United States of America for The Use and Benefit of Facilities Mechanical Contractors, Inc. v. Heffler Contracting Group

CourtDistrict Court, S.D. California
DecidedJanuary 4, 2021
Docket3:20-cv-01414
StatusUnknown

This text of United States of America for The Use and Benefit of Facilities Mechanical Contractors, Inc. v. Heffler Contracting Group (United States of America for The Use and Benefit of Facilities Mechanical Contractors, Inc. v. Heffler Contracting Group) is published on Counsel Stack Legal Research, covering District Court, S.D. California primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States of America for The Use and Benefit of Facilities Mechanical Contractors, Inc. v. Heffler Contracting Group, (S.D. Cal. 2021).

Opinion

1 2 3 4 5 6 7 8 UNITED STATES DISTRICT COURT 9 SOUTHERN DISTRICT OF CALIFORNIA 10 11 UNITED STATES OF Case No.: 3:20-cv-01414-WQH-JLB AMERICA for the Use and 12 Benefit of FACILITIES ORDER 13 MECHANICAL CONTRACTORS, INC., a 14 California corporation, 15 Plaintiff, 16 v. 17 HEFFLER CONTRACTING 18 GROUP, a California corporation; NATIONWIDE MUTUAL 19 INSURANCE COMPANY, an Ohio corporation; and DOES 1 20 through 10, inclusive, 21 Defendants. 22 HAYES, Judge: 23 The matter pending before the Court is the Motion to Compel Arbitration and Stay 24 Proceedings filed by Defendants Heffler Contracting Group and Nationwide Mutual 25 Insurance Company. (ECF No. 8). 26

28 1 I. PROCEDURAL BACKGROUND 2 On July 23, 2020, Plaintiff United States of America for The Use and Benefit of 3 Facilities Mechanical Contractors, Inc. initiated this action by filing a Complaint against 4 Defendants Heffler Contracting Group (“Heffler”), Alliant Insurance Services, Inc., and 5 DOES 1 through 10, inclusive. (ECF No. 1). 6 On August 11, 2020, Plaintiff filed an Amended Complaint against Defendants 7 Heffler, Nationwide Mutual Insurance Company (“Nationwide”), and DOES 1 through 10, 8 inclusive. (ECF No. 4). Plaintiff alleges that the federal government named Defendant 9 Heffler as the general contractor for construction of an Emergency Service Center at Fort 10 Hunter Liggett, California. See id. at 2-3. Plaintiff alleges that Defendant “Heffler entered 11 into a written subcontract with [Plaintiff] as the third mechanical subcontractor” on June 12 20, 2019. Id. at 3. Plaintiff alleges that, “in performing its services, [it] was forced to 13 spend a tremendous and unanticipated overtime and incurred extra expenses . . . due to 14 [Defendant] Heffler’s mismanagement of its subcontractors, inability to provide a proper 15 schedule and failure to ensure coordination of the work and subcontractors . . . .” Id. at 3- 16 4. Plaintiff alleges that Defendant Heffler “refus[es] to compensate [Plaintiff] for the extra 17 time and expenses” and “continues to withhold at least $8,697.78 owed to” Plaintiff. Id. 18 at 4. Plaintiff brings the following four causes of action: (1) breach of contract, (2) quantum 19 meruit, (3) imposition of statutory penalties, and (4) recovery under Mill Act Payment 20 Bond. See id. at 5-9. Plaintiff seeks damages, statutory penalties, attorneys’ fees, costs, 21 pre and post-judgment interest, and “[s]uch other and further relief as the Court may deem 22 just and proper.” Id. at 9. 23 On October 9, 2020, Defendants Heffler and Nationwide (“Defendants”) filed a 24 Motion to Compel Arbitration and Stay Proceedings. (ECF No. 8). Defendants contend 25 that section 17(B)(1) of the subcontract between Plaintiff and Defendant Heffler requires 26 arbitration of Plaintiff’s claims because Plaintiff’s claims arise under or relate to the terms 27 and conditions of the subcontract and do not involve the acts or omission of the owner of 28 the project, the United States Army Corp of Engineers. On November 2, 2020, Plaintiff 1 filed a Response in opposition. (ECF No. 13). Plaintiff contends that section 17(B)(1) of 2 the subcontract between Plaintiff and Defendant Heffler does not require arbitration of 3 Plaintiff’s claims because Plaintiff’s claims involve the acts or omission of the United 4 States Army Corp of Engineers. On November 9, 2020, Defendants filed a Reply. (ECF 5 No. 14). 6 II. FACTS 7 Defendant “Heffler was the general contractor for construction of the federally 8 funded Emergency Services Center project [ ] located at Fort Hunter Liggett.” Castner 9 Decl. ¶ 2, ECF No. 8-3 at 2. Defendant “Heffler entered into a written subcontract with 10 [Plaintiff] pursuant to which [Plaintiff] agreed to perform mechanical and related work at 11 [Fort Hunter Liggett] in exchange for payment by [Defendant] Heffler . . . .” Id. ¶ 3, ECF 12 No. 8-3 at 2. “As part of the requirements of [Defendant] Heffler’s contract with the owner 13 [of] the [p]roject, [Defendant] Heffler was required to obtain a Miller Act payment bond 14 to provide security for unpaid labor and materials . . . .” Id. ¶ 5, ECF No. 8-3 at 2. 15 Section 17 of the subcontract between Plaintiff and Defendant Heffler addresses 16 dispute resolution procedure. See Ex. B to Amended Complaint, ECF No. 4-3 at 29-30; 17 Ex. 1 to Defendants’ Motion, ECF No. 8-1 at 40-41; Ex. 1 to Castner Decl., ECF No. 8-3 18 at 34-35. Section 17 states that 19 A. Preliminary Dispute Resolution Procedure and Agreement to Arbitrate 20

