United States v. Electronic & Missile Facilities, Inc.

364 F.2d 705
Court of Appeals for the Second Circuit·Decided October 28, 1966·No. 30225·Published·Cited by 4 cases

Opinion

364 F.2d 705

UNITED STATES of America for the Use and Benefit of CAPOLINO
SONS, INCORPORATED, Plaintiff-Appellant,
v.
ELECTRONIC & MISSILE FACILITIES, INC., and Continental
Casualty Company, Defendants-Appellees.

No. 278, Docket 30225.

United States Court of Appeals Second Circuit.

Argued Feb. 23, 1966.
Decided Aug. 12, 1966, Certiorari Denied Oct. 28, 1966, See
87 S.Ct. 239.

Morris Wagman, New York City, for plaintiff-appellant.

Nathan Cohen, Valley Stream, N.Y., for defendants-appellees.

Before WATERMAN, MOORE and FRIENDLY, Circuit Judges.

WATERMAN, Circuit Judge:

Capolino Sons, Inc., use-plaintiff, appeals from a lower court order, entered on November 22, 1965, granting appellees' motion to stay proceedings in an action to recover contract damages brought by appellant against appellees,1 pursuant to Sections 1 and 2 of the Miller Act. 40 U.S.C. 270a-270b. The court below ordered appellant's action stayed pending arbitration of the dispute in accordance with the arbitration provision contained in the contract between appellant and Electronic & Missile Facilities, Inc. We affirm the lower court's order staying proceedings pending arbitration.

The facts are not disputed. General Services Administration awarded the appellee, Electronic & Missile Facilities, Inc., a contract to alter the seventh floor of a building located at 850 Third Avenue, Brooklyn, New York, for use as a Food & Drug Administration laboratory. Pursuant to Section 1(a) (2) of the Miller Act, 40 U.S.C. 270a(a)(2), Electronic & Missile Facilities furnished a payment bond, executed by the appellee Continental Casualty Company, guaranteeing payment to all persons supplying labor or materials in the prosecution of the alterations. Appellant was a subcontractor on the project and was primarily responsible for certain lathing, plastering, and furring work. The present action is a suit on the payment bond, brought by appellant pursuant to Section 2(a) of the Miller Act, 40 U.S.C. 270b(a), alleging appellant is owed an unpaid balance for work performed and materials supplied under the subcontract. The appellees successfully moved to stay the action on the ground that the subcontract between appellant and Electronic & Missile Facilities expressly provided for the arbitration of all disputes between them.

Section 2(a) of the Miller Act, 40 U.S.C. 270b(a), provides that every person who has furnished labor or materials in the prosecution of a construction project for the United States subject to the terms of the Act and who has not been paid therefor within ninety days 'shall have the right to sue on such payment bond for the amount, or the balance thereof, unpaid at the time of institution of such suit and to prosecute said action to final execution and judgment for the sum or sums justly due him * * *.' Section 2(b) of the Miller Act, 40 U.S.C. 270b(b), goes on to provide that every such suit 'shall be brought in the name of the United States for the use of the person suing, in the United States District Court for any district in which the contract was to be performed and executed and not elsewhere * * *.' Appellant contends it cannot be required to arbitrate its dispute with Electronic & Missile Facilities, even though it agreed to do so, because the language of the Miller Act, quoted above, not only guarantees it a right to sue the prime contractor and the surety in the federal district court for any district where the contract was to be performed, but also prohibits it from agreeing to substitute the mechanisms of arbitration for this right. In short, appellant urges us to hold that an otherwise valid agreement appellant entered into to arbitrate is repugnant to Section 2 of the Miller Act and thus cannot be enforced against appellant in proceedings instituted pursuant to that Section.

We are entirely unpersuaded by appellant's argument. First, it is quite clear that there is no explicit inconsistency between the provisions of the Miller Act and the provisions of the United States Arbitration Act. 9 U.S.C. 1-14. Certainly both acts can apply simultaneously to situations like that now before us. Though a materialman like appellant would otherwise be free, pursuant to Section 2(a) of the Miller Act, if he were not paid within ninety days after the last material had been furnished, to sue the prime contractor and the surety on the contractor's payment bond, there is no inconsistency in requiring that an arbitration precede resort to the courts if the materialman and the contractor had previously agreed to arbitrate disputes. Pending the arbitration a materialman could protect against the running of the one year statute of limitations found in Section 2(b) of the Miller Act by filing a protective suit, and the complaint could later be amended in the light of the arbitration award.

Free access — add to your briefcase to read the full text and ask questions with AI

United States v. Electronic & Missile Facilities, Inc., 364 F.2d 705 (2d Cir. 1966).

364 F.2d 705 (United States v. Electronic & Missile Facilities, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related