to have the reclamation laws, and especially the excess land provisions, applied to the Kings River and Kern River projects in two ways: by having these projects built and operated by the Bureau of Reclamation or, failing that, by having use of these projects for irrigation administered by the Bureau under the reclamation laws. The Administration failed in its efforts to have Pine Flat Dam constructed by the Bureau; Congress ultimately concluded that the dam should be built by the Corps of Engineers. But it succeeded in its alternative position, securing in section 8 a provision that the irrigation uses of projects constructed by the Corps of Engineers should conform with reclamation law.
Commissioner Bashore presented the Administration’s position to the House Flood Control Committee in detailed testimony supplementing the President’s letter. Commissioner Bashore’s presentation was directed specifically to the Kings River and Kern River projects.18 He repeated the Administration’s position that both projects should be built by the Bureau. He went on to urge, however, that if Congress should decide to authorize construction by the Corps of Engineers, the statute authorizing construction should provide that irrigation benefits of the two projects be administered by the Secretary of the Interior under the reclamation laws.19 The statutory language suggested by Commissioner Bashore appears in the margin.20
[1103]*1103Commissioner Bashore made it explicitly clear that the purpose of the provision was to make the acreage limitations applicable to the Kings River and Kern River projects.21 He emphasized the social purposes intended to be accomplished by breaking up the large landholdings in the areas that would be served by these projects— spreading the federal subsidy, preventing speculation, and making it possible for people of limited means to establish farms on irrigated lands on which families could be self-sustaining.22 He expressly rejected the notion that repayment by water users of the costs of construction allocated to irrigation would be an acceptable substitute for the advancement of these social purposes.23
All of the objections now raised to application of acreage limitations to the Kings River project were also fully presented to the committee — that all land to be served was in private hands, that local water users had appropriated most if not all Kings River water and had constructed extensive irrigation works in the area, and that no new lands would be brought under irrigation as a result of the project.24 In order to gain the benefits of federally subsidized flood control and irrigation without subjecting themselves to acreage limitations, the landowners urged the committee to adopt the dominant-interest test originally advocated by the Administration25 to recognize that the dominant purpose of the Kings River project was flood control, and to provide that it be constructed by the Corps of Engineers and be operated either by the Corps or, preferably, by the water users themselves.26
The bill reported by the House committee authorized construction of the Pine Flat Dam by the Corps of Engineers,27 but it
[1104]*1104also embodied the President’s proposal for joint administration of multiple-purpose projects. Section 5 of the bill provided that the projects should be operated for navigation and flood control purposes in accordance with regulations prescribed by the Secretary of War. Section 6 provided that projects built by the Corps of Engineers should be utilized for reclamation purposes in accordance with regulations prescribed by the Secretary of the Interior.28
With minor modifications, the language of section 6 followed that proposed to the committee by Commissioner Bashore for the avowed purpose of making acreage limitation provisions of reclamation law applicable to the irrigation features of the Kings River and Kern River projects in the event the committee should decide, as it did, that the construction of these dams should be assigned to the Corps of Engineers.29
In the course of debate on the floor of the House, Congressman Curtis, a member of the committee, explained section 6 in essentially these terms.30 Committee Chairman Whittington also described section 6 as a broad grant of power to the Secretary of the Interior to regulate reclamation features of the authorized projects.31 Each characterized the section as a concession to the Bureau of Reclamation and the Secretary of the Interior.
The Administration was still not entirely satisfied. Section 6 of the committee bill provided that water available for reclamation was to be distributed in accordance with regulations prescribed by the Secretary of the Interior, but it did not specifically state that such regulations should conform to reclamation law, as had Commissioner Bashore’s proposal.32 On April 10, 1944, Secretary Ickes wrote the Director of the Bureau of the Budget expressing concern that the committee bill did not make reclamation law applicable to irrigation uses of water stored behind the dams authorized in the bill. He made it clear that his objection was motivated by a fear that [1105]*1105the bill might permit large landowners on the Kings River and Kern River projects to avoid the acreage limitations.33 During the floor debates on May 9, 1944, Chairman Whittington offered a “perfecting amendment” on behalf of the Food Control Committee, adding to section 6 the express requirement that the Secretary of the Interi- or regulate the use of irrigation waters “under existing reclamation law.” He stated that the amendment was proposed because “some of the friends and spokesmen for reclamation were critical of the language in the bill.”34 The amendment was adopted. On May 20 the Acting Director of the Bureau of the Budget replied to Secretary Ickes’ letter of April 10, calling attention to this amendment to section 6 and stating, “[T]his change would give the Department of the Interior all the authority necessary.”35
As the bill left the House, therefore, the overwhelming evidence was that it represented a victory for the Administration’s position that the irrigation uses of the Kings River project and other projects authorized by the bill were to conform to the reclamation laws, and specifically to acre-
age limitations, even though the projects were to be built by the Corps of Engineers.
All that can be garnered to lend possible support to appellees’ contrary interpretation is language in the committee report and in Chairman Whittington’s remarks on the floor that really consists of nothing more than a sympathetic recitation of arguments advanced by water users against application of the reclamation laws to the Pine Flat project.36
Subsequent proceedings in the Senate removed any possible doubt as to Congress’ intention to apply acreage limitations to the Kings River project.
Hearings before a subcommittee of the Senate Commerce Committee produced the same general conflict of views that had developed in hearings before the House Flood Control Committee. Again California interests were arrayed against the Administration, which was supported by organizations of labor and small farmers. Again the controversy centered upon the application of acreage limitations, particularly to projects in the Sacramento-San Joaquin River Basin, including Pine Flat Dam. Again proponents of acreage limitation [1106]*1106pressed the historical purposes served by such provisions — spreading the federal subsidy, avoiding speculation, creating family farms — while opponents again pressed the features of the Kings River and Kern River projects that assertedly made application of acreage limitations inappropriate.37
Administration spokesmen again sought to have these projects built by the Bureau, rather than the Corps of Engineers, and expressed their disappointment in the House decision to the contrary;38 but they also reaffirmed the President’s alternative suggestion that water made available for irrigation by projects built by the Corps of Engineers be utilized in accordance with the reclamation laws, including acreage limitations.39
The issue was never in doubt. The subcommittee was obviously impressed with the experience and skill of the Corps of Engineers in building and operating dams for effective flood control.40 On the other hand, this same subcommittee had recently demonstrated its adherence to enforcement of acreage limitations in federally subsidized irrigation projects by rejecting the proposal that the Central Valley project be exempted from such limitations.41 Moreover, on the earlier occasion this same subcommittee had advanced as a solution to the apparent dilemma the very approach that was reflected in section 6 of the House bill — that is, that the Corps of Engineers be authorized to construct these multiple-purpose projects, but that irrigation features of such projects be utilized in conformity with the reclamation laws.42 It was inevitable that members of the subcommittee would suggest that the same approach be adopted in connection with Pine Flat and other nearby projects.43
Both Secretary Ickes and Commissioner Bashore appeared before the subcommittee. Both made it clear that at the heart of the conflict were the efforts of owners of large tracts of land in California projects, including the Kings River project, to escape the acreage limitation and antispeculation provisions of the reclamation laws. Both urged the subcommittee to reject these efforts.44 Both accepted section 6 of the [1107]*1107House bill as intended to make the reclamation laws, including acreage limitations, applicable to irrigation uses of projects authorized by the Act, but both suggested modification of the language to accomplish this purpose more effectively.45
During the hearings Secretary Ickes had written to the chairman of the Senate Commerce Committee:
I regard section 6 of the bill as intended to provide for the application of the Federal reclamation laws to projects having irrigation possibilities. . . . However, the provisions of this section are not entirely apt in their relation to the various technical features of the Federal reclamation laws.46
Secretary Ickes amplified these views in his testimony before the Senate committee:
[Section 6] as it now stands provides for the application of the Federal reclamation laws to the irrigation features of Army reservoir projects. However, it is not drafted in a way that ties in with the basic provisions of the reclamation laws in all pertinent respects. For example, it speaks of those laws as though they involved merely the imposition of regulations, whereas in truth they are largely designed to authorize a system of contractual relationships. It disregards the problem of allocating costs for multiple-purpose facilities serving other uses in addition to irrigation. And it overlooks the special laws relating to Indian irrigation developments. Hence, I believe that this section should be rephrased in a way that would eliminate possible future uncertainties with respect to its precise meaning and operation.47
The Secretary’s first concern, one particularly relevant here, is understandable. The mechanism adopted by section 46 of the 1926 Act for accomplishing the antimonopoly and antispeculation objectives of acreage limitations was to direct the Secretary of the Interior to include in repayment contracts with irrigation districts provisions under which the districts were required to [1108]*1108withhold water from owners of excess lands who had not executed recordable contracts agreeing to sell that excess land at ex-project prices. This enforcement mechanism, based upon contractual relationships, replaced the prior method of enforcement through regulations governing water right applications.48 The regulatory scheme therefore did not apply to projects built after the passage of the 1926 Act. Yet section 6 of the House bill was couched entirely in terms of the Secretary’s power to prescribe regulations, rather than the Secretary’s power to enter into contracts. Though technical, the deficiency was obviously significant. The revision proposed by the Secretary met the problem by broadening the language of section 6 to provide that dams were to be utilized for irrigation purposes “only in conformity with the provisions of this section,” that is, “under the provisions of the Federal reclamation laws (Act of June 17, 1902, 32 Stat. 388, and acts amendatory thereof or supplementary thereto)” — which of course included the 1926 Act.49
The subcommittee adopted the essence of the Secretary’s recommended modification of section 6; it is reflected in the language of section 8 as reported to the Senate,50 and as finally enacted.51
There can be no doubt, on this record, that in proposing section 8 the Senate subcommittee intended to adopt the Administration’s position that the reclamation laws, and specifically acreage limitations, should apply to irrigation uses of all projects authorized by the bill, including the Kings River project, even though the projects were to be built by the Corps of Engineers.