21 1) Disputes Under Prime Contract. Any dispute resolution procedure in the Prime Contract shall be deemed incorporated in 22 this Subcontract, and shall apply to any disputes arising 23 hereunder, except for disputes not involving the acts, omissions or otherwise the responsibility of the Owner under the Prime 24 Contract, and those which have been waived by the making or 25 acceptance of final payment. Subject to compliance with all applicable laws, including but not limited to those relating to 26 false claims, dispute and claim certifications, and cost and 27 pricing data requirements, Contractor’s sole obligation is to present any timely-filed claims by Subcontractor to Owner under 28 1 such procedure and, subject to the other provisions of this Subcontract, to pay to Subcontractor the proportionate part of 2 any sums paid by the Owner to which Subcontractor is entitled. 3 2) Settlement Negotiations. Subject to Prime Contract dispute 4 resolution procedures under Section 17.1.1, and as to disputes 5 not involving the acts, omissions or otherwise the responsibility of the Owner under the Prime Contract, promptly upon 6 notification by the Subcontractor of a dispute, the Contractor and 7 Subcontractor shall meet to informally resolve such dispute. If no resolution is achieved, the parties, prior to the initiation of any 8 action or proceeding under this Section, shall make a good faith 9 effort to resolve the dispute by negotiation between representatives with decision-making power, who, to the extent 10 possible, shall not have had substantive involvement in the 11 matters of the dispute, unless the parties otherwise agree. To facilitate the negotiation, the parties agree either to fashion a 12 procedure themselves or seek the assistance of a person or 13 organization experienced in alternative dispute resolution procedures, such as mediation or other similar procedures. 14

15 B. Arbitration Procedures. In the event the Prime Contract contains an 16 arbitration provision or for disputes not involving the acts, omissions or otherwise the responsibility of the Owner under the Prime Contract, 17 or allocation issues pertaining to Section 15.2(a) which were resolved 18 by the trier of fact in any underlying litigation or binding dispute resolution, the following shall apply: 19

20 1) Notice of Demand. For arbitration under the Prime Contract, notice of the demand for arbitration shall be filed in writing with 21 the other party to this Subcontract and shall conform to the 22 requirements of the arbitration provision set forth in the Prime Contract. For claims not involving the acts or omission or 23 otherwise the responsibility of the Owner under the Prime 24 Contract, the parties hereto shall submit all disputes arising under or relating to the terms and conditions of this Subcontract to 25 arbitration in accordance with the Construction Industry Rules of 26 the American Arbitration Association then in effect. In either case, the demand for arbitration shall be made within a 27 reasonable time after written notice of the claim, dispute or other 28 matter in question has been given, and in no event, shall it be 1 made after the date when institution of legal or equitable proceedings based on such claim dispute or other matter in 2 question would be barred by the applicable statute of limitations. 3 2) Award.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dean Witter Reynolds Inc. v. Byrd
470 U.S. 213 (Supreme Court, 1985)
Matthew Kilgore v. Keybank, National Association
718 F.3d 1052 (Ninth Circuit, 2013)
Perdue v. Crocker National Bank
702 P.2d 503 (California Supreme Court, 1985)
Shroyer v. New Cingular Wireless Services, Inc.
498 F.3d 976 (Ninth Circuit, 2007)
Roman v. Superior Court
172 Cal. App. 4th 1462 (California Court of Appeal, 2009)
Armendariz v. Found. Health Psychcare Servs., Inc.
6 P.3d 669 (California Supreme Court, 2000)
Sanchez v. Valencia Holding Co.
353 P.3d 741 (California Supreme Court, 2015)
Norcia v. Samsung Telecommunications America, LLC
845 F.3d 1279 (Ninth Circuit, 2017)
Samaniego v. Empire Today, LLC
205 Cal. App. 4th 1138 (California Court of Appeal, 2012)
Jacobs v. Regents of the Univ. of Cal.
219 Cal. Rptr. 3d 838 (California Court of Appeals, 5th District, 2017)
Net Global Marketing, Inc. v. Dialtone, Inc.
217 F. App'x 598 (Ninth Circuit, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
United States of America for The Use and Benefit of Facilities Mechanical Contractors, Inc. v. Heffler Contracting Group, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-of-america-for-the-use-and-benefit-of-facilities-mechanical-casd-2021.