United States v. Dunning Construction Company

223 F.2d 723
CourtCourt of Appeals for the Tenth Circuit
DecidedJune 28, 1955
Docket4874_1
StatusPublished

This text of 223 F.2d 723 (United States v. Dunning Construction Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Dunning Construction Company, 223 F.2d 723 (10th Cir. 1955).

Opinion

223 F.2d 723

UNITED STATES of America, The Department of the Army
(formerly War Department), of the United States of
America; and War Contract Hardship
Claims Board, Appellants,
v.
CHAS. M. DUNNING CONSTRUCTION COMPANY, Appellee.

No. 4874.

United States Court of Appeals Tenth Circuit.

May 23, 1955.
Rehearing Denied June 28, 1955.

Isidor Lazarus, Atty., Department of Justice, Washington, D.C. (Warren E. Burger, Asst. Atty. Gen., Paul W. Cress, U.S. Atty., Oklahoma City, Okl., and Melvin Richter, Atty., Department of Justice, Washington, D.C., were with him on the brief), for appellants.

R. C. Jopling, Jr., Oklahoma City, Okl. (F. M. Dudley, Oklahoma City, Okl., was with him on the brief), for appellee.

Before PHILLIPS, Chief Judge, and BRATTON and HUXMAN, Circuit Judges.

HUXMAN, Circuit Judge.

This was an action by Charles M. Dunning Construction Company, herein called the contractor, under the Lucas Act,1 as amended, to recover certain losses on a war contract. Trial was had to the court sitting as a court of equity. Judgment was entered in favor of the contractor and against the United States and the Department of the Army for $177,526.01, together with costs of the action.

The Lucas Act provided for reimbursement of losses sustained by contractors on war contracts under certain conditions between September 16, 1940, to August 14, 1945. During this period the contractor performed seven war contracts as an individual contractor. In addition it and two other contractors as joint venturers performed two additional war contracts. The contract on which a substantial loss was claimed, on which the claim was filed, and on which this suit was predicated, was contract No. W-957-eng-1890, herein called the principal contract. The other contracts need not be specifically designated or analyzed herein.

The contractor claimed it sustained a large loss in the performance of the principal contract because of delay without its fault and because of additional requirements by the Government. On October 16, 1943, it filed with a representative of the Government a request for an adjustment of the contract in the amount of $570,781.59, all of which loss was claimed because of 28 days delay. By subsequent letter it modified its claim to $489,098.50. After conferences between the respective parties, it was agreed that under the First War Powers Act of 1941,2 which was in force at that time, the contractor was entitled to recover a certain amount of losses which it incurred. The claim was eventually amended and adjusted to $309,500.74, and after some minor adjustments the claim was paid in an amount of $312,827.70. As a condition of receiving payment, the contractor was required to and did sign a release of all claims it might have against the Government, except a small claim for painting.

On January 18, 1947, after the passage of the Lucas Act, the contractor filed a timely claim with the proper agency which as ultimately corrected sought the recovery of an additional sum of $207,071.27 on the principal contract. This claim stated that it was being submitted pursuant to the Lucas Act and in accordance with Executive Order 9786. The company's claim of October 16, 1943, and the amendment thereto were referred to therein and copies of the same were attached. All of the remaining eight contracts with the Government in which the contractor had participated between September 16, 1940, and August 14, 1945, were mentioned and taken into account in the claim. The relief sought was not in excess of the claimed net loss on all Government contracts. The claim was considered by the War Contract Hardship Claims Board and was dismissed for the reason that the settlement of the original claim was considered a bar by virtue of Executive Order 9786.

The main item from which loss stemmed in the performance of the principal contract was delay. Because of delays the Government required the contractor to work on a basis of a 24 hour day and 7 days a week and to add sufficient plant equipment and labor to insure completion of the project within the contract time. It is not necessary to detail the items of additional expense incurred because of this. It is sufficient to say that the increased expenditures were heavy. The trial court found that there was a total of 28 days in delays which were not caused by the fault or negligence of the contractor. In our view the record sustains this finding.

