Spicer v. United States

118 F. Supp. 377, 127 Ct. Cl. 428, 1954 U.S. Ct. Cl. LEXIS 55
CourtUnited States Court of Claims
DecidedFebruary 2, 1954
DocketNo. 48871
StatusPublished
Cited by3 cases

This text of 118 F. Supp. 377 (Spicer v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Spicer v. United States, 118 F. Supp. 377, 127 Ct. Cl. 428, 1954 U.S. Ct. Cl. LEXIS 55 (cc 1954).

Opinions

MaddeN, Judge,

delivered the opinion of the court:

The plaintiff sues for losses incurred by him in the performance of contracts with the Government. The suit is based upon the Lucas Act, 60 Stat. 902, 41 U. S. C. 106 Note, as amended, 62 Stat. 992.

During the statutory period to which the Lucas Act is applicable, i. e. from September 16,1940, to August 14,1945, the plaintiff performed work under contracts with the United States Army Corps of Engineers, the work consisting of the construction of streets, roads, runways, taxiways, aprons, and drainage of oil fields in Texas, Oklahoma, Kansas, and Arkansas. Most of this work was done in the last half of 1942 and the first half of 1943.

The plaintiff made a profit on some of his contracts, but lost money on most of his large contracts. He lost money on the Palacios Airport contract which contract involved more than a million dollars, and on his contracts at Newport, Arkansas and Perry, Oklahoma, each of which had a contract price of about $400,000. He made money on a one million dollar contract at the Winfield, Kansas, airport, and lost money on two small contracts for about $20,000 each at Gamp Chaffee, Arkansas, and Muskogee, Oklahoma.

On October 26, 1943, the plaintiff filed an application for relief under the First War Powers Act, the application relating to the Winfield, Newport, Perry and Palacios contracts. The amount claimed was $445,095.18. In February and March 1944, the plaintiff filed supplementary applications for relief under the First War Powers Act for losses sustained on these same contracts. The amount claimed was $412,079.73. After an investigation, the Corps of Engineers made supplemental agreements with the plaintiff as to each of these contracts which gave him $137,232.75 in settlement of his requests for relief under the First War Powers Act on the three contracts on which the present suit is based.

After the enactment of the Lucas Act on August 7, 1946, the plaintiff, on January 25, 1947, filed a claim for relief under the Lucas Act. That claim was denied by the Chief, Army Engineers, and by the War Hardship Claims Board because Paragraph 204 of Executive Order 9786, issued in implementation of the Lucas Act provided that no claim [431]*431should be allowed if it had been considered and final action had been taken on it before August 14,1945.

The plaintiff then filed his suit in this court. The Government made a motion to dismiss. We denied the motion on the ground that Paragraph 204 of Executive Order 9786, was invalid because it was in contradiction of the provisions of the Lucas Act which it purported to implement. A. J. Spicer v. United States, 113 C. Cls. 267. On May 27, 1949, this court issued an order requiring plaintiffs in Lucas Act cases and the Government to prepare audits showing their respective positions with reference to losses incurred by plaintiffs on which claims had been made, and losses on all Government contracts during the pertinent period. Such audits were made, and the attorneys for the parties prepared a stipulation with reference to losses. At the beginning of the trial of the case before the Commissioner of this court this stipulation was read into the record. It said “the parties agree that the loss incurred during the periods of performing the contracts involved in this suit amounted to $309,939.21 in excess of the amounts which have been paid the plaintiffs.” Government counsel said that he agreed that the figures were correct “except for some adjustment on the insurance.” No question of insurance is now in controversy. He further said “However, the Government does not agree that the plaintiff is entitled to recover the amount shown; and first it would have to prove that the $309,000 figure represents losses which were not due to fault or negligence of the plaintiff. Second, the Government’s position further is that it is a legal question of prior settlement.”

This court having already decided, as shown above, that the prior settlement did not preclude recovery, counsel’s statement about prior settlement merely reserved the right to present again to this court, or to present to the Supreme Court, that legal question. The stipulation, then seemed to leave no question of fact to be tried except that of whether the plaintiff’s losses were due to his fault or negligence. The stipulation was so interpreted by the parties. At hearings, most of which took place approximately a year after the stipulation had been entered in the record, the only evidence presented was evidence as to fault or negligence.

[432]*432Our Commissioner made his findings of fact, based in relevant part upon the stipulation. The Government, in its bi’ief, takes the position that the stipulation is substantially worthless; that the figure of $309,939.21 produced by the audits is not an amount which the plaintiff may recover, even if he persuades us that his losses were not due to his fault or negligence. It says that, as to each of the contracts, the plaintiff may not recover more than it lost, which amount we do not know, and that, even if we knew it, the plaintiff could not, as to that contract, recover more than it claimed in its written requests for relief made before August 14,1945, less the amount which was awarded it by way of relief on that contract by the administrative action under the First War Powers Act.

If we were to adopt the Government’s position, the case would be substantially where it was four and one-half years ago when we denied the Government’s motion to dismiss and sent the case to trial. The whole purpose of our requirement of audits preliminary to trial would be nullified. We have a right to assume that, under the guidance of counsel, the audits made will be intelligently made, and will produce figures which are relevant to the solution of the case. Here the audit was made, it was put into the hands of experienced Government counsel, and, on the basis of the audit, he entered into a stipulation that the plaintiff’s losses were $309,-939.21. He meant, of course, the plaintiff’s Lucas Act losses, since otherwise the stipulation would have been useless and meaningless. And he said so, by inescapable inference, in his statement as to what defenses the Government still relied on. We are not willing to set aside the stipulation, and reopen the case for the purpose of allocating losses to particular contracts.

We think, however, that the amount named in the stipulation is in excess of what the law permits the plaintiff to recover and, since that error can be corrected on the present record and without delay, we will correct it.

Section 3 of the Lucas Act provides that:

Claims for losses * * * shall be limited to losses with respect to which a written request for relief was filed with such department or agency on or before August 14, 1945 * * *.

[433]*433As we have seen, the plaintiff filed a request for relief on October 26,1943, claiming $445,095.18. This claim included a small item for the Winfield contract on which, as it later appeared, the plaintiff made a profit. In February and March 1944, the plaintiff filed itemized requests on the three contracts which are the ones involved in this suit. The total amount claimed was $412,079.73. These claims were intended to amend and replace the October 26,1943 claim. On these claims the plaintiff was awarded $137,232.75 by the Chief of Engineers. That left $274,846.98 requested and not paid.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Dunning Construction Company
223 F.2d 723 (Tenth Circuit, 1955)
United States v. Chas. M. Dunning Construction Co.
223 F.2d 723 (Tenth Circuit, 1955)
Ross Engineering Co. v. United States
120 F. Supp. 188 (Court of Claims, 1954)

Cite This Page — Counsel Stack

Bluebook (online)
118 F. Supp. 377, 127 Ct. Cl. 428, 1954 U.S. Ct. Cl. LEXIS 55, Counsel Stack Legal Research, https://law.counselstack.com/opinion/spicer-v-united-states-cc-1954.