On the floor of the Senate a final attempt was made to bar application of acreage limitations to the California projects authorized by the 1944 Act, but it was turned back.
The President and Secretary Ickes persisted in their efforts to have projects in the general Central Valley area, including Pine Flat Dam, built by the Bureau of Reclamation rather than the Corps of Engineers, as the House bill provided. However, they welcomed the provision in section 8 making reclamation laws applicable to irrigation features of dams built by the Engineers. Each specifically mentioned the acreage limitations in connection with that section. Secretary Ickes warned that an effort would be made to amend or delete section 8 on the floor of the Senate.52
[1109]*1109The challenge anticipated by Secretary Ickes appeared in the form of two amendments proposed by Senator O’Mahoney of Wyoming. One sought to amend section 6 of the bill reported by the Senate committee to authorize the Secretary of War to contract for the storage of water for any beneficial use in any reservoir constructed by the War Department, “on such terms and conditions as he may deem reasonable.”53 Objection was immediately raised that this would permit the Secretary of War to sell water for irrigation use on such terms and conditions as he chose, and thus would “change the basis of the reclamation law.”54 Senator Hatch stated that the amendment would permit “the Army Engineers ... to supply water . entirely removed from . . . the acreage limitations and the other basic foundations of our irrigation law.”55
The second O’Mahoney amendment sought to make two changes in section 8 as reported by the Senate committee. It would have deleted the provision in section 8 that dams and reservoirs under the jurisdiction of the Secretary of War could be utilized for irrigation only in conformity with section 8, and thus with the reclamation laws; and it would have made section 8 inapplicable “to any dam or reservoir heretofore or hereafter constructed which supplements any existing locally operated irrigation system or other locally operated water facilities.”56
A letter from Secretary Ickes, in opposition to these proposals, pointed out the effect of the two amendments proposed by Senator O’Mahoney: “[T]he projects included in the bill for the great Central Valley area of California (Sacramento-San Joaquin River Basin, p. 31, H.R. 4485) would supplement some existing locally operated irrigation systems. Those projects, therefore, would be left subject only to section 6 which, as the Californians would have it amended, disregards the Federal reclamation laws while placing the Corps of Engineers in the irrigation field.”57 Senator Overton, chairman of the Senate subcommittee, also opposing the amendment, advised the Senate that section 8 had been included “at the request of the Secretary of Interior, and at his very earnest insistence,” [1110]*1110and “word for word as recommended by the Secretary of the Interior.”58
Senator Hayden moved that both amendments be referred to the Committee on Irrigation and Reclamation, on the ground that they would alter existing reclamation law and therefore should be considered by the committee with jurisdiction over that subject matter. The motion was adopted.59
The disposition of the O’Mahoney amendments reflects the Senate’s understanding that, under section 8, the reclamation laws, and specifically acreage limitations, would apply to utilization of water for irrigation on projects authorized for construction by the Corps of Engineers in the Sacramento-San Joaquin River Basin, including Pine Flat Dam on the Kings River. If this had not been so the proposed amendments would have served no purpose. The amendments were rejected precisely because they would have changed reclamation law, which both sides assumed to be applicable to such projects as section 8 read.
This conclusion was reaffirmed the following day in the course of Senate consideration of a proposal by Senator Murray of Montana to transfer “all functions, powers, duties, and projects” of the Secretary of War with respect to water conservation reservoirs in the west to the Secretary of the Interior, thus completely ousting the Secretary of War from these activities.60 Senator Murray based his proposal in part upon a desire to assure “that the Federal reclamation laws, with their various provisions for the development of family-size farms and the prevention of speculation in lands, should be made applicable to all reservoir projects in the west.” Senator Murray continued, “If the policy of the family-size farm . . . is to be accomplished, then these projects must be built, operated, and maintained by the Bureau of Reclamation under the reclamation laws.”61
In response, Senator Overton assured the Senate that Senator Murray’s objectives with respect to the application of reclamation law to irrigation in projects authorized by the bill would be achieved under section 8, which would make reclamation law applicable to the irrigation features of projects constructed by the Engineers. Senator Overton made this point with specific reference to projects in the Sacramento-San Joaquin River Basin. After referring to the President’s suggestion that the federal agency with the dominant interest in a particular project should construct it, Senator Overton continued:
The able junior Senator from Montana has made considerable comment in reference to the Sacramento and San Joaquin Rivers and the Central Valley, in California. The principle to which I have just referred was carried out in respect to the projects contained in the bill which were authorized for those streams. The testimony shows, I think rather conclusively, that the projects herein authorized to be constructed by the Army engineers are ones in which flood control predominates over irrigation. Of course, the Senate will understand that, insofar as irrigation is concerned, all surplus water which can be used for irrigation is turned over to the Department of the Interior, and the method of irrigation and the operation of the irrigation works are under the control of the Department of the Interior.62
Senator Overton also informed the Senate that the Corps of Engineers “had absolutely no objection whatsoever to the irrigation and power amendments [sections 8 and 5] which were suggested by the Secretary of the Interior . . . and were subsequently incorporated in the pending bill. The engineers stated that they were perfectly willing ... to turn over to the Bureau of Reclamation the distribution of all surplus water held back by the dams [1111]*1111constructed by them, the distribution of which would come under the reclamation law, or would follow whatever method Congress might determine upon.”63 Senator Murray’s amendment was then rejected.
The Senate adopted the committee’s proposed substitution of the present section 8 for section 6 of the House bill. The Senate version was accepted by the conference committee, and enacted into law with minor modifications not pertinent here. During the brief Senate debate on the conference report, Senator Overton, the flood manager of the bill, and Senator Hill, the Acting Majority Leader, engaged in the following colloquy for the express purpose of removing any possible doubt as to the applicability of section 8 to the Kings River project:
Mr. HILL. There still seems to be confusion on the part of some Senators with reference to the application of reclamation laws in regard to some of these projects.
I heard the distinguished senior Senator from Louisiana, when the bill was under consideration, and I think he made it very clear. However, I wish to ask this question: Is it not a fact that section 8 of this bill, as agreed to in conference, makes some reclamation laws applicable to the handling of irrigation water of any of the projects, including California projects, where it is found that irrigation may be carried out? I ask the Senator in charge of the bill whether it is not a fact that the President wanted the California projects in this bill constructed under the Bureau of Reclamation so that the water policies would conform to reclamation laws?
Mr. OVERTON. The Senator is correct with respect to the projects in the so-called Central Valley of California. The President wrote me and the chairman of the subcommittee in this regard. However, in view of the fact that the Senate amendment made not only the California projects but all such projects subject to irrigation laws, and in view of the fact that the House concurred in this action by agreeing to section 8 of the Senate bill, I am sure that the President will feel that we have met the problem that he raised. Section 8 of the bill clearly places reclamation uses of water from these projects under the Secretary of the Interior and under the applicable reclamation laws. No project in this bill which may include irrigation features is exempted from the reclamation laws.
Mr. HILL. I thank the Senator.
Mr. OVERTON. The Senate amendment made not only the California projects, but all such projects subject to the irrigation law. In view of the fact that the House concurred in that action by agreeing to section 8 of the bill, I am sure the Senator from Alabama will feel that we have met the question which he has raised. As I stated a while ago, section 8 of the bill clearly places reclamation uses of waters from all projects authorized in this bill under the Secretary of the Interior, and under the applicable reclamation laws.64
The report of the House conferees, though in general terms, also made it clear that section 8 reflected the wishes of the Secretary of the Interior with respect to the application of reclamation law to utilization of multiple-purpose projects for irrigation.65 There is nothing in the brief House debate on the conference report to contradict this interpretation or the more explicitly expressed views of Senators Hill and Overton.66
Appellees’ general response to this overwhelming evidence of congressional purpose contrary to their position is to ignore it. In a variety of ways appellees press the argument that Congress did not intend that reclamation law, and particularly acreage [1112]*1112limitations, would apply to the Kings River project because the dominant need for Pine Flat Dam was flood control, a matter within the special expertise of the Corps of Engineers; because private irrigation facilities were already in existence in the project area and no additional irrigation facilities were to be constructed; because the water of the Kings River had been completely appropriated and no additional water would be made available by the project; and because the project would bring no additional arid land under irrigation. The obvious difficulty with this argument is that it is contrary to the whole tenor of the legislative history. As has been seen, the legislative struggle was waged on precisely this ground. The very considerations appellees now advance were pressed upon Congress. Congress deliberately decided that while the Corps of Engineers should build Pine Flat Dam on the Kings River and control its operation for flood control, Pine Flat and all other multiple-purpose dams thereafter constructed should be utilized for irrigation under the provisions of the reclamation laws. This was the very purpose of section 8; it was adopted with the Kings River project and other nearby projects specifically, and primarily, in mind.
