United States v. Bethlehem Steel Corp.

113 F.2d 301, 1940 U.S. App. LEXIS 4825
CourtCourt of Appeals for the Third Circuit
DecidedJune 18, 1940
DocketNos. 7045, 7119, 7046
StatusPublished
Cited by21 cases

This text of 113 F.2d 301 (United States v. Bethlehem Steel Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Bethlehem Steel Corp., 113 F.2d 301, 1940 U.S. App. LEXIS 4825 (3d Cir. 1940).

Opinion

MARIS, Circuit Judge.

In 1917 this country was at war. The war emergency made it necessary for the Government to take over all ships suitable for war purposes then under construction at the various shipyards throughout the United States and to arrange with shipbuilders for the construction of as many additional vessels as possible and to construct them with the utmost speed. In the fall of that year the United States Shipping Board Emergency Fleet Corporation (now known as United States Shipping Board Merchant Fleet Corporation and herein referred to as the Fleet Corporation), an agency of the Government, entered into negotiations for the construction of ships by the Bethlehem Shipbuilding Corporation, Ltd., (hereinafter referred to as Bethlehem), a subsidiary of the Bethlehem Steel Corporation, having a number of shipyards and an experienced shipbuilding organization. In these negotiations Bethlehem was represented by two competent shipbuilders, Joseph W. Powell and Harry Brown, and the Fleet Corporation was represented by two equally competent shipbuilding experts, Admiral F. T. Bowles and G. S. Radford, who were advised by and had full opportunity to advise with Daniel II. Cox, a competent naval engineer and estimater, and Chester. Cuthell, counsel for the Fleet Corporation. In addiiion to these representatives the interests of the Fleet Corporation were protected by Charles Piez, its vice president and general manager, who while not previously a shipbuilder was a nationally known business executive of long experience.

Three forms of contract were considered by the negotiators, a “lump sum” contract, a “cost plus” contract and a “cost plus fixed fee” contract with a “bonus for savings.” The representatives of the Fleet Corporation endeavored to get Bethlehem to bid on a lump sum basis but it refused, stating in a letter of December 13, 1917, that “Because of the unprecedented conditions surrounding the Labor and Material market, it is impracticable to estimate within a reasonable percentage what will be the actual cost of construction, and it is therefore impossible to submit fixed prices for any of these vessels, except upon a basis so far above estimated cost that any figure acceptable to this Company would not he acceptable to the Emergency Fleet Corporation. It is proposed, however, that they be constructed on the basis of actual cost phis a fee, with an agreed upon probable cost, this Company to be paid in addition to the fee one-half of any saying that may he made below this cost figure, and with the further provision that the estimated cost figure will be increased due to any increase in rates of wages that may be approved by the Emergency F'leet Corporation.”

On December 19, 1917, Admiral Bowles on behalf of the Fleet Corporation wrote [304]*304Bethlehem requesting it to submit proposals for the construction of certain ships which he specified. Under the same date Bethlehem submitted a written proposal to construct these ships under the bonus for savings forni of contract, setting forth in its proposal the estimated cost of the vessels and the fixed profit to be paid. This proposal was the subject of further conference on January 3, 1918, at which Admiral Bowles unsuccessfully tried to persuade Powell to accept lump sum contracts but was finally persuaded to agree to accept the bonus- for savings form of contract in order to reach any agreement át all. On January 5, 1918, Admiral Bowles and Radford transmitted Bethlehem’s proposal to Piez with the following memorandum:

“We hand you herewith the Bethlehem Shipbuilding Corporation’s proposal dated December 19, for additional construction at their various plants, amounting in all to 19 vessels, exclusive of tugs. It may be noted that, with the exception of three ships, the vessels in question are .troop ships and tankers — ships of a type that only real shipbuilders can produce. satisfactorily. As is well known, we have been having difficulty in placing such vessels.

“We wish to place on record the fact that the Bethlehem Shipbuilding Corporation’s representatives have insisted on comparatively high prices for these vessels; that they have only • with -difficulty been persuaded to quote us on the types of ships referred to; and, that their attitude has been characterized by an arbitrary refusal to guarantee or stand behind delivery dates. In other words, it was difficult to persuade them to quote even a tentative delivery date, and they refused positively to accede, to a bonus and penalty clause for delivery.

