United States v. City of Detroit

288 F. Supp. 2d 836, 57 ERC (BNA) 1858, 2003 U.S. Dist. LEXIS 19054, 2003 WL 22427804
CourtDistrict Court, E.D. Michigan
DecidedOctober 22, 2003
DocketCIV.77-71100
StatusPublished
Cited by2 cases

This text of 288 F. Supp. 2d 836 (United States v. City of Detroit) is published on Counsel Stack Legal Research, covering District Court, E.D. Michigan primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. City of Detroit, 288 F. Supp. 2d 836, 57 ERC (BNA) 1858, 2003 U.S. Dist. LEXIS 19054, 2003 WL 22427804 (E.D. Mich. 2003).

Opinion

OPINION AND ORDER

FEIKENS, District Judge.

INTRODUCTION

On November 22, 2000, I ordered the Army Corps of Engineers (Corps) to accept dredged materials from Conner Creek at its Confined Disposal Facility (CDF) at Pointe Mouillee. The Corps appealed. On remand, the en banc court for the United States Court of Appeals for the Sixth Circuit has ordered me to rule on the following issues: (1) whether Detroit could have sued the Corps under the Administrative Procedures Act (APA), and if so, whether “exceptional circumstances” nonetheless exist to justify use of the All Writs Act; and (2) whether the Corps’ decision to conduct an Environmental Assessment (EA) was “arbitrary” or “capricious.” U.S. v. City of Detroit, 329 F.3d 515 at 527 (6th Cir.2003) (en banc).

FACTUAL BACKGROUND

The general facts surrounding this case have been sufficiently developed in three previous (unpublished opinion), 329 F.3d 515 (6th Cir.2003) (en banc). In the interest of judicial economy, I will not recite those facts here.

What is not covered in those opinions, however, is the Corps’ history of accepting environmental dredging materials at the Pointe Mouillee CDF, which is relevant to this remand.

On May 10, 1974, the United States and the State of Michigan entered into an agreement to construct a Confined Disposal Facility at Pointe Mouillee, Lake Erie. The agreement states that the Pointe Mouillee CDF is “for the containment and retention of dredged materials from the channels of the Detroit and Rouge Rivers.” An Environmental Impact Statement (EIS) was also developed in 1974. It states that the Pointe Mouillee CDF’s main environmental impact is the “[c]on-tainment of the polluted dredge spoil [which will] remove it as a source of pollution from the open waters of the bay.” 1 U.S. Army Corps of Engineers, Final Environmental Statement; Confined Disposal Facility at Pointe Mouillee for Detroit and Rouge Rivers, Summary at ¶ 3(a) (March 1974).

ANALYSIS

A. Mootness

The Corps argues that this portion of the case is now moot, because the funding issues that existed in late 2000 do not currently exist, and because defendants might not need to use Pointe Mouil-lee CDF for disposal. (U.S. Army Corps of Engineers’ Br. Regarding Issues Remanded by the U.S. Court of Appeals for the 6th Circuit at 2.) To avoid dismissal for mootness, “an actual controversy must be extant at all stages of review, not merely at the time the complaint is filed.” Preiser v. Newkirk, 422 U.S. 395, 401, 95 S.Ct. 2330, 45 L.Ed.2d 272 (1975) (quoting Steffel v. Thompson, 415 U.S. 452, 459, n. 10, 94 S.Ct. 1209, 39 L.Ed.2d 505 (1974)) (internal quotation marks omitted). In addition, the Court must be able to provide some remedy or a case is moot. Church of Scientology of Cal v. United States, 506 U.S. 9, 12, 113 S.Ct. 447, 121 L.Ed.2d 313 *838 (1992). The party asserting mootness bears the “heavy burden of demonstrating mootness.” Cleveland Branch, N.A.A.C.P. v. City of Parma, OH, 263 F.3d 513 at 531 (6th Cir.2001) (citing County of Los Angeles v. Davis, 440 U.S. 625, 631, 99 S.Ct. 1379, 59 L.Ed.2d 642 (1979)).

Neither of the Corps’ arguments renders the case moot. The first argument simply raises a legal issue in the case (my ability to use the All Writs Act to issue an order). Even if the All Writs Act did not apply, this would not eliminate the controversy between the state and local governments and the Corps about the acceptance of dredged sediments at Pointe Mouillee CDF, nor would it prevent the grant of all possible remedies. It is evident on the face of the questions that the Sixth Circuit remanded to me that even if the All Writs Act may not provide a remedy this Court could grant, the APA may very well do so. 329 F.3d 515 (6th Cir.2003). As discussed below, this Court is empowered to give a remedy under either statute.

Moreover, the reason my 2000 order was sufficient to secure funding was because it served as a guarantee that there was a facility that would accept the dredged materials, and therefore the project could go forward if funding was provided. The Corps argues that if that guarantee evaporated today, because the loan has gone through, there would be no practical barriers to continuing the project mandated by the Consent Judgment of this Court. There were two practical barriers to the mandated project that my order cleared away, however. To go forward on time, the project had two requirements: the disposal site and funding. If funding continued despite the removal of the Court’s guarantee, that funding is used, in part, to produce dredged material that requires disposal. The fact that funding depended on securing a disposal site underscores, not obviates, that timely availability of a disposal site is crucial to the project’s success. Therefore, the potential existence of current funding issues or lack thereof does not render this ease moot.

The second potential factual change cited by the Corps, whether there is a continuing need by defendants to use Pointe Mouillee CDF for disposal, does go to the heart of the controversy that makes up this case. The Corps argues that the dredging project “may well be completed without the need for any disposal at the Pointe Mouillee CDF,” and for that cites a statement by Michigan’s counsel that also used the word “may.” (Army Corps of Engineers’ Br Regarding Issues Remanded by the U.S. Court of Appeals for the 6th Circuit, at 2 and 44, fn 14 [emphasis mine].) Other than this equivocation, the Corps cites nothing to support its assertion that the project completion would go forward without delay even if it prevented defendants from using the Pointe Mouillee CDF in a timely fashion. This single statement simply cannot bear the weight of the “heavy burden” of the party asserting mootness. 440 U.S. 625, 99 S.Ct. 1379, 59 L.Ed.2d 642.

Since I find this case is not moot for the reasons stated above, I now proceed to answer the questions the Sixth Circuit has remanded to me.

B. Applicability of the APA and use of the All Writs Act

1.

Under the APA, 5 U.S.C. § 101 et seq.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. City of Detroit
401 F.3d 448 (Sixth Circuit, 2005)
United States v. The City Of Detroit
401 F.3d 448 (Sixth Circuit, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
288 F. Supp. 2d 836, 57 ERC (BNA) 1858, 2003 U.S. Dist. LEXIS 19054, 2003 WL 22427804, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-city-of-detroit-mied-2003.