Prebilt Co. v. United States

88 F. Supp. 588, 1950 U.S. Dist. LEXIS 4189
CourtDistrict Court, D. Massachusetts
DecidedJanuary 30, 1950
DocketCiv. No. 7433
StatusPublished
Cited by4 cases

This text of 88 F. Supp. 588 (Prebilt Co. v. United States) is published on Counsel Stack Legal Research, covering District Court, D. Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Prebilt Co. v. United States, 88 F. Supp. 588, 1950 U.S. Dist. LEXIS 4189 (D. Mass. 1950).

Opinion

FORD, District Judge.

This is an action against the United States and Raymond M. Foley as Administrator of the Housing and Home Finance Agency, a branch of the Public Housing Administration,1 under the provisions of the War Hardship Claims Act, sometimes called the Lucas Act, Act Aug. 7, 1946, Public Law 657, 79th Congress, 60 Stat. 902, as amended, 41 U.S.C.A. § 106 note, in which plaintiff, The Prebilt Company, seeks a determination by the court of what sums, if any, are equitably due to. plaintiff as a claimant under said Act, and an order directing the Agency to.settle the claim in accordance with the finding of the court.

Defendants harve moved for judgment on the pleadings or, in the alternative, for summary judgment. Affidavits with attached exhibits have been filed by defendants in support of their motion, and counter-affidavits have been filed by plaintiff.

Plaintiff in 1942 and 1943 entered into seven contracts with the Federal Public Housing.Authority for the prefabrication, construction, and erection of certain dwelling units and community buildings: These contracts will be referred to by the numerals I through VII placed before the contract designations as follows:

I Contract No. WAH(D-Mass-19061)-l

II Contract No. HA (Conn-6018) eph-1

III Contract No. HA(Conn-G037)cph-189

IV Contract No. HA(Conn-G037)cpIi-190

V Contract No. HA(Conn-6132)cph-107

VI Contract No. HA(Conn-6133)cph-103

VII Contract No. HA(Conn-6202)cpiL-102

The contracts were completed and the work accepted by the Agency. Defendants thereupon, during 1943 and 1944, filed as to each of them a signed certificate and release. As to contracts III and VII these certificates made no exceptions of further claims under the contract. Claims excepted as to contracts II and IV were satisfied in full, and claims excepted under the remaining contracts only in part, a total of $126,079.25 in claims under these contracts being denied.

On March 10, 1944, plaintiff submitted revised certificates and releases on contracts I, II, and IV. Additional claims excepted in these latter releases were considered and disallowed by the Agency, the Agency expressly reserving its -rights under the previously executed releases on said contracts.

Thereafter, at various dates during 1944, plaintiff submitted to the contracting officer claims for increased costs and damages under all contracts except III and VII. At some time plaintiff orally requested that these be considered as claims under Executive Orders 9001 and 9116, 50 U. S.C.A.Appendix, § 611 note, issued pursuant to the First War Powers Act of 1941, 50 U.S.C.A.Appendix, § 611. These claims were denied by the contracting officer, and plaintiff appealed these denials by letter to the Commissioner of the Federal Public Housing Authority. Each of these letters contained a paragraph in substance the same as the following from the letter of April 2, 1945 referring to contracts III, V, and VI: “The Prebilt Company specifically requests- that James B. Blandford, Administrator, and Philip M. Klutznick, Commissioner grant it relief, and to rewrite the contracts on these three named projects under the authority of powers granted by Executive Orders 9001,- 9116- and otherwise.”

These letters, covering all contracts except III and VII, were all dated not later than April 2, 1945. These appeals were all considered and denied, notice of the denial being sent to plaintiff by letters of various dates between August 31, 1945- and May 14, 1946.

By letter of March 19, 1946, plaintiff represented its claims as to all seven contracts, in the amount of $686,910.81, to the-contracting officer, asking relief under Section 201 of the First War Powers Act [591]*591of 1941, 50 U.S.C.A.Appendix, § 611. These claims were rejected by the contracting officer by letter dated April 11, 1946.

Thereafter, on December 18, 1946, plaintiff submitted to the Federal Public Housing Authority a claim in the sum of $405,-009.58 under the Lucas Act, together with supplementary data filed on -February 5, 1947. These claims were rejected by the Agency by letter dated March 16, 1948 and plaintiff thereupon brought this action.2

Defendants contend that judgment should be rendered in their favor because plaintiff is not entitled to relief under the Lucas Act on the following grounds:

1. Plaintiff failed to file requests for relief before August 14, 1945.

2. Plaintiff’s claim filed under the Lucas Act was not in conformity with that Act and regulations issued thereunder.

3. Plaintiff is barred from maintaining this action by the releases which it executed in 1943 and 1944.

4. Plaintiff is barred from relief because its claims were considered and rejected on the merits under the First War Powers Act of 1941.

The first question is whether plaintiff before August 14, 1945 filed a claim fulfilling the requirements of § 3 of the Lucas Act.3 Defendants’ contention is that since the various claims filed by plaintiff prior to that date did not specifically set forth that they were for “losses”, these claims do not fulfill the requirements of the Act. The basis for relief under the Lucas Act is that the contractor has suffered losses without fault or negligence on his part. But this basis for relief appeared in the statutes only with the enactment of the Lucas Act itself on August 7, 1946. Relief under the First War Powers Act previous to August 14, 1945 had been on the basis of whether the granting of it would facilitate the prosecution of the war. Surely a claimant under the Lucas Act is not to be barred because, when it sought relief months before August 14, 1945, it was not enough of a prophet to phrase its claims specifically in the words of a statute which was still months in the future. It is enough if, before that critical date, it put the government on notice that it sought not merely such adjustments as it might be entitled to have made as a matter of right under its contract, but also that it asked relief over and above its strict contract rights. On this basis, the plaintiff’s letters, above referred to, appealing to the head of the Agency from the denial of its claims by the contracting officer were sufficient notice that those claims were brought as claims for relief. While not specifically referring to the First War Powers Act, they did cite the Executive [592]*592Orders issued under that Act, and thus made the claims requests for the extraordinary relief which was then' available to contractors. Howard Industries, Inc., v. United States, 83 F.Supp. 337, 340, 113 Ct.Cl. 231.

It is true that the total amount sought by plaintiff in these requests for relief under Executive Orders 9001 and 9116 was $264,553.53 and that the amount sought by the present complaint is $405,-009.58. No requests for the additional sums now sought were filed before August 14, 1945. This variation in the amounts claimed is not a ground for judgment for the defendants at this stage of the proceedings. Plaintiff is entitled to go to trial on the merits of at least so much of its present claims as were properly presented, and at that trial it will be proper to determine to what extent and to what items ' its recovery should be limited. Stephens-Brown, Inc. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Dunning Construction Company
223 F.2d 723 (Tenth Circuit, 1955)
United States v. Chas. M. Dunning Construction Co.
223 F.2d 723 (Tenth Circuit, 1955)
Charles M. Dunning Const. Co. v. United States
115 F. Supp. 250 (W.D. Oklahoma, 1953)
Waxman v. United States
112 F. Supp. 570 (Court of Claims, 1953)

Cite This Page — Counsel Stack

Bluebook (online)
88 F. Supp. 588, 1950 U.S. Dist. LEXIS 4189, Counsel Stack Legal Research, https://law.counselstack.com/opinion/prebilt-co-v-united-states-mad-1950.