Viewing the conflict in the broader perspective of the reclamation program as a whole, any other outcome would have been surprising. The reclamation program is not primarily one of bringing arid lands under irrigation for the first time. Congress was advised as early as 1924 that one of the first projects approved under the 1902 Act, if not the first, was the Salt River project in Arizona, in which nearly all of the land was privately owned and under irrigation through a system of private canals. The function of the federally financed reclamation reservoir was to furnish water storage needed to conserve and regulate the existing water supply. Six other similar projects were also called to Congress’ attention.67 At this early date, Congress was warned, “It seems certain that the aid of the Government will be sought in the future to rescue meritorious but distressed private projects . . . .”68 The forecast was accurate. The number of instances in which the federal project supplemented existing irrigation steadily increased. In 1961 it was estimated that 60 percent of the total reclamation acreage fell in this category.69 In the Madera Irrigation District, one of the projects involved in the Ivanhoe Irrigation District litigation, 85,000 of a total of 112,000 acres had been developed for irrigation before the federal project was authorized.70 The opinion in Ivanhoe takes note of the fact that there was widespread preproject reclamation and irrigation development before lands were brought within the Central Valley project. 357 U.S. at 283, 78 S.Ct. at 1179, 2 L.Ed.2d at 1321. So general is this phenomenon that a recent commentator has stated, “reclamation today generally supplies only supplemental water.”71 In most of the respects in which appellees seek to distinguish the Kings River project from other projects Congress has made subject to the reclamation laws, therefore, the Kings River project is not an exception, it is the rule.
Appellees assert, however, that the Kings River project is unique in the respect that all of the water of the Kings River had been appropriated, and the project therefore would produce no “new” or “surplus” [1113]*1113water.72 Appellees’ factual premise is questionable, but if it were not, it would not follow that the project does not confer substantial benefits justifying imposition of acreage limitations. The Corps of Engineers and the Bureau of Reclamation agreed that approximately half of the costs of Pine Flat Dam were allocable to irrigation benefits, resulting principally from regulation of the river flow.73 There would be no inherent unfairness in applying acreage limitations in these circumstances. The federally financed reservoir confers substantial economic benefits upon the landowners by making water available when it otherwise would not be. The price at which excess lands must be sold will include the whole of any value attributable to pre-existing irrigation facilities and water rights; only the increase in value attributable to the federal project itself will be excluded.74 If in the case of the Kings River project the increment is small, as appellees contend, the price appellees will receive for their excess lands will be only slightly below full market price; if it is large the difference will, and should be, concomitantly substantial. In any event, as with all of the other distinguishing features relied upon by appellees, Congress was fully apprised of the almost complete appropriation of Kings River water under existing agreements,75 and was urged not to authorize construction and operation of Pine Flat Dam by the Bureau under the reclamation laws for this reason, among others.76 Nevertheless, Congress decided that acreage limitations should apply.
Appellees go so far as to suggest that application of acreage limitation provisions to the Kings River project would be impractical, even absurd, and Congress cannot be thought to have intended this result. The President of the United States, the Secretary of the Interior, and the Commissioner of the Bureau of Reclamation repeatedly urged Congress to provide that the Kings River project and those adjacent to it should be built, maintained, and operated by the Bureau of Reclamation in full compliance with the reclamation laws, including [1114]*1114acreage limitations. It is unlikely that a position so insistently pressed by the persons most knowledgeable and in highest authority in the executive branch would be as questionable as appellees suggest. At the very least, Congress could reasonably conclude that what these men urged as required by the public interest and the historical reclamation policy was not illogical or absurd. And of course it was not.77
Appellees discuss only Tulare Lake Basin —which, they say, has no dwellings or economic source of domestic water, is subject to periodic flooding involving economic risks too great for small farmers to bear, and still has an erratic water supply. Assuming all of this, Tulare Lake Basin is not the Kings River project. The Basin includes just over 200,000 acres; the Kings River project contains 1,065,000 acres. No one suggests that it would be impracticable to apply acreage limitation provisions to the project land outside the Basin. Indeed, more than 80 percent of this land is now in individual ownerships in tracts of 160 acres or less. Presumably Congress rested its decision upon the feasibility of acreage limitation in the project as a whole, not the Basin alone, and properly so.
But even as to the Tulare Lake Basin, appellees’ argument is unsound. The lack of on-site housing and domestic water supply is irrelevant. Since 1910 Bureau regulations have provided that the statutory residence requirement is satisfied if the owner lives within 50 miles of his land;78 a glance at a map will reveal the presence of many communities within this distance of Tulare Lake Basin.79 Only a small part of Tulare Lake Basin is still subject to frequent flooding.80 If events were to establish that small individual operations were [1115]*1115not practicable on land subject to this residual flood risk, or as to which the water supply may still be too erratic, leasing or consolidation of ownerships would no doubt follow.81 Congress may well have recognized that even if these adjustments occurred, substantial public interests would have been served by initial breakup of excess holdings at nonspeculative prices. The value of the increased productivity of the land and the substantial nonreimbursable flood control subsidy would have been widely distributed rather than accruing to the few who happened to own large tracts of land when the dam was built. An opportunity would have been afforded for persons of modest means to purchase a small tract of land and establish a farm under the improved water conditions. Even if this should prove infeasible, the changes that did occur would at least reflect the benefits provided by the project; the agricultural economy that emerged would not be dictated by a landownership pattern that existed prior to the substantial public investment.
Appellees argue that section 8 is inapplicable to the Kings River project because section 10 of the Act authorized this project “substantially in accordance with the plans contained in House Document Numbered 630,” the report submitted by the Corps of Engineers. Appellees point out that this report recites the various characteristics of the Kings River service area and its water rights along the lines set out above, and, further, that the report says nothing to indicate that acreage limitations were to be imposed.82 But it is also true that there is nothing in the legislative history to support appellees’ premise that if Pine Flat Dam were built on Kings River by the Corps of Engineers in accordance with its plan, section 8 would not apply to the project. The legislative history is precisely to the contrary.83
Appellees also contend that the language of section 8 itself excludes the Kings River project.84 They argue that the third sentence of section 8 (on which the United States’ argument for application of reclamation law to the Kings River project rests) is modified by the first two sentences of section 8; and, therefore, that reclamation law applies to dams operated under the direction of the Secretary of War only if the conditions of the first two sentences are satisfied, including the condition that additional works be constructed by the government for irrigation purposes. No such works were built on the Kings River project; ergo, section 8 does not apply. This interpretation would make the third sentence wholly redundant. As the legislative history demonstrates, this sentence was intended to convey a great deal of meaning. Its message is clear from a careful reading of all three sentences, even without resort to the legislative history. The whole of section 8 applies, of course, only to projects that are being operated under the direction of the Secretary of War. The first two sentences deal with situations in which additional works are required to realize the irrigation potential of such a project. In these cases a feasibility determination must be made by the Secretary of War, and authorization for construction of the additional works must be obtained from Con[1116]*1116gress. Such additional works are then to be constructed, operated, and maintained by the Secretary of the Interior under the reclamation laws. The third sentence is general in coverage; it provides that all dams operated under the direction of the Secretary of War are to be utilized for irrigation only in conformity with the section, i. e., under the reclamation laws; thus bringing under those laws dams for which no additional irrigation facilities are required.
The legislative history verifies the correctness of this interpretation. In Judge Stone’s succinct analysis before the Senate subcommittee, section 8 prescribes “that where there are irrigation benefits in a flood control reservoir, or if there are other facilities to be constructed by the Reclamation Bureau, to make use of the water stored for irrigation, then there must be compliance fully with the reclamation law.”85 Congress was repeatedly advised that a well developed private irrigation system already existed on the Kings River, yet section 8 was adopted with the Kings River project and adjacent projects primarily in mind, for the specific purpose of making the reclamation laws, including acreage limitations, applicable. Moreover, the Senate refused to adopt the O’Mahoney amendment that would have exempted from section 8 “any dam . . . which supplements any existing locally operated irrigation system.”86 To read section 8 as appellees suggest would be to include by implication the substance of the O’Mahoney amendment that Congress expressly declined to adopt87 — an amendment specifi[1117]*1117cally directed at the Pine Plat Dam, among others.