“The letter herewith, addressed „ to the Bethlehem Shipbuilding Corporation, in reply to their proposal, has been prepared for your signature and is now presented with the recommendation that it be signed. While the prices we have agreed to, with representatives of the Bethlehem Shipbuilding Corporation, are not satisfactory to us, nevertheless, they represent a material reduction from the prices quoted by that corporation. Realizing that tlie Nation will need these vessels, we have been actuated by the belief that further delay in placing the contracts should be eliminated and we believe that we have made the best compromise ¡possible under very difficult conditions,.” .

Prior to the receipt of this memorandum from Admiral Bowles and Radford, Piez had received a letter from Powell in anticipation of the final conference with Admiral Bowles. In this letter Powell agreed on behalf of Bethlehem “to accept the order to construct these vessels on such terms as may be personally determined by Mr. Charles Piez, the Vice President and General Manager.” On January 5, 1918, after receiving from Admiral Bowles and Rad-ford Bethlehem’s proposal and their accompanying memorandum reluctantly recommending its acceptance, Piez' on behalf of the Fleet Corporation awarded to Bethlehem seven contracts for the construction of a total of 21 tankers, eight cargo ships and 20 tugs upon the terms set forth in Bethlehem’s proposal. The contracts, which were dated December 31, 1917, were actually signed and delivered about .February 1, 1918. Subsequently in March, April and May six other contracts for the construction of 19 tankers and 18 cargo ships were executed between the parties upon substantially similar terms. All 13 of these contracts are involved in the present controversy. Five other contracts were also executed, one of them on February 1, 1918, and the others later. With them, however, we are not now concerned.

The total estimated cost of the 86 vessels involved, as set out in the contracts, was $119,750,000. The actual base cost of the ships as built was $92,990,520.91 and Bethlehem has been paid under the contracts the actual base cost of the ships, $92,990,-520.91, the cost of extras, $16,381,432.15, fixed profits specified in the contracts, $11,-962,400, and bonus for savings to the amqunt of $8,093,156.60. It will be seen that the total bonus for savings payable under the terms of the contracts would exceed $13,000,000, but the Fleet Corporation after paying Bethlehem $8,093,156.60 on this account declined to pay any more. A sum in excess of $5,000,000 is accordingly claimed by Bethlehem to be still due it from the Fleet Corporation.

The controversy with regard to the bonus for savings resulted in the institution of two suits in the District Court for the Eastern District of Pennsylvania. One was a suit in equity brought by the United States against Bethlehem Steel Corporation, Bethlehem Shipbuilding Corporation, Ltd., and certain subsidiary corporations for an accounting and to recover sums paid to the defendants or some of them under [305]*305the contracts above mentioned.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Commonwealth v. Cumberland Construction Co.
494 A.2d 520 (Commonwealth Court of Pennsylvania, 1985)
Laudenberger v. Port Auth. of Allegheny
436 A.2d 147 (Supreme Court of Pennsylvania, 1981)
Nedd v. United Mine Workers of America
488 F. Supp. 1208 (M.D. Pennsylvania, 1980)
Sun Shipbuilding & Dry Dock Co. v. United States Lines, Inc.
439 F. Supp. 671 (E.D. Pennsylvania, 1977)
Cold Metal Process Co. v. United Engineering & Foundry Co.
132 F. Supp. 597 (W.D. Pennsylvania, 1955)
Government Personnel Mut. Life Ins. Co. v. Wear
247 S.W.2d 284 (Court of Appeals of Texas, 1952)
Overfield v. Pennroad Corporation
146 F.2d 889 (Third Circuit, 1944)
United States v. Bethlehem Steel Corp.
315 U.S. 289 (Supreme Court, 1942)
Pittsburgh Can Co. v. United States
113 F.2d 821 (Third Circuit, 1940)

Cite This Page — Counsel Stack

Bluebook (online)
113 F.2d 301, 1940 U.S. App. LEXIS 4825, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-bethlehem-steel-corp-ca3-1940.