United States v. Samir K. Sain, No. 97-3114. United States of America v. Advanced Environmental Consultants, Inc., No. 97-3115

141 F.3d 463, 1998 U.S. App. LEXIS 7157, 1998 WL 164877
CourtCourt of Appeals for the Third Circuit
DecidedApril 10, 1998
Docket97-3114, 97-3115
StatusPublished
Cited by20 cases

This text of 141 F.3d 463 (United States v. Samir K. Sain, No. 97-3114. United States of America v. Advanced Environmental Consultants, Inc., No. 97-3115) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Samir K. Sain, No. 97-3114. United States of America v. Advanced Environmental Consultants, Inc., No. 97-3115, 141 F.3d 463, 1998 U.S. App. LEXIS 7157, 1998 WL 164877 (3d Cir. 1998).

Opinion

OPINION OF THE COURT

ROSENN, Circuit Judge.

This case primarily presents two questions of first impression in this circuit relating to the interpretation of the Major Fraud Act of 1988 (the “Act”). See 18 U.S.C. § 1031 (West 1997). The Act makes it a federal crime to defraud the United States in connection with a government contract that is valued in excess of $1 million. Specifically, we must decide whether a defendant may be charged with a separate violation of the Act for each of numerous executions of a single fraudulent scheme, and whether modifications of the original government contract, each of which have a value of less than $1 million, are within the purview of the Act when the underlying government contract has a value in excess of $1 million. The defendants make other arguments relating to the sufficiency of the evidence, the exclusion of expert testimony, whether an individual can be convicted of aiding and abetting a corporation he owns and controls, and alleged defects in their sentences. The district court rejected the defendants’ arguments. We affirm as to all issues. *

I.

A federal grand jury sitting in the Western District of Pennsylvania indicted Samir K. Sain and his company, Advanced Environmental Consultants, Inc. (“AEC”), on 46 counts of fraud in violation of the Act. Following trial, the petit jury returned guilty verdicts on all counts as to both defendants. The district court sentenced Sain to 37 months imprisonment and three years supervised release. The court sentenced AEC to five years probation and ordered it to pay a special assessment. In addition, the court ordered AEC to pay $597,124 in restitution, with any amount not paid by AEC to be paid by Sain. The defendants appealed. 1

II.

This complex fraud case arises out of an approximately $7-million contract between the United States Army and AEC, pursuant to which AEC built, owned, and operated a waste-water treatment plant at the Army Depot at Tooele, Utah. AEC is an environmental consulting company headquartered in Pittsburgh and incorporated in Pennsylvania. Sain has a masters degree in engineering and several credits toward a doctorate, is a licensed professional engineer, and is the sole shareholder and president of AEC. 2 It is well established that, because the jury returned guilty verdicts in the district court, this Court must construe the evidence in the light most favorable to the Government. See, e.g., Glasser v. United States, 315 U.S. 60, 80, 62 S.Ct. 457, 469-70, 86 L.Ed. 680 (1942); United States v. Cooper, 121 F.3d 130, 133 (3d Cir.1997). Following is a statement of facts which the jury could have found based on the trial evidence.

The Army operates a depot in Tooele, Utah, at which it services tanks and other types of military vehicles. Sometime in the 1980s, the Army entered into a consent decree with the State of Utah requiring the Army to treat the waste water it was generating at the depot and releasing into the ground water. To fulfill its obligation under this consent decree, the Army proposed to have a contractor build, own, and operate a plant to treat the depot’s waste water. After *467 the bidding process, AEC was selected. On November 30, 1987, AEC entered into the contract with the Army. Under the contract, AEC agreed to construct, own, and operate an industrial waste-water treatment plant at the depot for the “firm fixed price” of approximately $4.5 million. In a firm fixed price contract, once the price is established by the parties, the amount paid to the supplier of the goods or services does not vary with its costs. In this case, the risk of cost overruns rested with AEC. The term of the contract was for one year followed by four one-year options. The Army exercised each option and the contract lasted the full five years.

