Charles M. Dunning Const. Co. v. United States

115 F. Supp. 250, 1953 U.S. Dist. LEXIS 2398
CourtDistrict Court, W.D. Oklahoma
DecidedOctober 1, 1953
DocketCiv. Nos. 3874, 4075
StatusPublished

This text of 115 F. Supp. 250 (Charles M. Dunning Const. Co. v. United States) is published on Counsel Stack Legal Research, covering District Court, W.D. Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Charles M. Dunning Const. Co. v. United States, 115 F. Supp. 250, 1953 U.S. Dist. LEXIS 2398 (W.D. Okla. 1953).

Opinion

VAUGHT, Chief Judge.

The parties and the subject-matter being the same in each of these cases the court, on agreement of the parties, consolidated said cases for trial.

The plaintiff seeks to recover the sum of $207,041.21 claimed as losses in the performance of a contract it entered into with the United States of America (through its proper agency and hereinafter referred to as the Government or in the alternative the agency involved), on May 25, 1943, designated as contract No. W-957-eng-1890, by the terms of which the plaintiff agreed, for the consideration named therein, to furnish certain material and all labor necessary to construct and complete a plant, designated as Modification Center No. 17, at or near Oklahoma City, Oklahoma.

The complaint alleges as follows: Said modification center was a project essential to the war effort. Under the terms of the contract the Government agreed to furnish certain of the material called for in the plans and specifications. The contract provided that the plant should be completed within 116 days. The plaintiff commenced work under the contract on May 27, 1943 and completed its contract on or about September 21, 1943, within the specified time. In the performance of the contract the plaintiff sustained a loss of $489,098.15, which loss was not due to the fault or inefficiency of plaintiff, or to any other cause over which it had control, but was due to the acts of the Government, said loss resulting solely from delays in furnishing materials as required by it under the contract. Such delays caused a loss of 28 days time, or approximately 25 per cent of the 116 days time allocated under the contract for construction. In order to overcome the delay, plaintiff was compelled to hire a great number of additional workmen on the job, and due to labor conditions, these additional workmen were only 10 to 20 per cent efficient, and by reason thereof its plans were entirely disorganized, resulting in the losses of which it complains. On October 16, 1943, plaintiff filed its claim of $489,098.15 with the proper authorities and requested it be reimbursed for said loss by an adjustment or otherwise. Thereafter an official of the Government suggested to plaintiff that while the claim seemed meritorious, only $312,827.-70 of said claim could be allowed under the First War Powers Act, 1941, and that plaintiff should file another claim in that amount. Under date of July 27, 1944, plaintiff submitted a claim for an adjustment of the contract price in the sum of $312,827.70. On August 10,1944, a supplemental agreement, “Modification No. 29,” was entered into between plaintiff and the Government, under which the terms of the aforesaid contract No. W-957-eng-1890 were modified pursuant to the First War Powers Act, 1941, 50 U.S.C.A.Appendix, § 601 et seq., and Executive Order 9001, 50 U.S.C.A.Appendix, § 611 note, by increasing the amount of the contract by $312,827.70, which sum was thereafter duly paid to plaintiff and the completed modification center was duly accepted by the Government. No action has ever been taken on plaintiff’s claim of $489,098.15. On January 22, 1947, plaintiff filed a [252]*252claim for $207,041.21 as loss in the performance of said contract, as modified, under and pursuant to Public Law 657, 79th Congress 2nd Session, Chap. 864, 60 Stat. 902, 41 U.S.C.A. § 106 note (hereinafter referred to as the Lucas Act). Said claim was submitted to the War Contract Hardship Claims Board (hereinafter referred to as the Board), and thereafter said Board entered its order denying and dismissing the claim (copy of which was attached to and made a part of the complaint).

