United States v. Hanna Nickel Smelting Company

253 F. Supp. 784
CourtDistrict Court, D. Oregon
DecidedApril 27, 1966
DocketCiv. 63-530
StatusPublished
Cited by11 cases

This text of 253 F. Supp. 784 (United States v. Hanna Nickel Smelting Company) is published on Counsel Stack Legal Research, covering District Court, D. Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Hanna Nickel Smelting Company, 253 F. Supp. 784 (D. Or. 1966).

Opinion

SOLOMON, Chief Judge:

The Government filed this action on November 8, 1963, to recover $1,738,598 from defendant Hanna Nickel Smelting Company (hereafter called either the “Smelting Company” or the “Company”) for breach of the accounting provisions of a government contract. The Government also seeks to reform two later agreements between the parties and demands an additional $249,598.

During the Korean War, Government defense officials determined to increase the domestic production of nickel. The Hanna Coal & Ore Company, predecessor to defendant Hanna Mining Company (Mining Company), held extensive leases on Nickel Mountain near Riddle, Oregon. Negotiations between Hanna and the Government started in 1951, and on January 16, 1953, they signed Contract DMP-49. Hanna agreed to develop a mine on Nickel Mountain, and the Government agreed to buy enough ore to produce 125 million pounds of nickel. 1

Simultaneously, the Government and the Company (a subsidiary of Hanna Coal & Ore) signed Contract DMP-50 to build and test an experimental nickel smelter at Riddle. Under this contract, the Government agreed to finance the capital expenditures and operating costs of the smelter, subject to ceilings and limitations. The Company agreed to contribute only the real property.

If the smelting process did not prove feasible, contract DMP-50 would by its terms terminate. When tests established that the smelting process was successful, the Company became obligated, at no profit to itelf, to deliver 125 million pounds of nickel to the Government. The delivery price was based on (1) the Company’s actual cost of production (subject to a varying ceiling) and (2) an amount sufficient to amortize the Government's capital advances plus interest. The capital advances were to be amortized over the first 95 million pounds, so that the last 30 million pounds were to be delivered at the Company’s cost of production.

The Government’s advances for both capital and working capital were to be credited against the invoice price of nickel. So long as the Smelting Company borrowed its funds from the Government and kept its costs within the contract ceilings, it was, in effect, operating the smelter for the Government.

This arrangement had advantages for the Hanna Companies. The Mining Company was to make a profit on its sales of ore to the Government. The Smelting Company was to pay the Mining Company $100,000 per year after September 30, 1955, in return for management supervision. This cost of production would, in turn, be charged by the Smelting Company to the Government. The Government, rather than the Smelting Company assumed the risks inherent in testing a new process. Moreover, the Smelting Company had an option to purchase the smelter for commercial use at the end of the contract period at a fraction of its value — 7y2 per cent of the Government’s total capital advances.

The contract imposed an absolute ceiling of $22,875,000 2 on capital advances, and specified the purposes for which such advances could be used. It also provided for Government review and approval of capital expenditures. The contract lim *788 ited to $3,750,000 3 the amount of outstanding working capital advances.

In this action, the Government claims that the Company breached Contract DMP-50 by charging many capital items to expense accounts and by including them in actual costs of production. Because of the contractual limitations on capital expenditures, the Government contends that the Company’s accounting practices increased the price of nickel to the Government.

The Government initially objected to 284 items. It now admits that 68 were properly expensed and claims $1,392,376.-55 based upon the remaining 216 items.

The company contends that its accounting practices were consistent, proper, and permitted by the contract. In addition, it asserts that the Government is barred from maintaining this action because of its long-continued acquiescence in these accounting practices.

A separate trial was held in October, 1964, on the equitable defense. Later I concluded that I should hear all of the evidence before deciding any issue. The remaining issues were tried in July, 1965, after which the parties submitted voluminous briefs. All of the issues are now presented for decision.

Secondary Claims

The Company exercised its option to purchase the smelter in March, 1961, after delivering 105 million pounds of nickel under the contract. A new agreement required the Company to complete its original delivery obligation at 58.77 cents per pound or its actual cost of production, whichever was lower.

The Government contends that the 58.77 cent ceiling price was based upon the Company’s cost experience in 1959 and 1960 and that it must be revised downward if the Government’s principal claim is sustained. It revised the ceiling price downward to 57.49 cents per pound by applying the Company’s adjusted cost experience to the formula purportedly used by the parties in arriving at the 1961 agreement. More than two million pounds of nickel were delivered at the 58.77 cent ceiling price, and the Government claims $27,986 under the reformation issue.

The Company argues that the 58.77 cent ceiling price was a negotiated price based not only on a formula, but also on estimates of the Company’s actual cost of production. It claims that its costs were higher than expected and that the ceiling price, if reformed, should be reformed upward to 62.65 cents per pound.

In 1964, after this action was filed, the parties terminated the 1961 agreement. The Company paid $2,175,000, based upon the 58.77 cent ceiling price, in lieu of completing the required deliveries. It agreed to adjust this termination payment to accord with any reformation of the 1961 agreement. The Government seeks an adjustment of $221,612 in this action.

The Accounting Dispute

Contract DMP-50 called for the Company to test a French smelting process known as the Ugine process. Apparently because the Government hoped to expedite production, the contract precluded the use of a pilot plant. Instead, the Company agreed to conduct preliminary tests in France and then to build the first unit of the proposed smelting facility at Riddle, Oregon. If the smelting process proved feasible, the Company agreed to enlarge the smelter to' production scale.

As the Company tested various equipment and processes in the Riddle smelter, it discovered that many items required redesign or replacement with more efficient equipment. It also found that it needed new equipment to obtain maximum recovery of nickel from the ore. The Company charged some of these costs to operating expenses.

*789 In 1956, for example, ore dryer #1, installed during the testing process, proved much less efficient than dryer #2, installed during an expansion of the facility. Dryer #2 incorporated improvements based upon the Company’s experience with #1. Dryer #1 was rebuilt at a cost of $56,626.27, which was charged to expense.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mollet v. Commissioner
82 T.C. No. 49 (U.S. Tax Court, 1984)
Todd Shipyards Corp. v. Turbine Service, Inc.
467 F. Supp. 1257 (E.D. Louisiana, 1978)
Jumbo v. Nester Motors, Inc.
428 F. Supp. 1085 (D. Arizona, 1977)
H & M Moving, Inc. v. United States
499 F.2d 660 (Court of Claims, 1974)
Litton Systems, Inc. v. The United States
449 F.2d 392 (Court of Claims, 1971)
Schmeck v. Bogatay
485 P.2d 1095 (Oregon Supreme Court, 1971)
United States v. Georgia-Pacific Company
421 F.2d 92 (Ninth Circuit, 1970)
United States v. Hanna Nickel Smelting Co.
400 F.2d 944 (Ninth Circuit, 1968)
Chicago, St. P., M. & O. Ry. Co. v. United States
50 F. Supp. 249 (D. Minnesota, 1943)

Cite This Page — Counsel Stack

Bluebook (online)
253 F. Supp. 784, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-hanna-nickel-smelting-company-ord-1966.