Enough has been said to dispose of appellees’ related argument that section 8 was intended to apply only to the reclamation of “arid” lands (meaning, in appellees’ argument, lands not already under irrigation) because section 6 of the House bill used this adjective and section 8 was intended to accomplish only “technical” changes in the House version. Only a brief exposure to reclamation jargon is required to learn that all of the land area of the United States west of the 98th meridian is commonly referred to as “arid or semi-arid.” The only support for appellees’ argument is a self-serving statement by the water master for the Kings River Water Association in the course of the Senate committee hearings that section 6 of the House bill “will not affect us because we have no arid lands. Our irrigation systems are complete. . Consequently, that section should not apply to us.”88 No member of the Senate subcommittee commented on the water master’s statement. No further mention was made of this notion by either side during the hotly contested effort on the floor of the Senate to exclude the Kings River project and similar projects from section 8.
Some reliance is placed upon incidents occurring after the 1944 Act was passed. They appear to be both trivial and irrelevant. For example, Secretary Ickes claimed a “sweeping defeat of the California interests,”89 and drafted a presidential press release in much this tenor. President Roosevelt instead issued a moderate and restrained announcement. This is hardly a significant indication of the meaning of the statute, especially since there is no evidence that the President disagreed with the Secretary’s conclusion. A second example: The Chief of Engineers initially took the position that under section 10 the Secretary of War rather than the Secretary of the Interior was to negotiate repayment contracts with water users on the Kings River and Kern River projects.90 Eventually, albeit after some pressure from the White House, the Chief of Engineers joined with the Commissioner of Reclamation in a public announcement acknowledging that the Department of the Interior was to be the contracting agency and that the repayment contract was to be negotiated under reclamation law.91 Whatever the merits of the [1118]*1118controversy over which agency should negotiate the contract, it is clear from the legislative history as a whole that the terms negotiated were to be in conformity with the reclamation laws, and particularly with acreage limitation provisions. This was the conclusion reached by the Attorney General in his 1958 opinion. 41 Op.A.G. 377 (1958).
In sum, the Flood Control Act of 1944 made the provisions of section 46 of the Omnibus Adjustment Act of 1926 applicable to the Pine Flat project.
II
We consider next whether, by repaying construction charges, owners of excess lands may avoid the obligation under section 46 to execute recordable contracts with the Secretary of the Interior providing for the sale of their excess lands at ex-project prices.92 This is the more far-reaching of the two grounds for the district court’s decision since it affects all federal reclamation projects subject to section 46 of the 1926 Act, not just those authorized in the Flood Control Act of 1944.93
It will be demonstrated in the discussion that follows that appellees’ “payout” theory is not supported by the language of section 46, the purpose and legislative history of the section, or the administrative practice of the Department of the Interior.
The Statutory Language
Nothing in section 46 suggests that owners of excess lands may at their option prepay construction charges in lieu of agreeing to sell their excess lands at non-speculative prices. The language of the section is unequivocal and unqualified: (1) “No water shall be delivered” from any new project until the Secretary of the Interior has contracted with an irrigation district or districts for payment of costs of construction; (2) such contracts “shall provide that all irrigable land held in private ownership by any one owner in excess of one hundred and sixty acres shall be appraised . . . and the sale prices thereof fixed by the Secretary on the basis of its actual bona fide value . without reference to the proposed construction of the irrigation works”; and (3) “no such excess lands so held shall receive water from any project ... if the owners thereof shall refuse to execute valid recordable contracts for the sale of such lands . at prices not to exceed those fixed by the Secretary . . . .”94
[1119]*1119The language attaches no significance to repayment of construction charges. If owners of excess land were to receive project water but escape the obligation to contract to sell excess holdings at ex-project prices by repayment of construction costs, this means of avoiding the apparently absolute condition imposed by section 46 would have to be implied.
For reasons which follow, implying such an exception to the mandate of section 46 would be unwarranted. As will be shown, such an exception would frustrate the purpose of Congress to secure the division and redistribution on a nonspeculative basis of large private landholdings receiving the subsidy of government-financed irrigation benefits. It would be inconsistent with the legislative and regulatory antecedents of section 46 of the 1926 Act, and particularly with section 12 of the Reclamation Extension Act of 1914.95 It would be contrary to interpretive conduct of the Department of the Interior in administering the reclamation laws, beginning shortly after the adoption of the Reclamation Act of 190296 and continuing to date, with a relatively brief hiatus during the 1950’s founded upon an obviously mistaken and soon repudiated ruling.
The Congressional Purpose
It is a basic goal of the reclamation laws to create family-sized farms in areas irrigated by federal projects. It is also a basic goal of the reclamation laws to secure the wide distribution of the substantial subsidy involved in reclamation projects and limit private speculative gains resulting from the existence of such projects. Public lands on reclamation projects are made subject to entry under the homestead laws in tracts of 160 acres or less in order to preserve the public domain for actual settlers.97 Similarly, the 160-acre limitation and the requirement in section 46 of the 1926 Act that excess lands be sold at prices excluding enhancement of value from the existence of the project were intended to effect the breakup of large tracts of private lands on reclamation projects and assure the redistribution of such lands in small tracts at nonspeculative prices.98
In Ivanhoe Irrigation District v. McCracken, supra, 357 U.S. at 292, 78 S.Ct. at 1184, 2 L.Ed.2d at 1326, the Supreme Court recognized the vital role acreage limitation provisions play in accomplishing the historic purposes of the reclamation laws:
[1120]*1120From the beginning of the federal reclamation program in 1902, the policy as declared by the Congress has been one requiring that the benefits therefrom be made available to the largest number of people, consistent, of course, with the public good. This policy has been accomplished by limiting the quantity of land in a single ownership to which project water might be supplied. It has been applied to public land opened up for entry under the reclamation law as well as privately owned lands, which might receive project water.
And at 297, 78 S.Ct. at 1886, 2 L.Ed.2d at 1329:
[The 160-acre limitation] is a reasonable classification to limit the amount of project water available to each individual in order that benefits may be distributed in accordance with the greatest good to the greatest number of individuals. The limitation insures that this enormous expenditure will not go in disproportionate share to a few individuals with large land holdings. Moreover, it prevents the use of the federal reclamation service for speculative purposes. In short, the excess acreage provision acts as a ceiling, imposed equally upon all participants, on the federal subsidy that is being bestowed.
Any means of avoiding the acreage limitation and recordable contract requirements of section 46, including the “payout” theory advanced by appellees, would necessarily threaten the realization of these purposes.
Under appellees’ theory, the very persons against whom the requirements of section 46 are directed, the owners of excess lands, could avoid these requirements at their option by repaying the costs of construction allocated to irrigation. It is probable that they would elect to do so. The benefits bestowed by a reclamation project often exceed the costs landowners are required to repay.99 Users of project water for irrigation are not charged with project costs attributable to navigation, flood control, salinity prevention, production of hydroelectric power, storage of water for industrial and municipal uses, and other uses not directly related to irrigation.100 They may, however, receive substantial benefits from such nonreimbursable expenditures. Over half the cost of the Kings River project, for example, was allocated to flood control and was not charged to irrigators.101 Yet the benefit of flood control accrued almost entirely to irrigators through elimination of flood damage to soil, crops, and livestock in the Tulare Lake Basin102 — a portion of the Kings River service area in which excess holdings predominate. Obviously, it would be to the advantage of the owners of excess land to pay off construction costs allocated to irrigation and retain their excess lands, enhanced in value by this substantial additional subsidy, or sell them at prices reflecting the subsidy.103 Moreover, the value at[1121]*1121tributable to improved productivity of the land when irrigated may exceed the cost of irrigation facilities, even aside from the element of subsidy. Congress anticipated that this would be true, and was aware of the consequent serious potential for speculation.104 It was the purpose of the requirement of section 46 that excess lands be sold at ex-project prices to eliminate this windfall advantage.105 Thus, because of subsidy and increased productivity, the charges to be repaid by irrigators normally represent only a part of the enhancement in value resulting from the project. By paying off the allocated costs, large landowners would secure this enhanced value for themselves at a fraction of its worth.
Perhaps such a result might be justified if the provision in section 46 for a contract to sell excess lands at ex-project prices were nothing more than a device to induce immediate repayment of the government’s investment. But obviously it is not.106 It is the means adopted by Congress to achieve broader antimonopoly and antispeculation purposes conceived by Congress to be of importance to society as a whole. Section 46 was intended to accomplish the redistribution of large privately owned tracts at prices substantially below the actual value of such lands at the time of sale. It is irrational to suppose that Congress would have given an option to the owners of such excess lands to prevent the accomplishment of the purposes Congress sought to achieve — an option their self-interest would often compel them to exercise. They would be free to convert the product of large public investment to personal gain either by farming their entire holdings under the improved water supply or by selling or leasing all or a portion of those holdings at prices capitalizing the full benefits of the project. Congress’ intention to secure the breakup and redistribution of such private holdings at ex-project prices by means of the requirements of section 46 would be frustrated, and the subsidy-distribution and antis-peculation purposes of Congress would not be accomplished.107
[1122]*1122The record in this case illustrates the consequences of an implied “payout” exception to section 46. The Tulare Lake Canal Company has already paid the construction charges allocated to a substantial portion of project land. The circumstances surrounding this litigation strongly suggest that others would follow suit if it were determined that by doing so the landowners would be relieved of the obligation to sell their excess land at ex-project prices. The result would be to leave as much as 30 percent of the service area in holdings of more than 160 acres. Over 157,000 acres in the Tulare Lake Basin Water Storage District alone would remain in excess holdings averaging 2,600 acres each. There would be no distribution of the flood control subsidy realized by irrigators, no limitation on windfall gains resulting from construction of Pine Flat Dam, no opportunity for others to acquire small landholdings at reasonable prices and no attempt to establish family-sized farms in the Tulare Lake Basin and elsewhere in the Kings River service area.
