United States v. Darwin Construction Co.

680 F. Supp. 739, 1988 U.S. Dist. LEXIS 3533, 1988 WL 17108
CourtDistrict Court, D. Maryland
DecidedMarch 1, 1988
DocketCiv. Y-86-67
StatusPublished
Cited by4 cases

This text of 680 F. Supp. 739 (United States v. Darwin Construction Co.) is published on Counsel Stack Legal Research, covering District Court, D. Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Darwin Construction Co., 680 F. Supp. 739, 1988 U.S. Dist. LEXIS 3533, 1988 WL 17108 (D. Md. 1988).

Opinion

MEMORANDUM

JOSEPH H. YOUNG, District Judge.

On the date its payment was due on the civil contempt fine levied by this Court, respondent Darwin Construction Company filed a motion to set aside or reduce the fine pursuant to Fed.R.Civ.P. 59(e). In the attached order, the Court extends the time for payment of the fine for an additional fourteen days and denies respondent’s motion. This memorandum * will resolve re *740 spondent’s doubts that the Court carefully considered appropriate factors in determining that respondent was in contempt of the Court’s order to comply with the IRS summons for six days. The Court finds respondent’s legal arguments unavailing and affirms its choice of the $5000 per day level of the fine, the “specific penalty” chosen at the second stage of the contempt litigation on June 23,1986. See U.S. v. Darwin Construction Co., Inc., 679 F.Supp. 531, 532 (D.Md.1988).

On June 23, 1986, the Court ordered respondent to comply with the IRS summons or face penalties of $5000 per day for noncompliance. The order was not designed to compensate the petitioner for its expenses in bringing the suit, nor has the petitioner ever pled or proven such expenses. Rather the purpose of this second-stage contempt order was coercive, but not punitive: it was chosen to encourage respondent to produce documents which they continued to withhold even after this Court’s initial order was affirmed on interlocutory appeal. At the third-stage of this contempt litigation, the Court held an assessment hearing on January 22,1988, to determine whether the fine should be imposed. In the memorandum opinion and order dated February 4, 1988, the Court found that respondent violated the Court’s second-stage order for a period of six days and ordered it to pay $30,000 into the Registry of the Court. The Court based its determination of contempt upon the respondent’s proferred theory of substantial compliance, but also made a finding upon respondent’s good faith defense.

RESPONDENT’S DEFENSES

The essence of respondent’s argument is that “it is clear that Darwin did everything it possibly could after the order was entered” and that the “order served its purpose, and Darwin should not now be subject to an inordinately severe fine that in effect punishes Darwin for what the Court feels Darwin failed to do prior to the entry of the contempt order.” Respondent’s memorandum in support at 14. The Court rejects both assertions.

Respondent attacks the basis of the Court’s ruling upon these two defenses and implies that the Court improperly considered Darwin’s inadequate preparation for production of documents in determining its subsequent non-compliance. Respondent’s memorandum at 12-14. Specifically, Darwin claims that the items produced six days late were “lost” and that “considering only the period from the contempt order forward, immediate production of the lost items was impossible.” Id. at 13. “Because this is a civil contempt proceeding, the Court should consider only Darwin’s efforts to comply subsequent to the contempt order. Focusing on these efforts, it is clear that Darwin did everything it possibly could after the order was entered.” Id. at 14 (emphasis in original).

Darwin was required to comply substantially with the Court’s order. Substantial compliance is found where “all reasonable steps” have been taken to ensure compliance: inadvertent omissions are excused only if such steps were taken. See 679 F.Supp. at 536. Darwin argues only that there were “difficulties in arranging compliance____ Darwin could not reasonably be expected to find financial records that were labelled with the wrong year or that were located in a closed box of engineering materials buried behind dozens of other boxes in Darwin’s cramped quarters.” Respondent’s memorandum at 12. But Darwin does not assert that the documents missing from the first production on June 24, 1986, were beyond its possession or control. Nor does Darwin point to any special efforts made to ensure that the June 24 production was complete. Indeed, the Court found that unrefuted evidence presented at the assessment hearing showed “Skweres’ ignorance as to the contents of the nine boxes hurriedly dumped at Agent Kohorst’s office without identification or even concern regarding their completeness____” 679 F.Supp. at 537. Furthermore, neither Darwin nor its attorneys initiated contact with Agent Kohorst to ensure that the production was complete. It is clear that Darwin did not *741 take “all reasonable steps” to ensure complete production until after it was notified by Agent Kohorst that some documents were still unproduced and additional efforts to find the missing documents were made. Darwin’s efforts to achieve complete production between June 27 and June 30 do not transform its initial failure to make substantial compliance at the time of the first production. Thus, compliance was insubstantial until the second production occurred on June 30, 1986. This finding is based solely upon Darwin’s inattentiveness after the June 23 order was issued.

Darwin’s good faith defense is also rejected on the basis of its indifference regarding the completeness of the initial production, but particularly in light of the opportunity it had to prepare for production before the Court’s order on June 23, 1986. Respondent claims that “[ujnbeknownst to anybody ... there remained in Darwin’s offices following Skweres’ search [before June 23] a few items sought by the summons____” Respondent’s memorandum at 3. However, the fact that documents were found quickly after notification that they were missing from the initial production shows that they were easily obtainable before such notification. The evidence produced at the assessment hearing leaves no doubt that Darwin either knew that documents were missing or took no special steps to find out before the June 23 hearing. Darwin’s initial production, grounded in indifference and ignorance as to the completeness, did not show good faith where Darwin had over one year to ensure that all the documents listed in the summons were located and more than eight weeks’ notice that this Court’s contempt order would be enforced. Respondent’s argument that good faith is shown by Skweres’ cooperation in conducting “yet another search of Darwin’s offices to locate any records that might assist Agent Kohorst in any way, including alternative sources of the requested information,” id. at 4, is irrelevant: a good faith effort to produce documents after they are discovered missing and overdue does not show good faith regarding the initial production. The swiftness of subsequent discovery indicates only the paucity of good faith efforts to comply fully in the initial production.

REDUCTION OF THE FINE

The Court also rejects respondent’s chief demand that the fine be reduced from the threatened $5000 per day to a lower daily rate reflecting “Darwin’s efforts to comply ... sufficient ... to warrant excusing most or all of the fine.” Respondent’s memorandum at 9 n. 9.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
680 F. Supp. 739, 1988 U.S. Dist. LEXIS 3533, 1988 WL 17108, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-darwin-construction-co-mdd-1988.