United States v. Adam Bros. Farming, Inc.

369 F. Supp. 2d 1180, 2004 WL 3332051
CourtDistrict Court, C.D. California
DecidedJuly 12, 2004
DocketCV 00-07409CAS
StatusPublished
Cited by15 cases

This text of 369 F. Supp. 2d 1180 (United States v. Adam Bros. Farming, Inc.) is published on Counsel Stack Legal Research, covering District Court, C.D. California primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Adam Bros. Farming, Inc., 369 F. Supp. 2d 1180, 2004 WL 3332051 (C.D. Cal. 2004).

Opinion

369 F.Supp.2d 1180 (2004)

UNITED STATES of America, Plaintiff,
v.
ADAM BROS. FARMING, INC.; Iceberg Holdings, L.P.; Richard Adam; Peter Adam; Kieran Adam; and Dominic Adam, Defendants.

No. CV 00-07409CAS.

United States District Court, C.D. California, Western Division.

July 12, 2004.

Lily N. Chinn, Andrew J. Doyle, Martha C. Mann of the U.S. Department of Justice Environmental Defense Section, for Plaintiff United States.

Richard P. Crane, Barry M. Hartman and Suzanne M. Henry of Kirkpatrick & Lockhart LLP and David E. Dearing, for Defendants Adam Bros. Farming Inc. et al.

ORDER DENYING CERTIFICATION FOR INTERLOCUTORY APPEAL

SNYDER, District Judge.

I. INTRODUCTION

The present case is brought by the United States under the Clean Water Act, 33 U.S.C. § 1251 et seq. ("CWA"). The government filed its complaint on July 7, 2000, alleging that defendants Richard Adam, his sons Peter, Kieran and Dominic Adam, and the family's businesses, Adam Brothers Farming, Inc., and Iceberg Holdings, L.P., violated the CWA by draining, filling and grading wetlands and channelizing a creek on their property without a permit from the United States Army Corps of Engineers (the "Corps").

*1181 II. FACTUAL BACKGROUND

Defendants are the owners of land located near the community of Orcutt in Santa Barbara County, California (the "Site"). Orcutt Creek, which the parties variously describe as an intermittent stream, an ephemeral stream, and a flood channel, traverses the Site from east to west. In 1998 and 1999, defendants allegedly engaged in activities which altered the hydrology of the Site and had an adverse environmental impact on it. See December 8, 2003 Findings of Fact and Conclusions of Law ("Order") at 2. These activities allegedly included discharging dredge and fill materials into Orcutt Creek and wetlands adjacent to Orcutt Creek without a permit. Id.

According to the government, defendants were required to, but did not, obtain a permit from the Corps pursuant to section 404 of the CWA before discharging dredge and fill material into environmentally sensitive areas. Order at 2.

III. PROCEDURAL BACKGROUND

On July 7, 2000, the government commenced this action, alleging claims for unlawful discharge of dredged and fill material and failure to comply with a remediation order. Defendants filed a motion for summary judgment on December 19, 2001, on the ground that the Corps lacks regulatory jurisdiction pursuant to section 404 of the CWA over the Site. In an order dated July 12, 2002, the Court denied defendants' motion for summary judgment. The Court found that there was a genuine issue of material fact as to whether pumping water from the Orcutt Creek channel into a reservoir which sometimes flows onward to the Santa Maria River created a sufficient hydrological connection with waters of the United States to give rise to CWA jurisdiction.

The Court has trifurcated the issues to be tried in this case. The issue of whether regulatory jurisdiction exists under the CWA was tried to the Court on February 6, February 7, February 11, February 12, February 13, February 14, February 20, February 26, and February 27, 2003. Thirteen witnesses testified and 136 exhibits were admitted into evidence.

On December 8, 2003, the Court concluded that regulatory jurisdiction existed over the Site pursuant to 33 C.F.R. § 328.3(a)(5). In particular, the Court found that because water in Orcutt Creek flowed through a set of "gravity flow pipes" underneath a farm road and out of the Betteravia lakes area, a hydrological connection existed between the Site and the Pacific Ocean that was sufficient to give rise to CWA jurisdiction. Order at 7-14. The Court also found that even if water flowed out of Orcutt Creek only as a result of pumping, a hydrological connection would still exist, giving rise to regulatory jurisdiction over the Site. Order at 15-18. Finally, the Court concluded that to the extent that wetlands existed on the Site, such wetlands were "`wetlands adjacent' to `waters of the United States' pursuant to 33 C.F.R. § 328.3(a)(7)." Order at 21.

On May 21, 2004, defendants filed a motion to amend the December 8, 2003 Order to include certification for interlocutory appeal pursuant to 28 U.S.C. § 1292(b). In particular defendants seek certification of the following question of law for interlocutory appeal:

Is an isolated, non-navigable irrigation ditch that may indirectly and intermittently discharge into a `navigable water' only as a result of a man-made, mechanical pump and/or gravity flow pipes constructed, owned, and operated by unrelated third parties three miles away from Defendants' property a "tributary" *1182 of navigable waters subject to section 404(a) of the Clean Water Act, as interpreted by the Supreme Court in SWANCC and by this Circuit in Headwaters ?

IV. LEGAL STANDARD

28 U.S.C. § 1292(b) provides that:

When a district judge, in making in a civil action an order not otherwise appealable under this section, shall be of the opinion that such order involves a controlling question of law as to which there is substantial ground for difference of opinion and that an immediate appeal from the order may materially advance the ultimate termination of the litigation, [the judge] shall so state in writing in such order.

The purpose of an interlocutory appeal is to "facilitate disposition of the action by getting a final decision on a controlling legal issue sooner, rather than later" in order to "save the courts and the litigants unnecessary trouble and expense." John v. United States, 247 F.3d 1032, 1051 (9th Cir.2001)(en banc)(J. Rymer, special statement). However, "Section 1292(b) is a departure from the normal rule that only final judgments are appealable and therefore must be construed narrowly." Robin James v. Price Stern Sloan, Inc., 283 F.3d 1064, 1068 (9th Cir.2002). See also City of Hope Nat. Medical Center v. Blue Cross of California, 928 F.Supp. 1001, 1004 (C.D.Cal.1996)(J. Wardlaw)(finding that, in spite of a "small minority" of federal courts taking a contrary position, no "substantial ground for difference of opinion" existed regarding a controlling issue of law given the "virtual unanimity" among the various circuits and within the Ninth Circuit). Finally, even if a district court certifies an order for interlocutory appeal "the court of appeals nevertheless has discretion to reject the interlocutory appeal, and does so quite frequently." Robin James, 283 F.3d at 1068.

V. DISCUSSION

A. Does the Order Decide a Controlling Question of Law in this Action?

Defendants argue that the Court's December 8, 2003 Order decided a controlling question of law in this action.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
369 F. Supp. 2d 1180, 2004 WL 3332051, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-adam-bros-farming-inc-cacd-2004.