C.
The Statutes and Regulations
It would be inconsistent with reclamation law as developed by statute and regulation over nearly 75 years to now imply a “payout” exception to the requirement of section 46 of the 1926 Act.
It is important to define the issue clearly. The question presented in this case is whether, by payment of construction charges, the initial breakup of excess landholdings in single ownership can be avoided — in other words, whether owners of excess lands may, by paying construction costs, retain those lands and secure the right to the use of project water on them. The question is not whether a person who has disposed of his excess holdings, or irrevocably committed himself in a recordable contract to do so, may thereafter acquire additional project lands when construction costs allocated to his 160-acre tract have been paid and other conditions precedent to the full vesting of the right to receive project water for that tract have been satisfied.
The two questions are quite different. If payout could relieve owners of excess land of the obligation to contract to sell such land, the acreage limitation could be lifted even before it was implemented, and the social purposes of the limitation could be totally frustrated. However, once excess lands have been sold or irrevocably committed to sale in tracts of no more than 160 acres at prices that do not reflect the existence of the project, the purposes of the acreage limitation have been realized to a substantial extent. An opportunity has been afforded for wide distribution of irrigation subsidy and windfall gain and for the establishment of family farms and small individual holdings. This will remain true even if individual owners thereafter expand their holdings beyond 160 acres by purchasing additional land with appurtenant fully vested water rights.
Moreover, when full payment has been made and a claim to use of project water on a 160-acre tract has ripened into a vested water right, another recognized policy of the law becomes relevant. It is an established principle of homestead law that “When the patent issued, the full legal title passed to the patentee. He could do with the land that which he saw fit, sell or give it away . . . .” Hartman v. Butterfield Lumber Co., 199 U.S. 335, 337, 26 S.Ct. 63, 64, 50 L.Ed. 217, 218 (1905). The same rule may govern a fully vested water right. Once complete legal title to such a right has been acquired, it can be argued that the right should be freely alienable; that no restraint should be imposed upon subsequent purchase or sale, including any limi[1123]*1123tation on the amount of land having appurtenant vested water rights that may be acquired.108
Whatever the merits of this proposition,109 it is not the issue here. Our question is whether the initial breakup of excess holdings may be avoided by “payout.”
With this distinction in mind, certain relevant conclusions may be drawn from the background of reclamation statutes and regulations in effect prior to passage of the 1926 Act. These will be summarized briefly in the paragraph that follows and discussed thereafter in greater detail.
For the policy reasons stated earlier, Congress has consistently sought to limit initial holdings of public and private lands eligible to receive reclamation project water to 160 acres. Grants of public land were expressly so limited in the original Reclamation Act of 1902. In the 1902 Act, Congress sought to achieve the breakup of large holdings of private land by limiting water delivery to 160 acres. In administering this statute the Department of the Interior sought to secure commitments to sell excess lands prior to delivering water, and, in most cases, prior to undertaking construction of a project. Under the complex regulatory scheme adopted by the Department, it would have been impossible to avoid this initial breakup of excess holdings by paying construction costs. Building on this administrative practice, Congress included provisions in the Reclamation Extension Act of 1914 and later in section 46 of the 1926 Act expressly requiring owners of private land to agree to sell excess holdings. There is no provision in any of these statutes authorizing avoidance of acreage limitations by payment of construction costs. There is no mention of such a theory in the legislative history of any of these statutes. Each statute evinces a continuing purpose to limit initial private ..holdings to 160 acres and compel the redistribution of larger estates. In adopting the recordable contract requirement in section 46 of the 1926 Act, Congress intended to strengthen the excess land limitation, not to weaken it. Accordingly, it would be inconsistent with the statutory and regulatory antecedents of section 46, as well as the immediate legislative history of that section, to imply an option to purchase immunity from initial breakup by means of “payout.”
(1) 1902-1912
Congress effectively restricted the size of individual holdings of public land on reclamation projects by providing in sections 3 and 4 of the Reclamation Act of 1902 that homestead entries on such projects would be limited to a farm unit of from 40 to 160 acres as the Secretary might determine to be required to support a family.110 Persons who entered a tract of 160 acres of project land under the homestead laws before the Secretary made this determination were required to relinquish or dispose of the portion of the original 160-acre entry in excess of one farm unit.111
[1124]*1124Congress sought to limit private land holdings on reclamation projects to 160 acres and bring about the division and redistribution of larger tracts by providing in section 5 of the 1902 Act that project water should not be sold for a tract in excess of 160 acres to any one landowner.112 Section 5 also required the owner of private land to reside on or in the neighborhood of the 160-acre tract receiving project water.113 The purpose of these provisions, as the House Committee on Irrigation of Arid Lands explained, was to “compel the breaking up of any large tracts now held for which water rights from Government works are to be obtained by limiting the area of lands the property of any one landowner for which a water right may be acquired to 160 acres and requiring residence or occupancy of the land by the owner.114
The provisions of the 1902 Act imposing acreage limitations on public land entries in reclamation projects accomplished Congress’ purpose and remain the law today. Clearly these provisions cannot be avoided by paying irrigation construction charges. The legislative history of the 1902 Act establishes that Congress intended the limitations imposed upon owners of private land in reclamation projects to accomplish precisely the same purposes in essentially the same way as the limitation imposed upon public lands in such projects.115 The reasons for rejecting a “payout” exception to these limitations with respect to public lands, rooted in the congressional purposes, apply equally to private lands.
For example, no one contends that an entryman has ever been permitted to obtain a patent from the United States for more than 160 acres of public land and a right to water to irrigate that land simply by paying the nominal fee for the land, satisfying residency and cultivation requirements, and repaying irrigation construction costs allocated to the larger tract. Yet appellees’ payout principle would permit just such a circumvention of the quantitative limitation imposed upon water rights granted by the government to private landowners. We can think of no reason why the result should be different because the private owner obtains water rather than land, especially since the right to reclamation project water generally constitutes a much more substantial benefit than a patent to arid land.116
Nor does anyone suggest that if an entry on public land had been within the 160-acre limitation but exceeded the acreage later determined by the Secretary to constitute a farm unit capable of supporting a family, the entryman could have paid the construction charges on the entire entry and avoided the requirement that he relinquish or sell that portion in excess of a farm unit. The
[1125]*1125Department’s regulations would have foreclosed such a possibility.117 Again, the substantial reasons for denying public land entrymen the option to retain excess land and water by paying nominal land fees and the cost of constructing irrigation facilities also require denial to private landowners of the option to retain the right to receive project water for excess land.
Finally, the strength of the policy favoring distribution of reclamation benefits to actual settlers is reflected in the fact that entrymen on public land in reclamation projects have never been permitted to commute even the statutory residence and cultivation requirements by early payment, as other homestead entrymen do.118 The stricter limitations imposed on entrymen on public lands in reclamation projects by the 1902 Act were intended “to prevent the possibility of speculative holdings or the accumulation of large tracts in single ownerships.” 119 The same policy considerations argue against allowing private landowners to commute by early payment the requirement that they dispose of excess lands as a condition to receiving project water.
Steps taken by the Department of the Interior in administering the 1902 Act reflect the view that private lands on reclamation projects, like public lands, were to be made available for settlement in tracts of 160 acres or less, and that prepayment of construction costs would not have been an acceptable alternative to the accomplishment of this objective. The Department moved expeditiously to secure the initial breakup of excess private holdings. Retention of excess acreage and receipt of project water for that acreage after full payment of charges would have been incompatible with the means the Department adopted.
The feasibility of projects containing private lands often depended on bringing such lands under irrigation so that the costs of the project could be spread and the repayment obligation could be kept within practicable limits. Since under section 5 of the 1902 Act water could not be furnished to more than 160 acres in single ownership, it was necessary to insure, prior to construction, that large private holdings would be broken up and redistributed in tracts of this size.
The Department formed and utilized water users’ associations to accomplish this purpose.120 These associations became “an integral part of the project and directly associated with the Government in carrying out the details thereof,”121 including acreage limitations.122 The associations were required to enter into contracts with the United States guaranteeing repayment of each member’s share of the project’s construction charges,123 and the government in [1126]*1126turn promised to deliver water only to association members.124 To bring about the redistribution of excess private holdings, the Department approved a form of agreement between the association and its members requiring the latter to sell holdings in excess of 160 acres or to execute a trust deed empowering the association or a designee of the Secretary of the Interior to sell them.125 Since these agreements were entered into before the project was built, as a means of insuring the project’s feasibility,126 they were executed before construction costs could be estimated, much less repaid.127
The effect of these agreements was reinforced by departmental regulations. The Department required the filing of a water right application as a condition to receiving project water. An application for more than 160 acres would not be accepted from any one person.128 The limitation was absolute; there was no provision for an exception if construction charges were paid. Further, the applicant was required to belong to the water users’ association,129 which, as we have seen, would also require him to sell his excess land or execute a trust deed for its sale.130 Thus, the tender of full payment, either at the time of application or at some later date, would have come too late to avoid the initial breakup of excess holdings.
