United States v. Hallmark Construction Co.

30 F. Supp. 2d 1033, 1998 U.S. Dist. LEXIS 21600, 1998 WL 886884
District Court, N.D. Illinois·Decided December 8, 1998·No. 97 C 3682·Published·Cited by 6 cases

Opinion

DECISION ON THE MERITS

CONLON, District Judge.

Upon referral from the United States Army Corps of Engineers, Chicago District (“the Corps”), the United States filed a complaint against Hallmark Construction Company (“Hallmark”) for allegedly discharging pollutants into an isolated wetland on property known as the Heritage Knolls Subdivision. The United States seeks injunctive relief from Hallmark for unauthorized discharge of dredge or fill material into the wetland.

A three-day bench trial was held. After considering the testimony, exhibits and arguments of counsel, the court enters the following findings of fact and conclusions of law, as required by Rule 52(a) of the Federal Rules of Civil Procedure. As a preliminary matter, the court adopts and incorporates the parties’ stipulation of uncontested facts, as well as uneontroverted portions of Hallmark’s statement of contested facts in the joint final pretrial order.

I. THE WETLAND DELINEATION OF AREA B

The following background facts are either undisputed or have been proven at trial. In 1988, Hallmark purchased the property then known as the Swift Research Farm in order to develop a residential subdivision, Heritage Knolls. The farm contained several natural topographical depressions. The parties dispute the wetland jurisdictional status of the roughly five-acre depression known as Area B. Area B was an isolated water or wetland with no surface connection to navigable waters.

The farm was continuously planted from 1969 to 1988. Before development, all parts of Area B were cultivated for farming. Area B was drained by buried clay field tile to allow farming. The main tile lines were twelve-inch tile, connected to smaller tile lines three-inch and six-inch in diameter. The field tile was regularly and continuously kept in repair when the property was farmed. Eight out of ten years the tenant farmer, John Kestel, successfully grew crops in Area B.

In 1989, Hallmark began excavating Area B to construct a retention pond and storm-water management complex. Hallmark also used clean dirt for filling and grading other parts of Area B to construct roads and upland lots on which houses could be built. In the summer of 1990, Hallmark’s civil engineer, Rogina & Associates (“Rogina”), advised that a wetland delineation should be done and hired Planning Resources, Inc. (“PRI”). PRI’s engineer Kenneth Klick visited the property to identify and delineate wetlands on July 11,1990.

During Klick’s July 11 visit to the property, he observed flotsam and hydrophytic vegetation in Area B. A flotsam ring is created by dead or drowned vegetable debris deposited in a circular pattern where temporary inundation has occurred and receded. Klick reported the area previously had been affected by farming practices and approximately one acre of Area B had been graded to prepare for the construction or installation of roads and utilities. Although other areas of the farm had standing water during the inspection, Area B was neither saturated nor inundated. Using the methodology of the 1989 Federal Manual for Identifying and Delineating Jurisdictional Wetlands (“1989 Manual”), 1 Klick concluded Area B was a “seasonally flooded farmed wetland.”

On August 16, 1990, PRI and Rogina representatives met with Corps representatives, hand delivering PRI’s wetland report. The Corps requested that Hallmark fill out an *1036 “after-the-fact” permit application and provide a mitigation plan to address the loss of wetland area. On August 20, 1990, Hallmark submitted an application for Nationwide Permit 26 for the fill of less than ten acres of isolated waters. In the application, Hallmark proposed creation of new wetlands adjacent to the anticipated lake as its mitigation plan. Hallmark resubmitted the application on August 31, 1990. The Corps did not respond directly to Hallmark’s application. Instead, the Corps concentrated on obtaining a mitigation plan for Area B.

Hallmark retained SDI Consultants, Ltd. (“SDI”) to propose a mitigation plan, which was completed in 1995. SDI reviewed all historical data about Area B and, using the 1987 Manual, concluded Area B lacked wetland hydrology when farmed. SDI determined Area B did not require a mitigation plan because it was properly classified as “prior converted cropland” rather than a farmed wetland.

Upon receiving SDI’s report in early 1996, the Corps forwarded the report to the Natural Resources Conservation' Service (“NRCS”). In 1994, the Corps, NRCS, the Environmental Protection Agency, and the U.S. Fish and Wildlife Service signed a memorandum of agreement, making NRCS the lead agency with respect to wetland determinations on agricultural lands. NRCS reviewed PRI’s report, SDI’s report, and its own wetland map, prepared in 1987 or 1988. NRCS creates wetland maps based on examination of aerial photographs and historical data. Reviewing existing data, NRCS concluded Area B was a wetland.

Prior to receiving SDI’s report, the Corps had already concluded Hallmark was in violation of the Clean Water Act. In a letter dated August 24, 1995, the Corps asserted Hallmark had discharged fill material into wetlands without a permit. Because the SDI delineation concluded Area B was not a wetland, Hallmark refused to comply with the Corps’ request for a mitigation plan. Over the course of more than five years, the Corps repeatedly requested (and eventually demanded) that Hallmark provide an adequate mitigation plan to address the loss of wetlands. After attempts to resolve the dispute proved unsuccessful, the Corps referred this matter to the United States Attorney.

II FEDERAL JURISDICTION UNDER THE CLEAN WATER ACT

Congress enacted the Clean Water Act “to restore and maintain the chemical, physical and biological integrity of the Nation’s waters.” 33 U.S.C. § 1251(a) (1978). Section 301 of the Clean Water Act prohibits discharge of pollutants into navigable waters of the United States. 33 U.S.C. § 1311. Section 404 of the Clean Water Act authorizes the Corps to issue permits “for discharge of dredged or fill material into the navigable waters at specific disposal sites.” Id. § 1344. The discharge of any pollutant is unlawful unless it complies with the Act’s permit requirements. Id. § 1311(a).

A. DISCHARGE OF A POLLUTANT

“Discharge” is defined as “any addition of any pollutant to navigable waters from a point source.” Id. § 1362(12). The government argues Hallmark discharged a pollutant into Area B when it added sand'and dirt in order to fill the area, as well as when it redeposited material to the area as a byproduct of its contractors’ construction activities in clearing or leveling the area. Hallmark responds that it made no fill “addition” to Area B, but rather produced a net withdrawal in excavating for a storm water detention pond. Because Hallmark was excavating and not filling the area, any “discharge” of dredged material was merely “incidental fallback” from excavation.

Free access — add to your briefcase to read the full text and ask questions with AI

United States v. Hallmark Construction Co., 30 F. Supp. 2d 1033, 1998 U.S. Dist. LEXIS 21600, 1998 WL 886884 (N.D. Ill. 1998).

30 F. Supp. 2d 1033 (United States v. Hallmark Construction Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related