Plaintiff contends that its claim of January 22, 1947 in all things complied with the Lucas Act and Executive Order 9786, dated October 5, 1946, U.S. Code Cong.Service 1946, p. 1848, and showed on its face that plaintiff was entitled to receive the sum of $207,041.-21. That it had on file with the War Department before August 14, 1945 a written request for relief for the loss incurred under said contract in the sum of $489,098.15, but it did agree to accept $312,827.70 upon its claim filed July 27, 1944. At that time plaintiff was faced with bankruptcy. The Army engineers .advised plaintiff it could pay that amount under the First War Powers Act in order to prevent plaintiff, as a contractor necessary to the war effort, from becoming bankrupt, but that no more could be paid under said Act, and that unless plaintiff accepted said sum, ho relief whatsoever could be secured. Plaintiff prays for judgment in the sum of $207,041.21 and such other relief as it is entitled to in the premises.

The Government set up five defenses in its answer. First, it admitted that said contract had been entered into and the terms thereof but denied that plaintiff incurred the loss amounting to $489,-098.15 alleged to have resulted from a 28-day delay in completion of the contract caused by the fault of the Government and the inefficiency of the additional labor employed, necessitated by the delays. It admitted that plaintiff on October 16, 1943, addressed a letter to an agent of the Department of the Army requesting an adjustment of its contract in the amount of $489,098.15 for losses incurred in the performance of its contract, and subsequently, on July 27, 1944, wrote a second letter revising the requested adjustment to the sum of $312,-827.70, and on August 10, 1944, an agreement was executed between plaintiff and the representative of the Department of the Army under the terms of which plaintiff’s claims, it avers, were discharged and released in full by increasing the amount of the contract by $312,-827.70, paid to the plaintiff. It particularly avers that both of the letters and the agreement of August 10, 1944, were solely in reference to the identical claims of loss and the identical contract and factual situation. It admits plaintiff’s allegations relative to the claim of January 22, 1947 being submitted to and subsequently denied and dismissed by the Board but denies that said claim in all instances complied with the Lucas Act and Executive Order 9786, and that on its face the claim showed plaintiff was entitled to the sum of $207,-041.21. It further denied plaintiff’s allegations relative to the claim filed October 16, 1943 being undisposed of on August 14, 1945 and contends that final action was taken on said claim prior te August. 14, 1945 and denies that plaintiff has established any claim as alleged in the complaint. Second, the Government avers plaintiff has no claim upon which relief can be granted, in that a final determination was made of plaintiff’s claim before August 14, 1945, and therefore plaintiff is not entitled to relief under the Lucas Act and paragraph 204 of Executive Order 9786. Third, it contends that plaintiff would not have been granted relief under section 201 of the First War Powers Act, 1941, and Executive Order 9001 if final action had been taken prior to August 14, 1945, therefore, plaintiff is not entitled to relief under the Lucas Act and Executive Order 9786, paragraph 307. Fourth, it contends that under the circumstances-involved, such relief would be prohibited by section 6 of the Lucas Act, for the reason that the Department of the Army [253]*253was not authorized to grant the relief in the exercise of its power under the First War Powers Act, 1941, because it found that the requested amendment to the contract would not' facilitate the prosecution of the war. And for its fifth defense, it alleges plaintiff is barred from relief under the Lucas Act for the reason that it executed a bilateral agreement on or about September 29, 1944, comprising a complete discharge and release of the claim.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fogarty v. United States
340 U.S. 8 (Supreme Court, 1950)
Howard Industries, Inc. v. United States
83 F. Supp. 337 (Court of Claims, 1949)
Warner Const. Co. v. Krug
80 F. Supp. 81 (District of Columbia, 1948)
Prebilt Co. v. United States
88 F. Supp. 588 (D. Massachusetts, 1950)
McGann Mfg. Co. v. United States
98 F. Supp. 225 (M.D. Pennsylvania, 1951)

Cite This Page — Counsel Stack

Bluebook (online)
115 F. Supp. 250, 1953 U.S. Dist. LEXIS 2398, Counsel Stack Legal Research, https://law.counselstack.com/opinion/charles-m-dunning-const-co-v-united-states-okwd-1953.