United States v. Hanna Nickel Smelting Company, a Corporation, and the Hanna Mining Company, a Corporation, Hanna Nickel Smelting Company, a Corporation, and the Hanna Mining Company, a Corporation v. United States

400 F.2d 944, 1968 U.S. App. LEXIS 5484
CourtCourt of Appeals for the Ninth Circuit
DecidedSeptember 23, 1968
Docket21232
StatusPublished

This text of 400 F.2d 944 (United States v. Hanna Nickel Smelting Company, a Corporation, and the Hanna Mining Company, a Corporation, Hanna Nickel Smelting Company, a Corporation, and the Hanna Mining Company, a Corporation v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Hanna Nickel Smelting Company, a Corporation, and the Hanna Mining Company, a Corporation, Hanna Nickel Smelting Company, a Corporation, and the Hanna Mining Company, a Corporation v. United States, 400 F.2d 944, 1968 U.S. App. LEXIS 5484 (9th Cir. 1968).

Opinion

400 F.2d 944

UNITED STATES of America, Appellant,
v.
HANNA NICKEL SMELTING COMPANY, a corporation, and the Hanna Mining Company, a corporation, Appellees.
HANNA NICKEL SMELTING COMPANY, a corporation, and the Hanna Mining Company, a corporation, Appellants,
v.
UNITED STATES of America, Appellee.

No. 21232.

United States Court of Appeals Ninth Circuit.

September 23, 1968.

David L. Rose, (argued) Martin Jacobs, Attys., Dept of Justice, Barefoot Sanders, Asst. Atty. Gen., Washington, D. C., Sidney Lezak, U. S. Atty., Portland, Or., for appellant.

James H. Clarke, (argued) of McColloch, Dezendorf & Spears, Portland, Or., H. Chapman Rose and Ellis H. McKay, of Jones, Day, Cockley & Reavis, Cleveland, Ohio, for appellee.

Before MADDEN,* Senior Judge of the United States Court of Claims, and MERRILL and CARTER, Circuit Judges,

JAMES M. CARTER, Circuit Judge.

The United States filed the action below against the appellees (hereafter referred to as Hanna), to recover $1,738,558 for breach of the accounting provisions of a government contract; and also sought an additional $249,598 based upon a claim for reformation of two subsequent contracts between the parties.

The trial court awarded judgment to the United States in the sum of $560,632.89, made up of the following items:

(1) $231,506 for items which the trial court held represented capital improvements and which were improperly expensed as costs of production;

(2) $241,798.32, resulting from a reformation of the contract as it related to the price to be paid by the government to Hanna for ferronickel;

(3) $87,328.57 allowed as pre-judgment interest on certain amounts of money.

Cross-appeals followed. The United States contends that the contract was not ambiguous and that Hanna wrongfully expensed items which should have been capitalized; that additional amounts on various items should have been allowed the government. The United States also contends that the court's alternate holding of estoppel by acquiescence was erroneous.

Hanna in its cross-appeal contends that the district court erroneously reformed the contract resulting in the portion of the award shown above, and erroneously allowed prejudgment interest as shown above.

The facts are generally contained in the opinion by the district judge in United States v. Hanna Nickel Smelting Company, et al., 253 F.Supp. 784 (D.C. Or. 1966).

The Appeal by the United States

The district court found that the contract was ambiguous and we agree. It took testimony from accounting experts and on conflicting testimony interpreted the contract in favor of Hanna. We are satisfied with the trial court's disposition of this phase of the case as shown in the opinion (253 F.Supp. pp. 787-792).

As to the alternate ground of decision (253 F.Supp. pp. 793-795) under the subtitle "Equitable Issues," and involving estoppel against the United States by acquiescence, we express no opinion.

Hanna's Appeal

We are satisfied with the trial court's disposition of the questions raised by the cross-appeal of Hanna under the subsection "Reformation" (253 F.Supp. at 795). However, the court did not go into detail in connection with the problem of reformation and we therefore consider it briefly hereafter.

We are satisfied with the trial court's disposition of the matter of prejudgment interest (253 F.Supp. at 796).

The Reformation Issue

Hanna's obligation to deliver nickel was to deliver 125,000,000 lbs or deliver until June 30, 1962, whichever occurred first. By early 1961 Hanna had delivered all but 19,500,000 lbs., about a year's production.

The contract before the amendment which is involved in this case, provided as to price, the lower of two figures (1) the cost of production, or (2) the agreed ceiling price.

Amendment No. 5 was negotiated. Dated April 20, 1961, it was effective as of March 31, 1961. It read in part as follows:

"* * * The 19,499,863 pounds of contained nickel shall be produced by the Contractor after March 21, 1961 and shall be delivered to the Government at such time or times after March 31, 1961 and prior to June 30, 1965, as the Contractor in its sole discretion shall determine, at a price per pound of contained nickel which shall be equal to (a) the Contractor's average actual cost of production per pound of contained nickel in the calendar year in which such ferronickel is delivered to the Government or (b) $0.5877, whichever is less."

It extended Hanna's time to deliver the balance of the nickel contracted for to June 30, 1965, and relieved Hanna of its contractual obligations to operate the smelter at maximum capacity and to deliver all products to the government.

The court found that the ceiling price of 58.77 cents "was computed by an agreed formula which was based upon the difference between the company's cost of production in 1959 and 1960." The court found that Hanna had improperly included in its 1959 and 1960 cost figure, as expense, over $215,000 of capital expenditures, the effect of which was to raise the ceiling price.

The court reformed the contract so as to compute a ceiling price by applying the true cost figures. This meant a reduction of 1.24 cents per lb. and a ceiling of 57.53 cents per lb. The award in the judgment was computed on this ceiling.

This part of the judgment in favor of the government amounted to $241,798.32 plus interest of $87,328.57, a total of $329,126.89. It was computed on a difference of 1.24 cents per lb. on 2,186,409 lbs delivered under the amended agreement and 1.24 cents per lb. on an additional 17,313,454 lbs. covered by a final termination agreement.

After the amendment and on March 5, 1964, the contract was terminated. Hanna as part of termination, paid the government the difference between the 58.77 ceiling price and the market price of nickel and was relieved of the obligation to deliver the 17,313,454 lbs. This action was then on file and the parties agreed that if the prayer for reformation was granted, Hanna would pay the price reduction, times the number of undelivered lbs. The reformed price thus applied to the last 17,513,454 lbs. There is no dispute as to the computations.

Lengthy negotiations were had and correspondence exchanged between Hanna and GSA, which by this time was the government agency handling the contract.

As Hanna had continued with its production, its operation had become more efficient. The government had agreed to purchase all salable ferronickel produced for ore up to 125,000,000 lbs of contained nickel at a price equal to the cost of production plus an amount (payable over the first 95,000,000 lbs only) sufficient to amortize the advance of capital and interest.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Hanna Nickel Smelting Company
253 F. Supp. 784 (D. Oregon, 1966)
Mahoning Inv. Co. v. United States
3 F. Supp. 622 (Court of Claims, 1933)
Lundgren v. Freeman
307 F.2d 104 (Ninth Circuit, 1962)
United States v. Hanna Nickel Smelting Co.
400 F.2d 944 (Ninth Circuit, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
400 F.2d 944, 1968 U.S. App. LEXIS 5484, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-hanna-nickel-smelting-company-a-corporation-and-the-ca9-1968.