LAY, Circuit Judge.
United Family Farmers, Inc. (UFF), a nonprofit corporation organized under the laws of South Dakota, and individual farmers sought injunctive relief against the Secretary of the Interior to halt construction of the initial stage of a reclamation project known as the Oahe Diversion Unit of the Missouri River Basin Project.
UFF is composed of approximately 900 members, the majority of whom either reside or own land in Spink and Brown counties in South Dakota. The initial stage of the project is to provide for diversion of water from an existing reservoir for industrial and recreational uses, flood control, and the irrigation of 190,000 acres in the two counties.
UFF originally pled nine separate claims for relief; this appeal involves only UFF’s amended ninth claim,
which sought to enjoin further construction of the initial stage because of the Secretary’s failure to comply with § 12 of the Reclamation Extension Act of August 13, 1914, 43 U.S.C. § 418
Section 12 requires that “before any contract is let or work begun for the construction of any reclamation project,” the Secretary must have executed recordable contracts with
all
excess land owners within the project for the sale of their excess land to settlers at government-fixed prices. The Secretary conceded that
all
of the excess land owners had not executed recordable contracts. Nonetheless, the district court granted summary judgment for the defendants. The court ruled that § 46 of the Omnibus Adjustment Act of May 25, 1926, 43 U.S.C. § 423e
had superseded § 12 on
projects built after 1926. He found § 46 allows construction to proceed even though all the excess land owners have not executed recordable contracts, but prohibits the delivery of water to excess land until a recordable contract for its sale has been executed. The district court certified the judgment for appeal under Fed.R.Civ.P. 54(b).
The issue on appeal turns on the propriety of the district court’s ruling that § 46 of the Omnibus Adjustment Act of 1926 has superseded § 12 of the Reclamation Extension Act of 1914. We find the ruling correct and affirm the grant of summary judgment.
UFF urges that the 1926 Act did not expressly repeal § 12 and that the law looks with disfavor upon repeals by implication.
Posadas
v.
National City Bank,
296 U.S. 497, 503, 56 S.Ct. 349, 80 L.Ed. 351 (1936).
Plaintiffs argue that § 46 has not impliedly repealed § 12, because the two sections are capable of coexistence. They contend § 12 prevents construction until all the owners in the project agree to sell their excess lands at government-fixed prices. After construction is completed and the project is turned over to the irrigation district for management and debt retirement, UFF urges, § 46 then prevents the irrigation districts from delivering water to landowners who fail to comply with acreage limitation provisions.
In this way, UFF asserts, the overall intent of the reclamation laws is given effect by preventing large landowners from securing speculative land prices.
See Ivanhoe Irrigation District
v.
McCracken,
357 U.S. 275, 78 S.Ct. 1174, 2 L.Ed.2d 1313 (1958).
To determine whether the two sections are capable of coexistence requires an inquiry by this court as to whether Congress clearly and manifestly expressed an intention that § 46 was to supersede § 12.
Mor
ton v. Mancan,
417 U.S. 535, 550-51, 94 S.Ct. 2474, 41 L.Ed.2d 290 (1974).
The first restrictions on excess lands in reclamation projects was § 5 of the Reclamation Act of 1902, 43 U.S.C. § 431. Section 5 required that water could not be furnished to more than 160 acres in a single ownership. This restriction was to promote the anti-monopoly and anti-speculation policies of the reclamation laws. Because § 5 did not fully effectuate these policies, Congress enacted § 12 of the 1914 Act. Section 12 required that excess land owners must agree, prior to construction, to dispose of their excess lands. In addition § 12 imposed controls on the price at which excess land could be sold. Despite these new restrictions the promise of the reclamation laws was not fully realized. To determine what additional measures were needed to achieve these policy goals, the Secretary of the Interior appointed a committee known as the “Fact Finders.” In 1924 the Fact Finders presented their report.
Among their numerous proposals was the following recommendation:
That no reclamation project should hereafter be authorized until all privately owned land in excess of a single homestead unit for each owner shall have been acquired by the United States or by contract placed under control of the Bureau of Reclamation for subdivision and sale to settlers at a price approved by the Secretary. This price to be considered in determining what land and water will cost settlers and hence the feasibility of the project under the payment conditions of the law.
