United States v. Ambroid Co., Inc.

34 F. Supp. 2d 86, 29 Envtl. L. Rep. (Envtl. Law Inst.) 21042, 48 ERC (BNA) 1411, 1999 U.S. Dist. LEXIS 963, 1999 WL 44334
CourtDistrict Court, D. Massachusetts
DecidedJanuary 26, 1999
DocketCA 97-11377-JLT
StatusPublished
Cited by5 cases

This text of 34 F. Supp. 2d 86 (United States v. Ambroid Co., Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Ambroid Co., Inc., 34 F. Supp. 2d 86, 29 Envtl. L. Rep. (Envtl. Law Inst.) 21042, 48 ERC (BNA) 1411, 1999 U.S. Dist. LEXIS 963, 1999 WL 44334 (D. Mass. 1999).

Opinion

MEMORANDUM

TAURO, Chief Judge.

Plaintiff United States brings this action under the Comprehensive Environmental Response Compensation and Liability Act (CERCLA), 42 U.S.C. § 9607, for recovery of costs incurred by the cleanup of the Yankee Chemical Corporation site from March 1992 to February 1993 and on June 17, 1994. Before the court are the parties’ cross motions for summary judgment.

I

BACKGROUND

In March 1992, the Environmental Protection Agency (EPA) instituted a cleanup operation in response to the release or the threat of release of hazardous substances from the Yankee Chemical site, pursuant to section 104 of CERCLA, 42 U.S.C. § 9604. The EPA conducted a series of cleanup and removal activities from March 1992 to February 1993, recorded in seven Pollution Reports (PolReps) by the On Site Coordinator (OSC) Carole Tucker.

The last report by OSC Tucker, dated February 12, 1993, states that the EPA *87 agents had shipped off chemical wastes, shut down electricity and telephone services, withdrew security personnel, and sealed off the premises. The EPA also left behind drums of hazardous chemicals (Penta-San and Mercury compounds) which it deemed to have no legally-approved methods of disposal. The EPA gave the Massachusetts Department of Environmental Protection (MA DEP) keys to the storage building to perform periodic inspections and to further explore methods of disposal. OSC Tucker wrote at the bottom of that final PolRep: “case closed.”

On June 16, 1994, eighteen months after the closing of the site, MA DEP informed the EPA that the site had been broken into and the drums scattered, creating new threats of release. OSC Thomas Condon was assigned to the project. OSC Condon took immediate emergency actions, and retroactively filed an Action Memorandum for funding. The drums were removed on June 17,1994.

The government alleges that total cleanup of the site cost over a million dollars. It demands judgment for that amount, as well as a declaratory judgment for all future cleanup costs. At issue is whether the government’s claim is time barred.

II

ANALYSIS

CERCLA requires the government to bring a suit to recover costs of a removal action within three years after the removal effort is completed. 42 U.S.C. § 9613(g)(2)(A). The issue in these cross motions is whether the EPA’s June 17, 1994 removal was a new removal action for purposes of § 9613(g)(2)(A), or whether it was an extension of the removal action completed on February 12, 1993.

Because there are no material facts in dispute, this issue is ripe for summary judgment. If, as the government argues, the EPA’s activities constitute one continuous “removal action” beginning in March 1992 and ending in June 1994, the government’s claim for the entire cleanup cost would be timely. If, as Defendants argue, the EPA’s actions constitute two separate “removal actions,” the first of which ended in February 1993, the costs associated with those removal activities would be barred from recovery under the three-year statute of limitations.

A. Statutory and Case Law Provide Limited Guidance

A basic rule of statutory interpretation is to give the language of the statute its “plain meaning.” See U.S. v. Gomez-Rodriguez, 96 F.3d 1262, 1264 (9th Cir.1996). Unless otherwise defined, terms should be interpreted as having their ordinary, contemporary, and common meaning. See Perrin v. U.S., 444 U.S. 37, 42, 100 S.Ct. 311, 62 L.Ed.2d 199 (1979). While CERCLA’s definition of “removal” includes all activities the EPA conducted in this case, 1 the statute does not define when removal activities become distinct, successive “removal actions.”

Most precedents on statute of limitations involve ongoing removal and remedial efforts by the EPA which made up one removal action, even though the activities were conducted in stages. These cases generally interpret “removal action” broadly. See Kelley v. E.I. DuPont de Nemours and Co., 17 F.3d 836, 843 (6th Cir.1994) (holding that the two essential purposes of CERCLA are cleaning up hazardous waste and doing so at the expense of those who created it); U.S. v. R.A. Corbett Transport, Inc., 785 F.Supp. 81, 82 (E.D.Tex.1990) (holding that all activities *88 conducted at the site, including remedial investigations, were one “removal action”).

The Sixth Circuit in Kelley found that the emergency physical removal activities conducted by the EPA from 1984 to 1986, and its removal of later discovered waste 2 in 1987, were one removal action under § 9613(g)(2)(A). See 17 F.3d at 841. The court relied on the First Circuit’s decision in Reardon v. U.S., 947 F.2d 1509, 1519 (1st Cir.1991) (en banc), which held that “[t]he running of the statute of limitations is entirely within The EPA’s control ... [t]he government may take its own sweet time before suing, and ... the removal or remedial action may itself take years to complete.” See 17 F.3d at 843.

One Wheeler Road Assoc. v. Foxboro Co., 843 F.Supp. 792, 795 (D.Mass.1994), was factually similar to Kelley. Judge Young, following the Sixth Circuit’s lead, held that “CERCLA should be given a broad and liberal construction, and should not be narrowly interpreted to frustrate the government’s ability to respond promptly, or to limit the liability of those responsible for cleanup costs beyond the limits expressly provided.”

The Wheeler plaintiff conducted clean-up in three stages: (1) an excavation of a contaminated leaching basin in 1986; (2) further assessment in 1987 to ascertain vertical and lateral extensions of the groundwater contamination; and (3) remediation and removal of the remaining contamination from the property in 1989. See id. at 794. The plaintiff brought a recovery claim, and the defendant sought a partial summary judgment to avoid the costs incurred three years before the suit was brought. Judge Young held that the plaintiffs recovery action was timely and “[t]he removal process is complete only after the very last drum of contaminated soil has been removed from the property.” Id. at 796.

The case at bar is factually distinguishable from both Kelley and Wheeler.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
34 F. Supp. 2d 86, 29 Envtl. L. Rep. (Envtl. Law Inst.) 21042, 48 ERC (BNA) 1411, 1999 U.S. Dist. LEXIS 963, 1999 WL 44334, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-ambroid-co-inc-mad-1999.