At least as early as April of 1912, a water right application would not be accepted unless it included all the applicant’s land.131 This provision, coupled with the overall limit of 160 acres to an application, also had the effect of requiring the applicant to dispose of holdings in excess of 160 acres before he could apply for project water.132
[1127]*1127All of these regulations are still in effect.133 Their language is as unqualified as that of the statutes they seek to implement. None accords any significance to the prepayment of construction charges.
(2) 1912-1914
Despite this elaborate system of controls through water users’ associations, trust deeds, water rights applications, and administrative regulations, Congress was disappointed in its expectation that the provision of the 1902 Act for withholding project water from excess lands would lead to the prompt breakup of large tracts of private land. In 1914 Congress adopted a more direct and effective means to accomplish this objective.
Before turning to the 1914 Act however, mention must be made of the Act of August 9,1912,134 for an inference drawn from a phrase in a proviso to a section of this Act was the principal basis for the Department’s recognition of a “payout” exception to acreage limitation requirements for a period of the 1950’s — indeed, as will be seen, it is the foundation upon which the entire “payout” argument ultimately rests.135
The 1912 Act was not directed to the acreage limitation problem. Its purpose was to enable entrymen and private landowners on reclamation projects to obtain title before final payment to use as security for loans needed to develop their farms.136 To that end, section 1 of the 1912 Act provided that a patent to public land or a water right certificate for private land would issue upon proof of residence, reclamation, and cultivation, and payment of construction charge installments then due. Section 2 gave the United States a lien for construction charges not yet due.137 Sec[1128]*1128tion 3 provided that a certificate evidencing satisfaction of the lien was to issue upon full repayment of construction charges. The proviso in question then appears, reciting, in substance, that no person shall “acquire, own or hold” more than 160 acres of land “for which entry or water-right application shall have been made ... before final payment in full of all installments of buildings and betterment charges shall have been made.”138 Proponents of the “payout” theory have inferred from the last quoted phrase that after construction charges have been paid the acreage limitation is no longer applicable, and, therefore, excess private holdings may be retained in the first place simply by paying construction costs.
The initial inference may be justified,139 although it is irrelevant to this case. But the final conclusion is clearly wrong. The essential distinction is that drawn at the outset of this section between the unqualified obligation to comply with the acreage limitation as a condition to first securing a right to project water, and the ability to buy and sell a right to such water once that right has vested. Section 3 speaks only to the latter point; it does not purport to address the question of initial breakup of excess holdings.
On its face, the proviso contemplates that it will apply to private lands “for which . water right application shall have been made.” As has been shown, under administrative practice and regulations in effect in 1912 an applicant was required to sell his excess lands or irrevocably commit them to sale before his water right application could be accepted. There is not a word in the legislative history of the 1912 Act intimating an intention to abrogate these regulations and administrative practices; the regulations were reissued in more explicit form in 1916, and, indeed, remain in effect today.140 Thus, the proviso to section 3 applies by its terms only to a person who has never owned more than 160 acres or who had already reduced his holdings to that size by selling the excess or executing a trust deed for its sale. The proviso deals with the problem of subsequent acquisition of additional project land by such a person; it does not apply to the initial retention of excess lands.
Sections 1 and 2 of the 1912 Act advanced the time at which a patent or water right certificate could issue. Under principles of homestead law referred to earlier, this might also have advanced the time at which project lands and water rights could be purchased and sold free of acreage limitations.141 The apparent purpose of the proviso to section 3 was to delay freedom to alienate and accumulate lands with vested project water rights until all construction charges had been repaid, even though a patent or water right certificate had [1129]*1129issued.142 This was the contemporaneous construction of the statute by the Secretary of the Interior, who, in recommending to the President that he sign the bill, stated that the purpose of the proviso was “to prevent the consolidation of holdings until such time as full and final payment of the building charges shall have been made.143
Interpretative instructions — -commonly known as the King Instructions — issued two years later by Will R. King, Chief Counsel of the Reclamation Service, construed the proviso to section 3 in this same way.144 The King Instructions treat the proviso as dealing only with the acquisition or purchase of project lands after the acquiring landowner has complied with acreage limitations and other conditions to obtaining a vested water right. Two previous departmental opinions had intimated that the proviso in section 3 of the 1912 Act limited to 160 acres the area for which a person could hold project water rights “even after he has discharged all his obligations to the Government, except for operation and maintenance” charges — i. e., that a project landowner was forever prohibited from expanding his holdings. Chief Counsel King read the proviso in light of the public land law principle supporting free alienability of rights that have vested “after having complied in full with the provisions of the law in order to acquire the title.”145 He concluded that additional lands could be acquired by a person holding a tract of 160 acres or less if he first paid all charges on his own tract or if the charges on the tract to be acquired had already been paid by the previous owner.
The King Instructions did not address the question of initial compliance with acreage limitations. Such compliance necessarily preceded any possible application of the King Instructions. In order to have “discharged all his obligations to the Government” or to have “complied in full "with the provisions of the law in order to acquire” a project water right and thereby invoke the public law principle of free alienability relied upon by the Chief Counsel, the purchasing and selling landowners would first have had to reduce their holdings to 160 acres as required by the regulations then in effect. Thus, the King Instructions, like the proviso to section 3 of the 1912 Act they construed, are relevant only to the subsequent acquisition of additional lands by persons who have never owned more than 160 acres of project land or have already reduced their holdings to that figure, or agreed to do so, in order to come into initial compliance with the acreage limitations.146 Excess landowners in the Kings River service area do not fall into any of these categories.
[1130]*1130If there could be any lingering doubt, the Reclamation Extension Act of 1914147 made it absolutely clear that no inference of congressional approval of a “payout” theory based on the 1912 Act could possibly apply to the purchase of immunity from the requirement that initial excess holdings of private lands must be broken up as a condition to receiving project water.
For a variety of reasons, the Department’s regulatory scheme to implement the mandate of section 5 of the 1902 Act was not as effectively enforced as it might have been. Large tracts of private land remained in single ownership in reclamation projects.148 Moreover lands sold pursuant to the trust deeds or directly by the original owners often commanded extraordinary prices from the actual settler, bestowing a windfall profit on the original owner and imposing an added burden on the settler.
Section 12 of the 1914 Act was designed to eliminate these problems on future projects. This provision gave the force of positive statutory law to the requirement that private landowners must agree at the outset to dispose of their excess holdings as a condition to receiving project water. Also, for the first time, it imposed controls on the price at which excess lands could be sold. Section 12 reads as follows:
That before any contract is let or work begun for the construction of any reclamation project hereafter adopted the Secretary of the Interior shall require the owners of private lands thereunder to agree to dispose of all lands in excess of the area which he shall deem sufficient for the support of a family upon the land in question, upon such terms and at not to exceed such price as the Secretary of the Interior may designate; and if any landowner shall refuse to agree to the requirements fixed by the Secretary of the Interior, his land shall not be included within the projects if adopted for construction.149
It is patent on the face of this provision that Congress did not intend to permit private landowners to avoid the necessity of agreeing to sell their excess land by prepaying construction charges. The section required landowners to agree to sell excess lands “before any contract [was] let or work begun for the construction” of the project. Under section 4 of the 1902 Act, the Department could not compute estimated costs of construction until after contracts had been let.150 Indeed, Congress had been advised that because final costs of construction so often exceeded original estimates, it was the Department’s policy not to announce construction charges until a reclamation project was completed.
To have permitted owners of excess land to avoid the requirements of section 12 by “payout” would also have been contrary to the repeatedly stated congressional purpose [1131]*1131to break up and redistribute large private landholdings at nonspeculative prices.152
In contrast, there is nothing to support the notion that the breakup of excess holdings at nonspeculative prices under section 12 of the 1914 Act could be avoided by paying construction costs, either in the legislative history153 or in any other provision of the 1914 Act.154 Moreover, as noted earlier, the pre-1914 regulatory scheme, incompatible with an option to retain excess acreage by paying construction charges, remained in effect after the passage of the 1914 Act.155
(3) 1914-1926
Section 46 of the 1926 Act was derived from section 12 of the 1914 Act.156 It was [1132]*1132designed to achieve the antimonopoly and antispeculation policies of the earlier statute more effectively by closing loopholes disclosed by the 1924 report of a special committee appointed by the Secretary of the Interior known as the Fact Finders.157 It is evident from the Fact Finders’ report, relevant congressional proceedings, and the provisions of section 46 that Congress intended to continue its policy of securing the initial breakup of excess holdings of private land and did not intend to allow this objective to be frustrated at the option of owners of excess land.