In 1924 with the full support of President Coolidge and the Fact Finders, the Department of the Interior submitted H.R. 8836 to the House Committee on Irrigation and Reclamation.
Hearings on H.R. 8886 and 9611 before the House Committee on Irrigation and Reclamation,
68th Cong., 1st Sess. (1924). The fundamental purpose of the bill was to provide a new plan for repayment to the federal government of the construction costs of future irrigation projects.
One of the major changes in the
repayment system proposed by the bill was that the government would execute the repayment contracts with irrigation districts organized under state law. In the past the government entered into repayment contracts with the individual landowners. This change was allegedly designed to provide for better management of the projects and to further insure repayment.
Id.
at 35. The bill’s mandate was that these contracts must be entered into before any money could be expended for construction for “any
new
project or any
new
Free access — add to your briefcase to read the full text and ask questions with AI
LAY, Circuit Judge.
United Family Farmers, Inc. (UFF), a nonprofit corporation organized under the laws of South Dakota, and individual farmers sought injunctive relief against the Secretary of the Interior to halt construction of the initial stage of a reclamation project known as the Oahe Diversion Unit of the Missouri River Basin Project.
UFF is composed of approximately 900 members, the majority of whom either reside or own land in Spink and Brown counties in South Dakota. The initial stage of the project is to provide for diversion of water from an existing reservoir for industrial and recreational uses, flood control, and the irrigation of 190,000 acres in the two counties.
UFF originally pled nine separate claims for relief; this appeal involves only UFF’s amended ninth claim,
which sought to enjoin further construction of the initial stage because of the Secretary’s failure to comply with § 12 of the Reclamation Extension Act of August 13, 1914, 43 U.S.C. § 418
Section 12 requires that “before any contract is let or work begun for the construction of any reclamation project,” the Secretary must have executed recordable contracts with
all
excess land owners within the project for the sale of their excess land to settlers at government-fixed prices. The Secretary conceded that
all
of the excess land owners had not executed recordable contracts. Nonetheless, the district court granted summary judgment for the defendants. The court ruled that § 46 of the Omnibus Adjustment Act of May 25, 1926, 43 U.S.C. § 423e
had superseded § 12 on
projects built after 1926. He found § 46 allows construction to proceed even though all the excess land owners have not executed recordable contracts, but prohibits the delivery of water to excess land until a recordable contract for its sale has been executed. The district court certified the judgment for appeal under Fed.R.Civ.P. 54(b).
The issue on appeal turns on the propriety of the district court’s ruling that § 46 of the Omnibus Adjustment Act of 1926 has superseded § 12 of the Reclamation Extension Act of 1914. We find the ruling correct and affirm the grant of summary judgment.
UFF urges that the 1926 Act did not expressly repeal § 12 and that the law looks with disfavor upon repeals by implication.
Posadas
v.
National City Bank,
296 U.S. 497, 503, 56 S.Ct. 349, 80 L.Ed. 351 (1936).
Plaintiffs argue that § 46 has not impliedly repealed § 12, because the two sections are capable of coexistence. They contend § 12 prevents construction until all the owners in the project agree to sell their excess lands at government-fixed prices. After construction is completed and the project is turned over to the irrigation district for management and debt retirement, UFF urges, § 46 then prevents the irrigation districts from delivering water to landowners who fail to comply with acreage limitation provisions.
In this way, UFF asserts, the overall intent of the reclamation laws is given effect by preventing large landowners from securing speculative land prices.
See Ivanhoe Irrigation District
v.
McCracken,
357 U.S. 275, 78 S.Ct. 1174, 2 L.Ed.2d 1313 (1958).
To determine whether the two sections are capable of coexistence requires an inquiry by this court as to whether Congress clearly and manifestly expressed an intention that § 46 was to supersede § 12.
Mor
ton v. Mancan,
417 U.S. 535, 550-51, 94 S.Ct. 2474, 41 L.Ed.2d 290 (1974).
The first restrictions on excess lands in reclamation projects was § 5 of the Reclamation Act of 1902, 43 U.S.C. § 431. Section 5 required that water could not be furnished to more than 160 acres in a single ownership. This restriction was to promote the anti-monopoly and anti-speculation policies of the reclamation laws. Because § 5 did not fully effectuate these policies, Congress enacted § 12 of the 1914 Act. Section 12 required that excess land owners must agree, prior to construction, to dispose of their excess lands. In addition § 12 imposed controls on the price at which excess land could be sold. Despite these new restrictions the promise of the reclamation laws was not fully realized. To determine what additional measures were needed to achieve these policy goals, the Secretary of the Interior appointed a committee known as the “Fact Finders.” In 1924 the Fact Finders presented their report.
