United States v. Alcoa, Inc.

533 F.3d 278, 38 Envtl. L. Rep. (Envtl. Law Inst.) 20152, 66 ERC (BNA) 1993, 2008 U.S. App. LEXIS 13358, 2008 WL 2502759
CourtCourt of Appeals for the Fifth Circuit
DecidedJune 24, 2008
Docket07-50706, 07-50820
StatusPublished
Cited by20 cases

This text of 533 F.3d 278 (United States v. Alcoa, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Alcoa, Inc., 533 F.3d 278, 38 Envtl. L. Rep. (Envtl. Law Inst.) 20152, 66 ERC (BNA) 1993, 2008 U.S. App. LEXIS 13358, 2008 WL 2502759 (5th Cir. 2008).

Opinion

PATRICK E. HIGGINBOTHAM, Circuit Judge:

Alcoa produces from lignite fuel its own electricity for an aluminum plant in central Texas. Three citizen groups sued Alcoa for alleged violations of the Clean Air Act. The United States government also sued Alcoa. The suits were consolidated, and the district court entered a consent decree agreed to by all parties. Alcoa elected an option under the decree that permitted construction of a new power plant unit with specified emissions limitations. San-dow contracted to build the new unit and joined the decree. Alcoa failed to meet the decree deadline for commencing operation of the new plant. Over the citizen groups’ objection, the district court entered an order agreed to by the government and Alcoa, giving Alcoa more time to build the plant and commence operation but enforcing other aspects of the construction and operation requirements. The order required more pollution control technology and stricter emissions limitations than originally agreed to, if the lower emissions rates were achievable. The citizen groups appealed.

I

Alcoa, under a voluntary emissions reduction permit approved and issued by the Texas Commission on Environmental Quality, operates an aluminum smelting plant in Rockdale, Texas, producing its own electricity for the plant. Neighbors for Neighbors, Inc., Environmental Defense, and Public Citizen, Inc. (“citizen plaintiffs”) brought a citizen suit against Alcoa alleging violations of the Clean Air Act, and the United States filed its own claims. The complaints alleged, inter alia, that Alcoa modified three lignite-fired boilers at its plant without first obtaining pre-construction permits. The cases were consolidated, and the parties eventually agreed to a detailed consent decree, which the district court entered. The decree gave Alcoa three options: Alcoa could A) retrofit its existing plant technologies, labeled as the existing “Sandow units,” B) build a new power plant (“replacement units”) under an amended voluntary emissions reduction permit issued by the TCEQ, or C) shut down the existing plant and purchase electricity on the open market or build a new plant after obtaining a new permit from the TCEQ. 1 The decree also gave broad enforcement powers 2 to *282 the district court and required any modifications to be in writing and agreed to by all parties. 3 Alcoa chose Option B, which set deadlines for Alcoa to commence construction of replacement units at the plant, to shut down existing boilers, and to commence operation of the new units. Option B also specified emissions rate limits for the new plant 4 and incorporated the emission rates and limitations of Alcoa’s amended voluntary emissions reduction permit into the decree.

Alcoa set out to construct a plant that would produce electricity for its facility and additional power to sell on the open market. After briefly commencing construction of one new facility, it changed course and entered into a contract with TXU Sandow Development Company, which later joined the consent decree, to build the replacement units. Facing a delay in construction and operation, Alcoa requested and received from the TCEQ an extension of the construction deadline in its amended voluntary emissions reduction permit. It also twice petitioned the court to modify or construe the deadlines within the decree; the court denied these petitions.

Having failed to meet Option B’s operation deadline, Alcoa negotiated a stipulated order with the government. The order was amended following a public comment period and then entered by the district court over citizen plaintiffs’ objections. The government, Alcoa, and Sandow agreed to approximately $1.8 million in penalties. Additionally, the stipulated order extended Alcoa’s deadline for commencing operation of the new plant by approximately two and one-half years. 5 It required that the existing plant shut down earlier than originally required by the decree 6 and set stricter emissions limits for the new facility, provided they were achievable. 7 Finally, the order required *283 installation of an additional piece of pollution reduction equipment, a selective catalytic reduction system to reduce nitrogen oxide emissions. The district court entered an amended order accepting the stipulated order with its stipulated penalties, incorporating the order into the consent decree, finding Alcoa to be in contempt of the decree, and assessing penalties and attorney’s fees as a remedial measure for the contempt.