The Fact Finders’ report emphasized that the central purposes of the reclamation law were to encourage family farms, distribute the reclamation subsidy widely, and avoid speculation. It pointed out that large tracts of private land remained in private ownership and that speculation had not been eliminated; it noted that the reclamation law had been amended to require holders of excess lands to sell their surplus, but that the law had not fully accomplished its antimonopoly and antispeculation purposes.158
To meet these problems the report recommended “[t]hat no reclamation project should hereafter be authorized until all privately owned land in excess of a single homestead unit for each owner shall have been acquired by the United States or by contract placed under control of the Bureau of Reclamation for subdivision and sale to settlers at a price approved by the Secretary.” 159 A draft of proposed legislation attached to the report provided that as a general rule excess lands should be acquired by the United States and should then be made subject to disposition under the reclamation laws in the same manner as other public lands. The draft legislation provided that the alternative of requiring contracts to sell at prices approved by the Secretary — the model for the recordable contract requirement in section 46 of the 1926 Act— was to be utilized in connection with the large tracts held by federal land grantees, such as railroads.160 It was thought that intermediate acquisition by the United States of such large holdings would cause an unacceptable drain on the reclamation fund.161
Both alternatives proposed by the Fact Finders were incompatible with a “payout” theory. It could not have been thought that by paying construction charges after the project had been completed and those charges had been determined, the original owner of excess lands could compel the government to terminate the interest of any intervening settler on the excess land and relinquish the government’s fee title to such land, or surrender the government’s vested contract right to sell the excess land of federal grantees at prices fixed by the Secretary.
The differences between section 46 of the 1926 Act and the recommendations of the [1133]*1133Fact Finders are minor. They reflect no weakening of the congressional will to require the breakup of excess holdings, and no approval of avoidance by payout.
As finally passed, section 46 adopted the Fact Finders’ alternative of requiring owners of excess land to contract to sell such land at prices fixed by the Secretary and extended this procedure to all owners of excess land, rather than confining it to federal grantees. The Fact Finders’ report does not suggest that this alternative was to be any less absolute than the alternative of outright acquisition by the United States. The reason for the choice was concern that acquisition by the United States would prove costly and productive of delay no matter who owned the excess land.162 The congressional committee was told that any alternative that would assure sale of excess lands directly to actual settlers at nonspeculative prices would serve Congress’ purposes just as well.163 The committee was advised, in effect, that the alternatives of intermediate acquisition by the United States and direct sale to actual settlers pursuant to a contract placed under the control of the Department were equivalents,164 and proceeded on that assumption.165
Under the Fact Finders’ proposal, construction could not have begun until all owners of excess lands transferred such land to the United States or contracted to sell it at government-fixed prices, just as under section 12 of the 1914 Act. As we have shown, subsequent “payout” could not have avoided disposal. Section 46 as passed allows construction to proceed, but bars delivery of project water to excess land until a recordable contract for its sale is executed. The reasons for the change are clear, and reflect no diminution of Congress’ determination to break up excess landholdings. In the course of committee hearings, it was pointed out that under the Fact Finders’ proposals, construction of a project might be prevented or delayed if even one owner refused to transfer or contract to sell excess land;166 Congress obviously thought it necessary to avoid such an impasse.167 In addition, Congress thought it would be difficult to negotiate contracts requiring sale of excess holdings at nonspeculative prices until the government evidenced its good faith by affirmative action. Congress was assured that its purpose would be achieved as readily by conditioning the delivery of water, rather than the commencement of construction, upon the execution of the desired contracts.168
[1134]*1134Thus, neither respect in which section 46 of the 1926 Act differs from the Fact Finders' recommendations reflects a purpose to soften the impact of acreage limitations.
Section 46 was adopted to meet two problems that had developed in the administration of the 1914 Act.169 Ironically, the means adopted by Congress to close one of the loopholes in the 1914 Act is seized upon to support the theory that acreage and price controls may be avoided completely by “payout.” It is argued that the clause following the recordable contract provision in section 46170 permits an owner of excess land to free himself of the requirement that the Secretary approve the price at which such lands are sold by paying half of the construction charges attributable to them, and thereby recognizes at least a partial “payout” theory. This is a patent misconstruction of the meaning and purpose of the clause in question. Its purpose and effect was to strengthen the Secretary’s hand in dealing with speculative sales, not to weaken it by permitting avoidance of price controls by partial “payout.”
[1135]*1135The portion of section 46 preceding the clause in question restates the absolute requirement, drawn from the 1914 Act, that to obtain project water, initial owners of excess land must agree to sell such land at prices fixed by the Secretary. The purpose of this provision, as we have seen, is to compel the initial sale of excess lands at prices excluding enhancement from the presence of the project. The 1914 Act did not, however, give the Secretary authority to control the price at which the excess lands were thereafter resold by the purchaser. As a consequence, the landowners avoided the price limitation on the sale of excess lands by selling such lands to middlemen who then resold them at unregulated prices, often on the original owner’s behalf.171 The clause in question was included in section 46 to meet this problem, at least in part, by enabling the Secretary to control the price at which some resales were made.172
The construction of the clause suggested by “payout” proponents would permit the owner of excess land to sell that land at speculative prices by paying half the construction costs. In many if not most instances, as we have seen, owners of land would exercise this option, even at twice the price. Thus the construction suggested by appellees, though not affecting the requirement that excess land be sold, would effectively negate the bar against sale of excess land at speculative prices. Why Congress would wish such a result is not suggested. It would conflict directly with Congress’ intent to place additional curbs on speculation and windfall gain. When the clause in question is confined to sales subsequent to the initial sale of excess lands, as intended, it does not embody a partial “payout” principle as appellees argue.
In sum, the historical background of section 46 of the 1926 Act leaves no room for an implied option to avoid initial breakup of excess landholdings by paying construction costs. Admittedly, no such option is available as to public lands, and the same purposes were intended to be served by the application of the acreage limitation to private lands. The regulations formulated by the Department of the Interior before 1926 contemplated the initial breakup of excess private holdings, and were incompatible with avoidance of that requirement by a “payout” of construction costs. The Act of 1912 is not to the contrary; it is concerned with acquisitions after rights have vested, not with the breaking up of initial holdings — a condition to the vesting of rights in the first instance. The Act of 1914 in effect adopted the procedure reflected in the Department’s administrative practices and regulations. On its face, the 1914 Act is inconsistent with the notion that initial breakup of excess lands could be avoided by paying construction costs. Section 46 of the 1926 Act is based upon the 1914 Act. The 1926 Act was intended to make the acreage limitation and antispeculative provisions more effective, not less. The Fact Finders’ report and relevant legislative hearings reflect that the means adopted in section 46 was considered to be equivalent, for these purposes, of outright acquisition of excess lands by the government at the outset — an arrangement that would have made avoidance by “payout” impossible.
[1136]*1136D.
Administrative In terpretation
It is argued, however, that the conduct of the Department of the Interior in administering the statute indicates that the Department inferred an exception to section 46 if construction costs were paid. Except for a relatively brief period in the 1950’s, the administrative interpretation is either inferentially or expressly to the contrary.
As has been shown, the regulations adopted before 1926 were premised upon initial breakup of excess holdings and were incompatible with avoidance of that requirement by paying construction charges. This is not to imply that the regulations were deliberately designed to this end. The suggestion that disposition of initial excess acreage could be avoided by paying construction charges does not appear to have occurred either to Congress or to the Department of the Interior during this period. There is no evidence of a single instance between 1902 and 1926 in which the Department agreed that repayment of construction charges would permit the original owner of excess lands to receive project water for such lands without first selling or agreeing to sell them.173
From 1926 to the middle 1940’s the case for administrative recognition of a payout exception to section 46 rests primarily upon passages culled from less than a score of letters and internal memoranda prepared in the course of over 15 years of the Department’s daily operations. This material was selected from the Department’s files in 1955 in response to a congressional inquiry into the legitimacy of a proposed “payout” option in contracts affecting owners of excess lands in the Kings River project. The showing is hardly impressive. The volume of material is strikingly meager for so extensive a program. More important, nearly all of the material in the collection appears on its face to be irrelevant to appellees’ “payout” theory. Almost all of the excerpts are generalized statements derived from section 3 of the 1912 Act and the King Instructions. They do not concern the initial breakup of excess holdings, but the subsequent purchase, sale, or consolidation of vested rights by water users who had already reduced their holdings to 160 acres or committed themselves to do so.174
[1137]*1137Since the middle of 1940’s, the history of the acreage limitation has been to a large extent a reflection of the unsuccessful struggle of owners of large tracts of land in California, including the Kings River area, “to obtain the Federal irrigation investment without accepting the acreage limitations.” 175
An effort to obtain legislative exemption from acreage limitations of the Central Valley project was defeated in 1944.176 In the same year landowners in the Kings River service area, especially those in the Tulare Lake Basin, also sought a legislative exemption from acreage limitations for the Kings River project and other nearby projects during consideration of the Flood Control Act. Appellees argue here that the Flood Control Act did in fact include both a total exemption and a “payout” option. The reasons for rejecting the argument that Congress granted landowners on the Kings River project a total exemption in the Flood Control Act were set out in Part I of this opinion. The fallacies in the somewhat inconsistent argument that Congress in the same statute also authorized the landowners to escape section 46 of the 1926 Act by “payout” are summarized in the margin.177 In 1947 a proposal to exempt projects in California, Colorado, and Texas died in committee after extensive [1139]*1139hearings.178 In 1950 and 1951 bills were introdueed to relieve Kings River landowners of acreage limitations in return for a lump sum payment of construction costs; neither passed.179
Following this series of defeats in Congress, Kings River water users turned to the Department of the Interior for relief. These efforts also ultimately failed, but only after a highly controversial period of several years, beginning in late 1953, during which the Department authorized and conducted negotiations with Kings River water users on the premise that lump sum prepayment would relieve them of acreage limitations.180 Only during this relatively brief period, more than 25 years after passage of the last comprehensive acreage limitation statute, did the Department officially adopt appellees’ “payout” principle.