Among their numerous proposals was the following recommendation:
That no reclamation project should hereafter be authorized until all privately owned land in excess of a single homestead unit for each owner shall have been acquired by the United States or by contract placed under control of the Bureau of Reclamation for subdivision and sale to settlers at a price approved by the Secretary. This price to be considered in determining what land and water will cost settlers and hence the feasibility of the project under the payment conditions of the law.
In 1924 with the full support of President Coolidge and the Fact Finders, the Department of the Interior submitted H.R. 8836 to the House Committee on Irrigation and Reclamation.
Hearings on H.R. 8886 and 9611 before the House Committee on Irrigation and Reclamation,
68th Cong., 1st Sess. (1924). The fundamental purpose of the bill was to provide a new plan for repayment to the federal government of the construction costs of future irrigation projects.
One of the major changes in the
repayment system proposed by the bill was that the government would execute the repayment contracts with irrigation districts organized under state law. In the past the government entered into repayment contracts with the individual landowners. This change was allegedly designed to provide for better management of the projects and to further insure repayment.
Id.
at 35. The bill’s mandate was that these contracts must be entered into before any money could be expended for construction for “any
new
project or any
new
division of a project.” (Our emphasis).
With the exception as to holders of federal land grants, the proposed legislation varied the disposal scheme of § 12 of the 1914 Act by requiring all excess private land to be
sold
to the United States before any money could be expended on construction.
The Omnibus Adjustment Act of 1926, as finally passed, embodied many of the provisions of H.R. 8836 and the Fact Finders’ proposals, but relevant here, the 1926 Act provided a salient variance as relating to the disposal of excess lands. First, in § 46 the execution of the repayment contracts with the districts was
conditioned
upon the delivery of water and not the expenditure of construction funds as proposed in the bill. Also in § 46 the provisions dealing with the disposal of excess private and public lands were merged. The proposal for the acquisition of the excess private land by the government was deleted, and § 46 as passed required the execution of “recordable contracts” for the sale of the land. However, the important change in § 46, relevant here, is that the recordable contracts must be executed prior to delivery of project water rather than prior to the expenditure of construction funds.
A 1926 Senate Report gives indication for the reason that the
repayment
contract was to be conditioned upon the delivery of water and not the expenditure of construction funds, but it does not reveal the reason for the corresponding change of the time for the execution of the
recordable
contracts.
The only legislative history relating to this change is the testimony during the hearings on H.R. 8836. In
United States v. Tulare Lake Canal Co.,
535 F.2d 1093 (9th Cir. 1976),
Judge Browning described the concern expressed during the
hearings and the reason for the subsequent change:
Under the Fact Finders’ proposal, construction could not have begun until all owners of excess lands transferred such land to the United States or contracted to sell it at government-fixed prices, just as under section 12 of the 1914 Act. As we have shown, subsequent “payout” could not have avoided disposal. Section 46 as passed allows construction to proceed, but bars delivery of project water to excess land until a recordable contract for its sale is executed. The reasons for the change are clear, and reflect no diminution of Congress’ determination to break up excess landholdings. In the course of committee hearings, it was pointed out that under the Fact Finders’ proposals, construction of a project might be prevented or delayed if even one owner refused to transfer or contract to sell excess land; Congress obviously thought it necessary to avoid such an impasse.
535 F.2d at 1133 (footnotes omitted).
We agree that it was the clear and manifest intent of Congress to avoid such an impasse and that this intent can only be effectuated by interpreting § 46 as superseding § 12 on all reclamation projects started after 1926. Therefore in order for the construction of the initial stage of the Oahe Diversion Unit to be conditioned upon the execution of recordable contracts, Congress must expressly so provide.
We find no such requirement in the legislation for the initial stage of the Oahe Diversion Unit
or the Missouri River Basin Project.
The judgment is affirmed.