United States v. Kimberly Construction, Inc.

43 F. App'x 283
CourtCourt of Appeals for the Tenth Circuit
DecidedJuly 25, 2002
Docket99-4188, 99-4198
StatusUnpublished
Cited by7 cases

This text of 43 F. App'x 283 (United States v. Kimberly Construction, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Kimberly Construction, Inc., 43 F. App'x 283 (10th Cir. 2002).

Opinion

ORDER AND JUDGMENT **

EBEL, Circuit Judge.

This case involves a tortuous series of post-judgment motions and rulings, resulting in an amended judgment from which the parties appeal and cross-appeal. Kimberly Construction and Vigilant Insurance, defendants in the action below, appeal the district court’s entry of judgment against them and in favor of Fred Noyes, a subcontractor, and the court’s creation of a hen in favor of Hi-Valley Chemical against that judgment. Hi-Valley Chemical, an intervening plaintiff in the action below, cross-appeals the district court’s decision to relieve Vigilant Insurance from Hi-Valle/s original judgment against it. The parties raise other issues on appeal, which are discussed below.

I.

Fred Noyes, dba A-2 Plumbing and Heating (“Noyes”), filed the instant action under 40 U.S.C. § 270b(a) and (b) (“the Miller Act”) against its general contractor, Kimberly Construction, Inc. (“Kimberly”), and Kimberly’s bonding company, Vigilant Insurance Company (“Vigilant”), in the United States District Court for the District of Utah to recover costs for “labor and materials” provided to a Veterans Ad *285 ministration construction project (‘V.A.project”). Kimberly counterclaimed against Noyes seeking amounts due on two prior construction projects. Hi-Valley Chemical (“Hi-Valley”) intervened in the action, seeking payment for chemicals it provided to Noyes on the V.A. Project. Approximately a month prior to trial, Hi-Valley moved to file an amended complaint, seeking to add Kimberly and Vigilant as defendants.

The trial court granted Hi-Valley’s motion to add Kimberly and Vigilant as defendants on the first day of trial. Following a four-day bench trial, the district court judge instructed all parties to file ten-page briefs in support of their closing arguments, along with their proposed findings of fact and conclusions of law. Vigilant did not raise a statute of limitations defense either at trial or in its post-trial brief.

The district court issued its findings of fact and conclusions of law, finding that Kimberly “agreed to pay Hi-Valley for materials provided to the V.A. Site.” In its March 4, 1999, judgment, the district court granted Hi-Valley a judgment against Kimberly and Vigilant, jointly and severally, for the materials provided to the V.A. project, and for approximately half of the attorney’s fees that Hi-Valley had requested. The district court found that Noyes was in breach on the first two construction projects (prior to the V.A. project), entitling Kimberly to reimbursement for those two projects in the approximate amount of $160,000. For the V.A. project, however, the district court found that Kimberly owed Noyes a payment of roughly $82,000. Under the terms of the V.A. sub-contract, the district court found that this sum due to Noyes was “to be applied as an offset against the reimbursements” Noyes owed Kimberly from the previous two construction projects. Accordingly, the March 4 judgment granted Kimberly and Vigilant a judgment against Noyes for the difference between the amounts Noyes owed to Kimberly and the amount Kimberly owed Noyes, resulting in a judgment against Noyes of approximately $78,000. The district court also ordered Noyes to pay Kimberly and Vigilant approximately half the attorney’s fees they had requested.

Following the March 4 judgment, Vigilant and Kimberly filed a Rule 59(e) motion to alter or amend the judgment, requesting that the district court remove Vigilant from the judgment that Hi-Valley had against Vigilant and Kimberly. They argued that the Miller Act’s one-year statute of limitations prevented Hi-Valley from bringing a claim against Vigilant because the limitations period had expired at the time Hi-Valley intervened. Contending that they had not waived the statute of limitations defense, Vigilant and Kimberly insisted that they did not raise it earlier “because Hi-Valley did not initially state a claim” against them, even though Hi-Valley had sought to add Kimberly and Vigilant as defendants over a month before trial. They also argued in this Rule 59(e) motion that insufficient evidence was presented at trial to support the district court’s conclusion that Kimberly and Vigilant were responsible for payment to Hi-Valley for the materials delivered to the V.A. Project.

On May 6, the district court granted the portion of Vigilant and Kimberly’s Rule 59(e) motion requesting that Vigilant be removed from Hi-Valley’s judgment against them. 1 Following this action by the district court, Hi-Valley filed its own *286 Rule 59(e) motion, requesting that the district court also find Noyes liable for the materials Hi-Valley delivered to the V.A. project and that the court grant Hi-Valley a hen against Noyes’s judgment against Kimberly. In response to these requests, the court issued an amended judgment, in which it granted Hi-Valley a judgment against Noyes and Kimberly, jointly and severally, for the materials used at the V.A. site. It then granted Hi-Valley its requested hen, and “[fjor purposes of foreclosing on or otherwise enforcing that hen,” granted Noyes a judgment against Kimberly and Vigilant for the amount they owed Noyes on the V.A. project, approximately $82,000. 2 The court granted Kimberly and Vigilant a judgment against Noyes in the amount of approximately $78,000. 3

Kimberly and Vigilant appeal this amended judgment, claiming that the district court erred (1) in creating a judgment against them and in favor of Noyes; (2) in granting Hi-Valley a hen against that “fictional” judgment; and (3) in granting Hi-Valley a judgment against Vigilant Insurance because, according to them, the court had properly ruled earlier that Hi-Valley’s claim was barred by the statute of limitations. 4 Kimberly and Vigilant also claim on appeal that the evidence presented at trial was insufficient to support a finding that Hi-Valley was entitled to a judgment against Kimberly. Hi-Valley cross-appeals, rebutting the issues Kimberly and Vigilant raise on appeal and claiming that the district court erred (1) in granting Vigilant’s Rule 59(e) motion asserting its statute of limitations defense; and (2) in reducing Hi-Valley’s claim for attorney’s fees. The parties also request attorney’s fees associated with bringing their appeals and cross-appeals.

II.

The district court had jurisdiction pursuant to 40 U.S.C. § 270b (a) and (b), commonly known as the “Miller Act.” This court has jurisdiction pursuant to 28 U.S.C. § 1291.

A. Vigilant’s 59(e) motion asserting statute of limitations.

We review motions to alter or amend a judgment under Rule 59(e) for an abuse of discretion. Brown v. Presbyterian Healthcare Servs., 101 F.3d 1324, 1331 (10th Cir.1996). A district court abuses its discretion if it commits an error of law.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Circle C Resources v. Charlene Hassler
2023 WY 54 (Wyoming Supreme Court, 2023)
Marshall v. Abdoun
E.D. Pennsylvania, 2021
United States v. Colorado Mufflers Unlimited, Inc.
116 F. App'x 218 (Tenth Circuit, 2004)
Evolution, Inc. v. SunTrust Bank
342 F. Supp. 2d 943 (D. Kansas, 2004)
Estate of Sisk v. Manzanares
270 F. Supp. 2d 1265 (D. Kansas, 2003)
Horizon Holdings, LLC v. Genmar Holdings, Inc.
244 F. Supp. 2d 1250 (D. Kansas, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
43 F. App'x 283, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-kimberly-construction-inc-ca10-2002.