Proponents and opponents alike attributed the origins of the theory of “payout” as an alternative to contracting to sell excess lands solely to a memorandum prepared in 1947 by Felix S. Cohen, Associate Solicitor of the Department of the Interior.181 The Cohen opinion was thought to have established that payment of construction charges by an irrigation district released its eonstituent owners of excess land from the obligation to execute recordable contracts as a condition precedent to receiving project water for that land.
The reasoning of the Cohen opinion is as follows: (1) Under the proviso to section 3 of the 1912 Act as interpreted in the King Instructions, payment of construction charges frees the land from acreage limitations; (2) section 3 of the 1912 Act and section 46 of the 1926 Act are integral parts of a comprehensive land-limitation plan; (3) the same rule should therefore apply to section 46 of the 1926 Act. That is the whole of the argument.
The obvious error in this reasoning is that it ignores the distinction between the initial breakup of excess holdings and the subsequent purchase, sale, and consolidation of water rights once they have been acquired. As we have seen, section 3 of the 1912 Act and the King Instructions apply only to the latter and not to the former. They recognize a right to sell and acquire vested water rights without regard to the 160-acre limitation. They assume compliance with the conditions precedent to obtaining such vest[1140]*1140ed water rights, including the requirement that initial excess holdings be disposed of— imposed by regulation prior to 1914 and thereafter by the express provision of section 12 of the 1914 Act and section 46 of the 1926 Act.
With this error corrected, nothing remains. The Cohen opinion does not discuss the unqualified requirement of initial breakup in section 12 of the 1914 Act, essentially re-enacted as section 46 of the 1926 Act. It does not explore the legislative history of the acreage limitation provisions in the 1902,1912,1914, or 1926 acts, or Congress’ purpose in enacting any of them. It does not discuss the Department’s regulations or administrative practices. It gives no consideration to the consequences of the rule it announces.
The surprising superficiality of the Cohen opinion may be explained by the political context in which it was issued. It appears to have been a hastily contrived means to achieve an end thought to be of overriding importance to the Department. For whatever reasons, the Bureau of Reclamation had not moved as decisively or uniformly as it might have to enforce acreage limitations.182 A survey of reclamation projects completed in 1946 and a conference of key Bureau personnel in early 1947 revealed substantial noncompliance with the acreage limitations on many projects.183 Senator Downey of California and others were marshaling support for a renewed attempt to entirely exempt projects in California, Colorado, and Texas from acreage limitations.184 Department and Bureau officials wished to present a record of enforcement to Congress as part of an overall defense of acreage limitation provisions.185 It was considered impracticable at that late date to secure the individual recordable contracts the Bureau had failed to require as a precondition to delivering project water when projects were first opened. The Cohen opinion was prepared as a part of a program to meet this problem. It was transmitted to field offices to provide a means for achieving rapid “compliance” with acreage limitations which could then be reported to Congress, albeit “compliance” by avoidance through payment of construction charges.186 Secretary of the Interior Oscar Chapman and Commissioner of Reclamation Michael Straus both regarded this procedure as a remedial measure to be applied to then-existing projects, as to which there had been a history of substantial, long standing nonenforcement. It was not regarded as a policy of general applicability permitting all landowners to avoid the acreage limitation as a matter of course.187
Commissioner Straus later changed his position, offering the Cohen opinion as justification for acceptance of lump sum pre[1141]*1141payment from Kings River water users.188 Secretary Chapman disagreed, insisting that the Cohen opinion and the administrative letter transmitting it to the field had not established a general policy applicable to new projects, especially Pine Plat Dam.189 In December 1952, Secretary Chapman challenged the authority of the Cohen opinion for any purpose, pointing out that it had not been submitted to the Secretary for approval.190 The Secretary instructed Commissioner Straus that the Bureau was not to accept full payment of construction charges as an alternative to compliance with acreage limitations, and, specifically, that no such contract was to be negotiated with the Kings River Water Association.191
After the change of Administration in 1953, the Bureau was authorized to negotiate a Kings River repayment contract embodying the lump sum prepayment principle. Sole reliance was placed on the Cohen opinion.
Late in 1955, subordinate Bureau officials completed negotiation of a contract with the Kings River Conservation District, a service-area-wide entity created for the purpose of contracting with the United States for Pine Flat repayment. The con[1142]*1142tract included a provision allowing individual landowners to avoid sale of their excess lands at nonspeculative prices by paying that portion of the total construction charges that could be fairly allocated to their individual holdings.192 Protests followed. The Department advised correspondents that questions of law and policy underlying the contract were being reviewed.193 In mid-1957, Solicitor Elmer F. Bennett issued an opinion concluding that “Congress has not authorized accelerated payments by individual landowners of their aliquot part of the district liability as a means of evading excess land limitations.”194 Acting upon this opinion, the Secretary disapproved the proposed contract, stating that to permit individual prepayment to have the suggested consequence “would reduce the statutory limitations to a mere shadow. This would make the test, not one of public policy, but solely one of the financial capability of each landowner to purchase immunity from the statutory restrictions.”195
Negotiations were resumed, but with a view toward executing separate repayment contracts with the various canal companies and irrigation and water storage districts in the service area. Proposed contracts were again agreed upon. They include a provision that upon payment of all construction charges by the contracting district or company its constituent landowners would be relieved of the requirement that they sell excess lands at nonproject prices.196 Secretary of the Interior Fred A. Seaton declined to execute the contracts. Because of the considerable opposition to the Department’s position, the widespread public interest in the question, and its “transcendent importance in the administration of the Federal reclamation laws,” he requested an opinion of the Attorney General on the basis of which the “payout” issue might “definitely be set at rest within the Executive Branch.”197 The effect of the Secretary’s request, transmitted one day before he left office, was to defer the final decision on “payout” to the incoming administration.198 The incoming Attorney General returned the proposed contracts to the Department of the Interior for initial consideration. In December 1961 Solicitor Barry issued an opinion concluding that the “payout” provision in the proposed contracts was unlawful. In striking contrast to the Cohen opinion, Solicitor Barry’s memorandum fully exposed and explored all aspects of the problem, including the purposes of the excess land limitations, the terms and legislative history of each of the relevant statutes, the regulations issued by the Department, the administrative practices of the Department over the years, and the consequences of the alternative solution. On the basis of this examination, Solicitor Barry concluded that “[pjayout is not relevant to the recordable contract requirement of Section 46 of the 1926 Act,” but only to subsequent consolidation of vested water rights first acquired in accordance with the law.199 Attorney General Robert F. Kennedy concurred in Solicitor Barry’s conclusions.200 The doctrine thus established, rejecting payout as an alternative to compliance with section 46 of [1143]*1143the 1926 Act, has remained Department policy to the present.201
In sum, except for a period of a half dozen years, the administrative practice of the Department has been either inferentially or expressly contrary to appellees’ theory of “payout” as an alternative to initial redistribution of excess lands. The theory’s sole claim to legitimacy was the 1947 Cohen opinion. That opinion was invoked beyond its intended purposes. In any event, it was patently wrong. Its authority was soon challenged; it remained hotly contested throughout; and it was soon overruled. The substance of the Department’s construction of section 46 during this brief interlude must be rejected in view of the repeatedly endorsed public policies involved in limiting initial holdings of private lands receiving water from federal reclamation projects, the compelling legislative history of each successive excess land statute, the unambiguous regulations and early administrative practice on which the 1926 Act was built, and the general scheme of enforcement of the acreage limitations since 1902.
There is no basis for implying an exception to the absolute language of section 46 that would permit excess landowners to escape the obligation of that provision by payment of construction charges.
The Kings River project is subject to the reclamation laws. Landowners in that project must execute recordable contracts to sell their excess land at ex-project prices in compliance with section 46 in order to receive project water for their excess lands, even if the irrigation district or other contracting agency through which they receive project water repays its share of the irrigation costs of the Pine Flat Dam.
Reversed.
Related
Cite This Page — Counsel Stack
535 F.2d 1093, 6 Envtl. L. Rep. (Envtl. Law Inst.) 20, 1976 U.S. App. LEXIS 11993, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-tulare-lake-canal-co-ca9-1976.