Bricks, Inc. v. United States Environmental Protection Agency

426 F.3d 918, 35 Envtl. L. Rep. (Envtl. Law Inst.) 20218, 61 ERC (BNA) 1425, 2005 U.S. App. LEXIS 22728, 2005 WL 2676668
CourtCourt of Appeals for the Seventh Circuit
DecidedOctober 21, 2005
Docket05-1125
StatusPublished
Cited by9 cases

This text of 426 F.3d 918 (Bricks, Inc. v. United States Environmental Protection Agency) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bricks, Inc. v. United States Environmental Protection Agency, 426 F.3d 918, 35 Envtl. L. Rep. (Envtl. Law Inst.) 20218, 61 ERC (BNA) 1425, 2005 U.S. App. LEXIS 22728, 2005 WL 2676668 (7th Cir. 2005).

Opinion

FLAUM, Chief Judge.

In July 2000, Environmental Protection Agency Region 5 (“the EPA”) filed a complaint against Bricks, Inc. (“Bricks”), alleging that Bricks violated the Clean Water Act, 33 U.S.C. §§ 1251 et seq. (“CWA”), by discharging dredge and fill material into wetlands without a section 404(a) permit, 33 U.S.C. § 1344. The EPA assessed class II civil penalties against Bricks, pursuant to section 309(g) of the CWA. 33 U.S.C. § 1319(g). The administrative law judge (“ALJ”), after two days of hearings, *919 issued an Initial Decision in favor of the EPA. Bricks appealed to the Environmental Appeals Board (“the Board”). The Board overturned the ALJ’s Initial Decision, finding that the EPA had not proved its case by a preponderance of the evidence.

Bricks then filed a fee and expenses application with the ALJ, pursuant to the Equal Access to Justice Act (“EAJA”). 5 U.S.C. § 504; 28 U.S.C. § 2412. The EAJA allows a defendant who prevails in an action brought by a federal agency to recover its legal fees and expenses, unless the agency’s position was substantially justified or if special circumstances would make an award unjust. 5 U.S.C. § 504(a)(1); 28 U.S.C. § 2412(d)(2)(A)(ii). Bricks contended that the EPA’s position was not substantially justified and also argued that it was entitled to fees in excess of the statutory maximum of' $125 per attorney hour. The ALJ granted Bricks’ fees and expenses, but denied Bricks’ request for attorney’s fees in excess of the statutory maximum. The EPA appealed and Bricks cross appealed to the Board. The Board reversed the ALJ’s award of fees, finding that the EPA was substantially justified in bringing its complaint against Bricks. Bricks petitions for review of the Board’s decision and asks this Court to reinstate the ALJ’s fee award and to award Bricks attorney’s fees in excess of the statutory cap. For the following reasons, we deny Bricks’ petition.

I. Background

Bricks owns a triangular piece of farmland in North Aurora, Illinois that is bordered on the east by Orchard Road, the west by Deerpath Road, and the south by Interstate 88 (“the property”). The property is located approximately two to three miles east and fifteen miles south of Fox River, a navigable water, and one to two miles west of a non-navigable tributary of Blackberry Creek. A portion of the property contains wetlands.

In 1997, Bricks began planning to develop the property. Bricks wished to install an access road connecting the property to Orchard Road and Deerpath Road. Bricks hired Environmental Planning Team Chicago (“EPT”) to perform a wetlands delineation on the property, following the procedures set forth in the U.S. Army Corps of Engineers’ Wetlands Delineation Manual. EPT found that there were approximately eleven acres of wetlands on the property, one-third of an acre of which would be filled to construct the access road, and advised Bricks that it would need to obtain a Nationwide or Individual Permit before filling the wetlands. 1 Bricks directed its engineering consultant, Manhard Consulting, Inc. (“Manhard”) to obtain permits from the Corps, and Man- *920 hard hired Environmental Consultants and Planners (“ENCAP”) to obtain any necessary permits. ENCAP concluded that Bricks’ plans to install the access road would impact 0.3 acres of wetlands and would be covered under a Nationwide Permit. ENCAP then submitted a Pre-Certi-fication Notification to the Corps, asking the Corps to confirm that the project was covered under a Nationwide Permit.

Bricks began constructing the access road before it received a response from the Corps, completing the road between August 23 and 25, 1999. The Corps notified Bricks on August 23, 1999 that it had received Bricks’ Pre-Construction Notification and that, according to a preliminary evaluation, the project would require authorization under Nationwide Permit 26 or under an Individual Permit.

Subsequently, the Corps was informed that Bricks was already developing the property. A Corps employee visited the property and observed that Bricks had placed fill in a wetland area while constructing the access road. The Corps issued a Cease and Desist Order to Bricks on August 26, 1999. During later investigations, employees of the Corps, the EPA, and the local Soil Conservation District found that Bricks had destroyed wetlands when constructing the access road and two retention basins.

The Corps then responded by letter to Bricks’ Pre-Certification Notification. The Corps reported that Nationwide Permit 14 would cover Bricks’ construction of the access road, but not the two retention basins. Bricks would need to obtain an after-the-fact permit to be covered by Nationwide Permit 26. While Bricks was attempting to obtain an after-the-fact permit from the Corps, the EPA issued a Findings of Violation and Compliance Order (“Compliance Order”) stating that Bricks was in violation of section 301 of the CWA. 33 U.S.C. § 1311. The Compliance Order required Bricks to submit an after-the-fact application to the EPA, containing a mitigation plan for restoring wetlands located on the property. Bricks submitted the application in January 2000. On June 7, 2000, the Corps issued Bricks an after-the-fact permit pursuant to Nationwide Permit 26, authorizing Bricks to discharge materials into 1.05 acres of wetlands on the property.

On July 21, 2000, the EPA filed an administrative complaint, alleging that Bricks used bulldozers and other earth-moving machinery to discharge approximately 8,000 cubic yards of fill into wetlands on its property; that, under the CWA, this activity constituted discharge of pollutants; and that because Bricks did not have a permit under section 404 of the CWA, 33 U.S.C. § 1344, Bricks had violated section 301 of the CWA, 33 U.S.C. § 1311. The complaint also alleged that the wetlands are adjacent to an unnamed tributary of Blackberry Creek, which is itself a tributary of Fox River, an interstate water within the ambit of the CWA. This made the wetlands “waters of the United States,” protected by the CWA. See 33 U.S.C. § 1362(7). Bricks responded by arguing, among other things, that the wetlands were isolated and did not fall under CWA jurisdiction. Therefore, according to Bricks, the company was not required to obtain a section 404(a) permit. See 33 U.S.C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
426 F.3d 918, 35 Envtl. L. Rep. (Envtl. Law Inst.) 20218, 61 ERC (BNA) 1425, 2005 U.S. App. LEXIS 22728, 2005 WL 2676668, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bricks-inc-v-united-states-environmental-protection-agency-ca7-2005.