United States of America for the use and benefit of Lyndon Steel Co. v. E.W. Howell Co., LLC, et al.

District Court, E.D. New York·Decided July 20, 2026·No. 2:26-cv-00402·Unknown

Opinion

UNITED STATES DISTRICT COURT EASTERN DISTRICT OF NEW YORK

UNITED STATES OF AMERICA for the use and benefit of LYNDON STEEL CO.,

MEMORANDUM DECISION AND Plaintiff, ORDER

v. 26-cv-402 (BMC)

E.W. HOWELL CO., LLC, et al.,

Defendants.

COGAN, District Judge.

This is a dispute arising from a construction contract involving a U.S. Department of Energy (“DOE”) research lab known as Brookhaven National Laboratory (“BNL”) on Long Island. Defendant E.W. Howell (“Howell”) was the prime contractor for the project and plaintiff Lyndon Steel Co. (“Lyndon”) was a subcontractor. Lyndon completed the work but went unpaid to the tune of $1.5 million. Lyndon sued to recover payment for its services out of the bonds issued by defendants Pacific Indemnity Company and Liberty Mutual Insurance Company (the “Sureties”). Defendants have moved to dismiss the complaint for lack of subject matter jurisdiction or, alternatively, to enforce the subcontract’s forum-selection clause or dispute-resolution clause which acts as a condition precedent to suit. Lyndon sought leave to amend its complaint to add additional grounds for federal jurisdiction in the event that defendants’ prevailed on their primary argument. For the reasons below, the Court dismisses the case for lack of subject matter jurisdiction and denies Lyndon leave to amend as futile. BACKGROUND BNL is owned by the federal government but operated and managed by a private entity, Brookhaven Science Associates, LLC (“BSA”). BSA has a lengthy contract with the DOE that outlines BSA’s responsibilities to ensure that it, inter alia, “advances the mission goals of the DOE.” In sum and substance, BSA manages the property, personnel, and operations of BNL.

As part of its oversight of BNL, BSA entered into a $61.8 million contract with Howell for the construction of “a new administrative building at the main entrance to BNL” dubbed the “Construction of the Science and User Support Center” project. Several times, the contract documents expressly state: “This Contract does not bind nor purport to bind the Government of the United States.” The contract required Howell to post a performance bond and a payment bond, both valued at 100% of the contract price. Howell furnished the bonds to BSA via the Sureties and began construction. About a year into the project, Howell entered into a $5 million subcontract with Lyndon for 5,100 manhours of “structural and miscellaneous steel work.” The subcontract contained a choice-of-law and a forum-selection clause, stating, respectively, that the “validity,

interpretation, and performance of this Subcontract shall be governed by the laws of the State of New York,” and further requiring that any “action or proceeding arising out of, in connection with, or in relation to this Subcontract, shall be brought in the Supreme Court of the State of New York, County of Nassau.” The subcontract also contained a dispute-resolution clause, under which Howell and Lyndon “agree[d] they will attempt to resolve through direct negotiation and discussion any dispute, claim, or controversy,” including an agreement to “participate in mediation in good faith” and that the “non-binding mediation is a condition precedent to any other form of dispute resolution.” Lyndon worked on the project for the following three years. Lyndon contends that it performed its end of the bargain, but that Howell shorted Lyndon $1.56 million. After Lyndon’s demands for payment went unresolved, Lyndon turned to the courts. Lyndon first filed suit in Suffolk County Supreme Court, and that case was dismissed for violating both the forum-

selection and dispute-resolution clauses. See Lyndon Steel Co. v. E.W. Howell Co., LLC, Ind. No. 617490/2025 (Suffolk Cnty. Sup. Ct. Jan. 9, 2026). Lyndon shortly thereafter filed suit in Nassau County Supreme Court. See Lyndon Steel Co v. E.W. Howell Co., LLC, Ind. No. 601315/2026 (Nassau Cnty. Sup. Ct. Jan. 19, 2026). Lyndon, ostensibly trying to insulate itself from the Nassau case potentially being dismissed for violating the dispute-resolution clause, filed this case four days later. Lyndon invokes the Court’s federal question jurisdiction, see 28 U.S.C. § 1331, by asserting that this case arises under the Miller Act, 40 U.S.C. § 3131 et seq. The Miller Act provides for exclusive federal jurisdiction, thereby rendering the forum-selection clause unenforceable. See infra § I. Defendants have moved to dismiss the suit on three grounds: (1) the Court lacks subject

matter jurisdiction under the Miller Act; (2) the subcontract requires this case to be brought in another forum; and (3) Lyndon’s failure to mediate bars its initiation of a lawsuit. Lyndon, having identified additional grounds for federal subject matter jurisdiction, sought leave to amend its complaint in the event that defendants prevailed on their Miller Act argument. As discussed below, the Court lacks subject matter jurisdiction, and any amendment would be futile. DISCUSSION I. Miller Act Jurisdiction Unlike with private construction projects, the federal government’s “sovereign immunity bars creditors from enforcing liens on Government property.” Dep’t of the Army v. Blue Fox, 525 U.S. 255, 257 (1999). To protect federal subcontractors, the Miller Act requires the prime contractor performing “construction, alteration, or repair of any public building or public work of the Federal Government” to, inter alia, “furnish to the Government [a] payment bond for the protection of all persons supplying labor and material in carrying out the work,” when the value of the contract exceeds $100,000. 40 U.S.C. § 3131(b).

The Miller Act “gives the subcontractors and other suppliers ‘the right to sue on such payment bond for the amount, or the balance thereof, unpaid at the time of institution of such suit.’” Blue Fox, 525 U.S. at 257 (quotations omitted); see also U.S. ex rel. Sherman v. Carter, 353 U.S. 210, 216 (1957) (“The Miller Act represents a congressional effort to protect persons supplying labor and material for the construction of federal public buildings in lieu of the protection they might receive under state statutes with respect to the construction of nonfederal buildings.”). The Miller Act is a viable means for Lyndon to escape the subcontract’s forum-selection clause because it “vests exclusive jurisdiction over suits on Miller Act bonds in the federal courts.” U.S. ex. rel. Bryan Elec. Co. v. Aetna Cas. & Sur. Co., 297 F.2d 665, 667 (2d Cir.

Free access — add to your briefcase to read the full text and ask questions with AI

United States of America for the use and benefit of Lyndon Steel Co. v. E.W. Howell Co., LLC, et al., (E.D.N.Y. 2026).

United States of America for the use and benefit of Lyndon Steel Co. v. E.W. Howell Co., LLC, et al. (United States of America for the use and benefit of Lyndon Steel Co. v. E.W. Howell Co., LLC, et al.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Claflin v. Houseman
93 U.S. 130 (Supreme Court, 1876)
United States Ex Rel. Sherman v. Carter Constr. Co.
353 U.S. 210 (Supreme Court, 1957)
United States v. Orleans
425 U.S. 807 (Supreme Court, 1976)
Goodyear Atomic Corp. v. Miller
486 U.S. 174 (Supreme Court, 1988)
Department of the Army v. Blue Fox, Inc.
525 U.S. 255 (Supreme Court, 1999)
Walsh v. McGee
918 F. Supp. 107 (S.D. New York, 1996)
Ritchie v. Carvel Corp.
714 F. Supp. 700 (S.D. New York, 1989)
Diversified Carting, Inc. v. City of New York
423 F. Supp. 2d 85 (S.D. New York, 2005)