United States v. Newport News Shipbuilding & Dry Dock Co.

178 F. 194, 101 C.C.A. 514, 1910 U.S. App. LEXIS 4490
CourtCourt of Appeals for the Fourth Circuit
DecidedFebruary 12, 1910
DocketNo. 837
StatusPublished
Cited by6 cases

This text of 178 F. 194 (United States v. Newport News Shipbuilding & Dry Dock Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Newport News Shipbuilding & Dry Dock Co., 178 F. 194, 101 C.C.A. 514, 1910 U.S. App. LEXIS 4490 (4th Cir. 1910).

Opinion

PRITCHARD, Circuit Judge

(after stating the facts as above). The findings of fact and conclusions of law by the learned judge who tried this case below clearly present the points involved in this controversy. The findings of fact are supported by the evidence, and we are therefore not inclined to interfere with the same. The rule that a contract is to be construed most strongly against the party preparing it is well settled, and applies to the government in a case like this as well as to an individual. In the case of Garrison v. United States, 7 Wall. 688, 19 L. Ed. 277, the court, among other things, said:

[201]*201“Tlie supiik'Hieniary agreement is signed by Gen. Butler and not by the plaintiff. Its doubtful expression should, therefore, according to the well-settled rule, be construed against the party who uses the language.”

The facts in this case show that the contract was prepared in the Navy Department, and we are justified in assuming that it was drafted by a law officer of that department. The parties to it, as appears from the findings of fact, had, prior to the date of this contract, entered into similar contracts, and under those contracts the speed trial was not under the standardization method, and the.plaintiff below, in making its estimates, at the time it entered into this contract, did not include the same. It is true that between 1890 and the date, of the trial of the Charleston it had been customary to run such trials, but the court below found that in every instance such trials were run by the government at its own expense and after the government had accepted the vessel.

To construe this contract in conformity with the contention of counsel for plaintiff in error would be to hold that it contemplates that contractors, under its provisions, shall make two trials. The contract, which is plain and explicit, provides that only one trial shall be made. It says:

“When the vessel is completed as required by the drawings, plans and specifications and ready for delivery to the party of the second part, she shall be subjected to a trial trip in tbe open sea under such conditions prescribed or approved by the Secretary of the Navy to test the hull and fittings * ® * and the speed of the vessel.”

Thus it will be seen that the contract provides for “a trial trip/' which necessarily means only one trip, and which clearly shows that it was in the minds of the contracting parties at the time that only one trial trip should be made.

It dearly appears that the government, as well as the contractor, understood that the ancient method of trial was to be the one by which the Charleston was to be tested. Thus it was to he a trial of speed and endurance which was to be obtained during the four consecutive hours of its duration. The minds of the parties met in the construction of the contract in this respect. That the government understood that standardization was not contemplated by the contract is apparent from all the facts and circumstances surrounding the transaction. It had uniformly adhered to its policy of requiring trials by the ancient method, until the Charleston’s trial. Until that time, no ship constructed for the government of more than 3,250 tons displacement had been tried by the standardization method, nor until that period had any such trial been required of any contractor, in the absence of a request for such trial or an assent thereto. It is significant that on the 7th day of November, 1903, bids on two .13,000-ton battleships were accepted, and in those instances the contractual provisions were similar to the Charleston, no provision for standardization being made. However, on the 8th day of September, 1901-, bids were called for on two 14,500-ton armored cruisers (the North Carolina and Montana), and special provision was made for a speed trial of four hours’ duration on a measured course “under conditions prescribed or approved by [202]*202the Secretary of the Navy, and also a standardization trial,” thus clearly showing that it 'was the intention of the Secretary of the Navy that, in order to exact the standardization test in addition to the speed trial, it was necessary specifically to provide for the same.

Notwithstanding the facts as we have stated them, when the Charleston was completed and ready for trial, the Secretary of the Navy informed the contractor that he desired the trial to be by standardization. The contractor, instead of complying with the request made by the Secretary of the 'Navy, immediately informed him that he understood that the Charleston contract only contemplated a trial by the ancient method, and that to require an additional trial, such as standardization, would result in additional expense, and insisted that the department should not deviate from its previous practice. However, the contractor stated that, “if the Department insists upon the change, we will accept the Provincetown course, and will submit estimates of the increased cost.” To this communication it appears that no reply was made by the Secretary of the Navy until the 15th day of June, 1905, at which time the contractor was ordered to proceed with the standardization trial, and the contractor thereupon complied with the request, incurring the additional expense, for which the judgment was rendered by the court below. Thus it will be seen that at the time the contractor was requested to make the additional trial the Secretary of the Navy was informed that if this trial was made it would be regarded as a change for which estimates had not been made, and that increased costs for the same would be submitted. By the terms of the statement made by the contractor at that time, the Secretary of the Navy knew that it was the purpose of the contractor to proceed under the interpretation which he had placed upon the contract,, and his order to proceed with the standardization trial, under such circumstances, •was in the nature of an acceptance of such interpretation. In the case of Central Pacific Railway Company v. United States, 28 Ct. Cl. 427, in referring to thi,s question, it is said:

■“A construction given to a contract by tlie express declaration of one party, and the silent acquiescence of the other prior to or during the service of the performance, cannot be repudiated after the party has acted upon the faith of it.”

Assuming that the changed clause of the contract does not apply to an alteration of the duties of the contractor thereunder, nevertheless, if the Secretary of the Navy, in the exercise of the inherent power vested in him by virtue of his office, and the statutes relating to the same, actually exercised such power by modifying, extending, or enlarging the contract, such action on his part necessarily involves an obligation to pay any sums that may have been expended in making such modification. In the case of United States v. Corliss S. E. Co., 91 U. S. 322, 323 (23 L. Ed. 397), the court said:

“The duty of the Secretary of the Navy, by the act of April 30, 1798, creating the Navy Department, extends, under the orders of the President, to ‘the procurement of naval stores and materials, and the construction, armament, equipment, and employment of vessels of war, as well as all other matters-connected with the naval establishment of the United States.’ 1 Stat. 553 [c. 35]. The power of the President in such eases is, of course, limited by the leg-[203]*203islaiion of Congress.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ohio Sav. Bank & Trust Co. v. Willys Corp.
16 F.2d 859 (Third Circuit, 1926)
United States v. George A. Fuller Co.
296 F. 178 (D. Kansas, 1923)
Locke v. McMurry
287 F. 276 (Eighth Circuit, 1923)
First Nat. Bank of Anamoose v. United States
206 F. 374 (Eighth Circuit, 1913)
Scully v. United States
197 F. 327 (D. Nevada, 1912)

Cite This Page — Counsel Stack

Bluebook (online)
178 F. 194, 101 C.C.A. 514, 1910 U.S. App. LEXIS 4490, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-newport-news-shipbuilding-dry-dock-co-ca4-1910.