United States v. Justin J. Reeves, LLC

CourtDistrict Court, E.D. Louisiana
DecidedAugust 30, 2024
Docket2:24-cv-00868
StatusUnknown

This text of United States v. Justin J. Reeves, LLC (United States v. Justin J. Reeves, LLC) is published on Counsel Stack Legal Research, covering District Court, E.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Justin J. Reeves, LLC, (E.D. La. 2024).

Opinion

UNITED STATES DISTRICT COURT EASTERN DISTRICT OF LOUISIANA

UNITED STATES OF AMERICA, CIVIL ACTION FOR THE USE AND BENEFIT OF D. HAYES ENTERPRISE, LLC, Plaintiff

VERSUS NO. 24-868

JUSTIN J. REEVES, LLC, ET AL., SECTION: “E” (4) Defendants

ORDER AND REASONS Before the Court is a motion to dismiss and compel arbitration, or in the alternative, stay the case, filed by Defendants, Justin J. Reeves, LLC, (“JJR”) and Nationwide Mutual Insurance Company (“Nationwide”) (sometimes referred to as “the Defendants”).1 Plaintiff, D. Hayes Enterprise, LLC, filed an opposition.2 Defendants filed a reply.3 BACKGROUND Plaintiff, a subcontractor, alleges that on October 15, 2021, it contracted with JJR, the general contractor for a project on behalf of the United States Army Corps of Engineers known as “Westshore Lake Pontchartrain Access Roads, Project Number W912P821C0046” (“the Project”).4 Nationwide issued a payment bond to secure JJR’s payment to subcontractors on the Project.5 Plaintiff alleges JJR stopped making

1 R. Doc. 10. 2 R. Doc. 12. 3 R. Doc. 13. 4 R. Doc. 1, p. 3. 5 Id. payments to Plaintiff for materials supplied and work performed.6 In total, Plaintiff alleges JJR has failed to pay Plaintiff a sum of $1,549,083.86 for labor and materials.7 Plaintiff filed suit on April 5, 2024, asserting Miller Act8 claims against both Defendants and a variety of state law breach of contract claims against JJR, including Failure to Pay claims under LA R.S. 9:2781, Louisiana Prompt Pay Act claims under LA

R.S. 9:2784, penalties under LA R.S. 9:4856, detrimental reliance claims, and claims for damages.9 As to Plaintiff’s Miller Act claims against JJR as principal and Nationwide as surety, Plaintiff alleges the Defendants are “justly, truly, and solidarily indebted for all sums due to D. Hayes” under the Act.10 Defendants argue that Plaintiff breached the Project subcontract because Plaintiff “did not have the resources to fully fund and complete its scope of work,” which prompted JJR to send Plaintiff a “Cure Notice” outlining is defaults.11 Defendants say this caused JJR to limit the scope of Plaintiff’s work on the Project and assume performance of the responsibilities assigned to JJR in the subcontract.12 Defendants argue that JJR paid Plaintiff a total of $4,443,737.21, which constituted full payment under the subcontract, so Plaintiff is not entitled to more.13

Relative to the instant motion, Defendants seek to compel arbitration of this dispute because “the contract between JJR and [Plaintiff] contains a valid agreement and Plaintiff is contractually bound to arbitrate its claims and causes of action.”14 In the event

6 Id. at p. 4. 7 Id. at p. 5. 8 40 U.S.C. §§ 3131 et seq. 9 See generally id. 10 Id. at pp. 6-7. 11 R. Doc. 10-1, p. 3. 12 Id. 13 Id. 14 R. Doc. 10, p. 1. the Court denies its request to send all claims to arbitration, the Defendants seek to stay the remainder of the proceedings pending the disposition of arbitration.15 LEGAL STANDARD I. The Federal Arbitration Act

The Federal Arbitration Act (“FAA”) governs the enforceability of arbitration agreements.16 The FAA “reflects the fundamental principle that arbitration is a matter of contract.”17 The United States Supreme Court has clarified that “federal [arbitration] policy is about treating arbitration contracts like all others, not about fostering arbitration.”18 “The FAA thereby places arbitration agreements on an equal footing with other contracts.”19 “Arbitration is a substitute for litigation whose purpose is to settle the parties’ differences in a fast, inexpensive manner and in a tribunal chosen by them.”20 When presented with a motion to compel arbitration, a court must first assess “if the party has agreed to arbitrate the dispute” in a valid arbitration agreement, and second, “if any

federal statute or policy renders the claims nonarbitrable.”21 Arbitration is “a way to resolve those disputes—but only those disputes—that the parties have agreed to submit to arbitration.”22 A court assesses “whether the dispute in question falls within the scope