In the plant, AEC installed four large metal tanks called “adsorbers.” Each of the tanks was designed to hold approximately 5,000 pounds of filtering carbon. Waste water would be pumped through the tanks with the carbon filtering out much of the water’s pollutants. Periodically, as pollutants built up in the carbon, the carbon would become ineffective and have to be replaced. The process of replacing the carbon was called a “change out.” The contract provided for two of these change outs per year at AEC’s expense and did not specify the type of carbon to be used.

After the Army and AEC entered into the contract, but before AEC began operating the plant, the Army modified the contract to incorporate the City of Tooele’s water purity standards which were more strict than those imposed by the consent decree. The Army requested that AEC submit a cost proposal providing for the Army to reimburse AEC for its increased costs resulting from these stricter water purity standards. Ultimately, AEC submitted four cost proposals, none of which were approved by the Army. Instead, on April 11, 1989, the Army unilaterally imposed a modification of the contract pursuant to which AEC would receive approximately $682,000 in addition to the original contract price.

In the spring of 1989, before the Army had acted on AEC’s fourth cost proposal, AEC claimed that the waste water generated by the Army consistently contained a higher level of pollutants than the amounts specified in the contract. According to AEC, this higher level of pollutants required more than the two carbon change outs per year allowed by the contract. In an attempt to recoup these additional costs, AEC began submitting claims to the Army for reimbursement for costs associated with the additional change outs. On May 5,1989, May 26,1989, and June 20, 1989, AEC submitted claims. Each claim was for $27,500 and purported to represent the costs associated with a complete change out of the four tanks plus a 10-percent profit for AEC. According to the claims, AEC installed 5,000 pounds of carbon in each of the four tanks at a cost of $1.25 per pound of carbon, a price which corresponded to the market price for virgin carbon.

The Army agreed that these changed conditions warranted an equitable adjustment of the contract to compensate AEC for the costs of some of the additional carbon change outs. Lieutenant Colonel K.L. Andrews, the Army officer responsible for administering the AEC contract during most of the relevant time, notified Sain in a letter dated April 25, 1989 that no money would be paid to AEC by the Army for the additional carbon change outs unless AEC first submitted “documentation necessary - to support a claim.” Andrews advised that such documentation include “cost invoices, time sheets, and any other [necessary] documentation.” Also, at trial, Andrews testified that, in addition to the notification letter, he told Sain numerous times that supporting documentation was required in brder for AEC to receive payment. At trial, Sain reluctantly conceded that Andrews had required this documentation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Karen Ramm
Third Circuit, 2022
United States v. Azam Doost
3 F.4th 432 (D.C. Circuit, 2021)
Herrera v. Papillon
29 Pa. D. & C.5th 416 (Monroe County Court of Common Pleas, 2013)
GEORGE WASSERMAN & JANICE WASSERMAN GOLDSTEN FAMILY LLC. v. Kay
14 A.3d 1193 (Court of Special Appeals of Maryland, 2011)
United States v. Fullmer
584 F.3d 132 (Third Circuit, 2009)
United States v. Campa
529 F.3d 980 (Eleventh Circuit, 2008)
CardioVention, Inc. v. Medtronic, Inc.
483 F. Supp. 2d 830 (D. Minnesota, 2007)
United States v. Reitmeyer
356 F.3d 1313 (Tenth Circuit, 2004)
United States v. Rigas
281 F. Supp. 2d 660 (S.D. New York, 2003)
United States v. Johnson
66 F. App'x 320 (Third Circuit, 2003)
Berry v. Van Why
46 Pa. D. & C.4th 312 (Monroe County Court of Common Pleas, 2000)
United States v. Vincent R. Davis
183 F.3d 231 (Third Circuit, 1999)
United States v. Davis
Third Circuit, 1999
Hurley v. Atlantic City Police Department
174 F.3d 95 (Third Circuit, 1999)
United States Court of Appeals, Third Circuit
174 F.3d 95 (Third Circuit, 1999)
Hurley v. Atl Cty Pol Dept
Third Circuit, 1999

Cite This Page — Counsel Stack

Bluebook (online)
141 F.3d 463, 1998 U.S. App. LEXIS 7157, 1998 WL 164877, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-samir-k-sain-no-97-3114-united-states-of-america-v-ca3-1998.