Newport News Shipbuilding & Dry Dock Co. v. United States

79 Ct. Cl. 1, 1934 U.S. Ct. Cl. LEXIS 340, 1934 WL 2022
CourtUnited States Court of Claims
DecidedMarch 5, 1934
DocketNo. 30372
StatusPublished
Cited by2 cases

This text of 79 Ct. Cl. 1 (Newport News Shipbuilding & Dry Dock Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Newport News Shipbuilding & Dry Dock Co. v. United States, 79 Ct. Cl. 1, 1934 U.S. Ct. Cl. LEXIS 340, 1934 WL 2022 (cc 1934).

Opinion

Williams, Judge,

delivered the opinion of the court:

This case grows out of the construction of the battleship Virginia, for which the plaintiff and the United States, represented by the Secretary of the Navy, entered into a contract on February 15,1901. The contract called for the completion of the vessel in 36 months from the date of the contract, that is on or before February 14, 1904. Work under the contract was completed by the plaintiff and the vessel was delivered to the defendant at the Norfolk Navy Yard on April 25, 1906, 800 days beyond the contract period for completion.

Because of the length of time the case has been on the docket of the court a brief reference to the record history of the case is deemed proper. The original petition was filed on April 8,1909, practically three years after the completion [14]*14and delivery of the vessel. The amended petition, upon which the case is heard, was filed two and one half years thereafter, on November 23, 1911. Following the filing of the amended petition plaintiff proceeded with the taking of its testimony, which was concluded in chief prior to December 9, 1919, on which date the parties entered into a stipulation suspending the taking of further testimony pending the decision of this court in Moran Bros. Co. v. United States, a case growing out of the construction of the battleship Nebraska, in which claims substantially the same as those made by the plaintiff in the instant case were involved. The Moran case was decided on August 14, 1925, 61 C.Cls. 73.

Thereafter, on April 1, 1926, this case and three others brought by the plaintiff, no. 30373 West Virginia, no. 30374 Maryland, and no. 30375 Charleston, were referred to a commissioner of the court before whom the plaintiff resumed the taking of testimony, which it closed on the four cases on January 3, 1929. The defendant previous to that date had closed the taking of its testimony. On January 16, 1930, the four cases were rereferred to a commissioner for a report of the facts. The record of the cases consists of four volumes of printed testimony, oral and documentary, of nearly four thousand pages, and thousands of pages of testimony in manuscript form. The commissioner gave a most careful and exhaustive study of the testimony, to the request for findings, and to the various contentions of the parties, and on December 2, 1931, made an elaborate report containing detailed findings as to the material facts in this and the three companion cases. Considering the magnitude of the work involved, and the fact that the commissioner during the period was also carrying his full part of the current work of the court, the report was expeditiously made.

Following the filing of the commissioner’s report counsel for the Government entered a motion for an extension of time in which to file exceptions to the same, which motion was allowed, and the exceptions were filed on April 12, 1932. On April 23, the defendant filed a motion to continue the case to the October 1932 calendar, which motion the court allowed on May 7, 1932. Thereafter, on May 16, 1932, the [15]*15plaintiff filed its brief on the merits of the case, also its answer to the defendant’s exceptions to the commissioner’s report. On June 15, 1932, plaintiff filed its motion to limit the time within which the defendant should file its brief. On June 21, 1932, the court entered an order that the defendant file its brief on or before August 15,1932, and that the case be placed on the October 1932 calendar for trial. August 12, 1932, defendant filed its motion for an extension of time in which to file its brief to September 15, 1932, which motion was allowed by the court on August 19, 1932. Upon the call of the October 1932 calendar the defendant’s brief not having been filed, the case was placed on the January 1933 calendar for trial. The defendant’s brief not being on file on the call of the January 1933 calendar the case was continued and placed on the April 1933 calendar for trial. The defendant’s brief not having been filed, the case on the call of the April 1933 calendar was passed. On May 8, 1933, the court entered an order directing the defendant to file its brief on or before August 1, 1933. On July 29, 1933, defendant filed its motion for an extension of time to September 15, 1933, for filing its brief, which motion was allowed on August 7, 1933. The defendant filed its brief on September 12, 1933, and the case was argued and submitted to the court on October 10, 1933, or within one month after it was ready for trial.

The plaintiff in the amended petition asks for a judgment against the United States in the sum of $363,470.46. The items of the claim are as follows:

1. Change from a sheathed to an unsheathed vessel___$79, 845. 00
2. Damages on account of delay caused by changes_ 198,144. 00
3. Increased expense of gun foundations_ 8,139.71
4. Damages for delay in delivery of contract plans_ 24,194. 00
5. Damages for delay in delivery of armor and ordnance— 41,193. 00
6. Admitted balance due_ 11, 954.75

The items of the claim will be considered in the order stated:

1. Change from a sheathed to an unsheathed vessel. — The act of March 3, 1899, provided that the battleships therein authorized be sheathed and coppered. There being doubt in the mind of Navy Department officials as to the wisdom [16]*16of sheathing and coppering vessels, and apparently anticipating a possible change in the law requiring it, the Bureau circular calling for bids for the construction of the vessels authorized by the act requested bidders to submit two classes of bids, one for sheathed and coppered ships in accordance, with the requirements of the act, and one for the construction of the same ships not sheathed and cop-pered, the Department reserving the right to adopt either form of construction in case it should be authorized to do so, at the price named in the bid for such sheathed or unsheathed ships, the award, however, to be based on the bid for sheathed and coppered ships. The plaintiff submitted a bid of $3,593,000 for a sheathed ship (the Giovernment in the meantime having determined to perform the work of coppering the vessel) and a bid of $3,540,000 for the construction of the same vessel with the sheathing omitted. After some negotiations between the plaintiff and the Navy Department relating entirely to a sheathed vessel, in which the plans and specifications were by mutual agreement modified, the contract was awarded plaintiff for the construction of a sheathed vessel for a lump sum of $3,590,000, the contract price to be increased or decreased as the cost of changes,1 which were authorized in the contract, might add to or diminish the cost pf construction.

[17]*17Subsequent to the signing of the contract and before work upon the vessel had started, the Secretary of the Navy, in the exercise of the discretion vested in him by the act of March 3, 1901, 31 Stat. 1132, decided to omit the sheathing of the vessel. He immediately notified plaintiff of that fact and stated that the change from a sheathed to an unsheathed vessel would be referred to the board on changes for determination of the cost thereof.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kehm Corp. v. United States
93 F. Supp. 620 (Court of Claims, 1950)
George A. Fuller Co. v. United States
69 F. Supp. 409 (Court of Claims, 1947)

Cite This Page — Counsel Stack

Bluebook (online)
79 Ct. Cl. 1, 1934 U.S. Ct. Cl. LEXIS 340, 1934 WL 2022, Counsel Stack Legal Research, https://law.counselstack.com/opinion/newport-news-shipbuilding-dry-dock-co-v-united-states-cc-1934.