15 R. Doc. 10-1, p. 1. 16 9 U.S.C. § 1, et seq. 17 Coinbase, Inc. v. Suski, 144 S. Ct. 1186, 1192 (2024). 18 Morgan v. Sundance, Inc., 596 U.S. 411, 418 (2022) (“The policy is to make ‘arbitration agreements as enforceable as other contracts, but not more so.’”); see also Volt Info. Scis., Inc. v. Bd. of Trs. of Leland Stan. Junior Univ., 489 U.S. 468, 476 (1989). 19 Rent-A-Ctr., W., Inc. v. Jackson, 561 U.S. 63, 67 (2010). 20 Hanlon v. Monsanto Ag Prod., LLC, 124 So. 3d 535, 539 (La. Ct. App. 2 Cir. 10/9/13) (citing Tubbs Rice Dryers, Inc. v. Martin, 33 So.3d 926 (La. Ct. App. 2 Cir. 2010)). 21 Sherer v. Green Tree Servicing LLC, 548 F.3d 379, 381 (5th Cir. 2008). 22 First Options of Chi., Inc. v. Kaplan, 514 U.S. 938, 943 (1995). of [the] arbitration agreement. A court should further consider “whether any federal statute or policy renders the claims nonarbitrable.”23 II. The Miller Act The Miller Act imposes certain obligations on the prime contractor on any “contract of more than $100,000 . . . for the construction, alteration, or repair of any

public building or public work of the Federal Government.”24 “The purpose of the Miller Act is to protect those whose labor and materials go into public construction projects and to insure that they will be paid.”25 “The Miller Act represents a congressional effort to protect persons supplying labor and material for the construction of” federal projects.26 “The essence of its policy is to provide a surety who, by force of the Act, must make good the obligations of a defaulting contractor to his suppliers of labor and material.”27 Because the Miller Act “is highly remedial in nature,” it “is entitled to a liberal construction and application . . . to effectuate” Congress’s “intent to protect those whose labor and materials go into public projects.”28 “Parties often arbitrate non-Miller Act disputes while bringing civil actions under the Miller Act to preserve Miller Act claims.”29 A party may only expressly waive its Miller Act claims in writing.30

23 Cent. Rock Corp. v. Horton Constr. Co., No. 2:13-CV-00406-PM-KK, 2013 WL 12184300, at *2 (W.D. La. July 31, 2013) (citing Jones v. Halliburton Co., 583 F.3d 228, 234 (5th Cir. 2009)). 24 40 U.S.C. § 3131(b). 25 Weiss, 532 F.2d at 1013 (citing Graybar Electric Co. v. John A. Volpe Construction Co., 387 F.2d 55 (5th Cir. 1967)). 26 U.S. for Benefit & on Behalf of Sherman v. Carter, 353 U.S. 210, 216 (1957). 27 Id. at 216-17. 28 Clifford F. MacEvoy Co. v. U.S. for Use & Benefit of Calvin Tomkins Co., 322 U.S. 102, 107 (1944) (citing Fleisher Eng'g & Constr. Co. v. U.S., for Use & Benefit of Hallenbeck, 311 U.S. 15 (1940)).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Grigson v. Creative Artists Agency, L.L.C.
210 F.3d 524 (Fifth Circuit, 2000)
Washington Mutual Finance Group, LLC v. Bailey
364 F.3d 260 (Fifth Circuit, 2004)
Southern Energy Homes, Inc. v. Godwin
183 F. App'x 441 (Fifth Circuit, 2006)
Jones v. Halliburton Co.
583 F.3d 228 (Fifth Circuit, 2009)
United States Ex Rel. Sherman v. Carter Constr. Co.
353 U.S. 210 (Supreme Court, 1957)
Scherk v. Alberto-Culver Co.
417 U.S. 506 (Supreme Court, 1974)
First Options of Chicago, Inc. v. Kaplan
514 U.S. 938 (Supreme Court, 1995)
Noble Drilling Services, Inc. v. Certex USA, Inc.
620 F.3d 469 (Fifth Circuit, 2010)
Sherer v. Green Tree Servicing LLC
548 F.3d 379 (Fifth Circuit, 2008)
TUBBS RICE DRYERS, INC. v. Martin
33 So. 3d 926 (Louisiana Court of Appeal, 2010)
United States Ex Rel. Milestone Tarant, LLC v. Federal Insurance
672 F. Supp. 2d 92 (District of Columbia, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
United States v. Justin J. Reeves, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-justin-j-reeves-llc-laed-2024.