Numerous assignments of error are urged for reversal to which consideration will be given. It is contended that the contractor's written request for relief prior to August 14, 1945, failed to confer jurisdiction or prove a cause of action under Section 3 of the Lucas Act because relief was claimed on only the principal contract. It is contended that the claim should have been based on all nine contracts in which the contractor participated. Obviously, this position is untenable. The letter dated October 16, 1943, submitting one claim in the sum of $489,098.50 and the letter of July 17, 1944, modifying the original claim to $309,500.74 were both submitted with respect to loss suffered on the principal contract. Neither letter made reference to the remaining eight contracts because nothing was sought to be recovered under any of those contracts. Recovery only of loss on the principal contract was sought under the First War Powers Act. At the time the original claim was made, the Lucas Act had not been enacted. After the passage of the Lucas Act and under its provisions the contractor sought, as it had a right to, to recover the balance of its claimed loss on the principal contract which it had not received in the first settlement and which it could now claim under the Lucas Act by complying with its provisions. All that it sought was recovery of the balance of the loss on the principal contract. It was not required to make a claim for loss on all contracts it had with the Government. Save for the provision of Section 2 of the Lucas Act, providing that the respective department or agency should not allow any amount in excess of the net loss on all contracts held by the claimant with the Government between September 16, 1940, and August 14, 1945, no reference need have been made to the remaining contracts. But to comply with that provision it was necessary to call them to the attention of the proper agency. Reference was made to these other contracts in the claim filed under the Lucas Act to recover the balance of the uncompensated loss on the principal contract. The Government was apprised of those contracts and the status thereof. Failure to claim loss on any of them was not fatal to a proper claim for the balance of the loss which the contractor claimed had not been recovered in the settlement of its claim filed under the First War Powers Act.

Meister v. United States, D.C., 106 F.Supp. 292, upon which the Government relies, is not applicable because there the claimant under the Lucas Act failed to make any disclosure of some additional 20 contracts which he had performed for the Government during the period of time covered by the Act. There was also a suggestion of fraud on the part of the claimant.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Jones
131 U.S. 1 (Supreme Court, 1889)
Reid v. United States
211 U.S. 529 (Supreme Court, 1909)
Illinois Surety Co. v. United States Ex Rel. Peeler
240 U.S. 214 (Supreme Court, 1916)
Munro v. United States
303 U.S. 36 (Supreme Court, 1938)
Fogarty v. United States
340 U.S. 8 (Supreme Court, 1950)
Howard Industries, Inc. v. United States
83 F. Supp. 337 (Court of Claims, 1949)
Fogarty v. United States
80 F. Supp. 90 (D. Minnesota, 1948)
Warner Const. Co. v. Krug
80 F. Supp. 81 (District of Columbia, 1948)
United States v. Chas. M. Dunning Construction Co.
223 F.2d 723 (Tenth Circuit, 1955)
Holt-Fairchild Co. v. United States
111 F. Supp. 930 (Court of Claims, 1953)
Rosner v. United States
113 F. Supp. 439 (Court of Claims, 1953)
Warner Construction Co. v. United States
115 F. Supp. 465 (Court of Claims, 1953)
Spicer v. United States
118 F. Supp. 377 (Court of Claims, 1954)
Ross Engineering Co. v. United States
120 F. Supp. 188 (Court of Claims, 1954)
Stephens-Brown, Inc. v. United States
81 F. Supp. 969 (W.D. Missouri, 1949)
Prebilt Co. v. United States
88 F. Supp. 588 (D. Massachusetts, 1950)
Meister v. United States
106 F. Supp. 292 (N.D. Ohio, 1952)
McGann Mfg. Co. v. United States
98 F. Supp. 225 (M.D. Pennsylvania, 1951)

Cite This Page — Counsel Stack

Bluebook (online)
223 F.2d 723, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-dunning-construction-company-ca10-1955.