In the meantime, Alcoa applied to the TCEQ to build a plant with a megawatt capacity exceeding its voluntary emissions reduction permit. Plaintiff citizens argued before the district court that this violated the terms of the consent decree, as the consent decree incorporated all of the permit terms, including the lower megawatt capacity. The district court held that the issue was for the state administrative process, not a federal forum. Plaintiff citizens appealed from this ruling and from the district court’s entry of the stipulated order, urging that the order was a modification of the consent decree not agreed to in writing by all parties. At oral argument, citizen plaintiffs abandoned the issue of whether the higher megawatt capacity violated the consent decree and whether the court erred in holding that the issue was properly for the state administrative forum. This leaves us with the question of whether the court’s acceptance of the stipulated order was a modification of the decree or a remedy and, if a remedy, whether the court abused its discretion in entering the provisions agreed to in the stipulated order.

II

Consent decrees are both contracts and legal instruments. In bargaining for the consent decree, citizen plaintiffs promised not to sue Alcoa provided it met the decree requirements, and Alcoa promised to meet the obligations of the decree option that it would elect to follow in order to reduce plant emissions. The contested decree provision is the deadline for commencing plant operation contained within Option B of the decree. 8 As we have discussed, Option B provided that Alcoa would construct and operate a replacement unit under an amended voluntary emissions reduction permit to be approved by the TCEQ, and would meet specified emission rates in operating the new unit. Option B incorporated into the decree the emissions rates and limitations that would be part of Alcoa’s amended voluntary emissions reduction permit, as well as any limitations contained within subsequent amendments to that permit. Finally, it required that Alcoa commence construction of the first replacement unit within 19 months after the issuance of Alcoa’s amended permit and commence operation within 43 months of issuance.

Alcoa failed to meet the operation deadline. 9

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Crawford v. City of Jackson
S.D. Mississippi, 2023
Chisom v. State of Louisiana
Fifth Circuit, 2023
Cooper v. Kliebert
M.D. Louisiana, 2021
Caliste v. Cantrell
E.D. Louisiana, 2020
Smith Ex Rel. Smith v. Sch. Bd. of Concordia Parish
906 F.3d 327 (Fifth Circuit, 2018)
Linda Frew v. Chris Traylor
820 F.3d 715 (Fifth Circuit, 2016)
Little Tchefuncte River Ass'n v. Artesian Utility Co.
155 F. Supp. 3d 637 (E.D. Louisiana, 2015)
Frew v. Janek
5 F. Supp. 3d 845 (E.D. Texas, 2013)
Chisom v. Jindal
890 F. Supp. 2d 696 (E.D. Louisiana, 2012)
Chisolm ex rel. CC & MC v. Greenstein
876 F. Supp. 2d 709 (E.D. Louisiana, 2012)
City Of El Paso Texas v. El Paso Entertainment, In
464 F. App'x 366 (Fifth Circuit, 2012)
Vandesande v. United States
94 Fed. Cl. 624 (Federal Claims, 2010)
City of El Paso, Texas v. El Paso Entertainment, Inc.
382 F. App'x 361 (Fifth Circuit, 2010)
Smeal Fire Apparatus Co. v. Kreikemeier
782 N.W.2d 848 (Nebraska Supreme Court, 2010)
Ingalls v. Thompson (In Re Bradley)
588 F.3d 254 (Fifth Circuit, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
533 F.3d 278, 38 Envtl. L. Rep. (Envtl. Law Inst.) 20152, 66 ERC (BNA) 1993, 2008 U.S. App. LEXIS 13358, 2008 WL 2502759, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-alcoa-inc-ca5-2008.