United States of America for The Use and Benefit of Facilities Mechanical Contractors, Inc. v. Heffler Contracting Group

District Court, S.D. California·Decided January 4, 2021·No. 3:20-cv-01414·Unknown

Opinion

UNITED STATES OF Case No.: 3:20-cv-01414-WQH-JLB AMERICA for the Use and Benefit of FACILITIES ORDER CONTRACTORS, INC., a California corporation, Plaintiff, v. GROUP, a California corporation; NATIONWIDE MUTUAL INSURANCE COMPANY, an Ohio corporation; and DOES 1 through 10, inclusive, Defendants. HAYES, Judge: The matter pending before the Court is the Motion to Compel Arbitration and Stay Proceedings filed by Defendants Heffler Contracting Group and Nationwide Mutual Insurance Company. (ECF No. 8).

On July 23, 2020, Plaintiff United States of America for The Use and Benefit of Facilities Mechanical Contractors, Inc. initiated this action by filing a Complaint against Defendants Heffler Contracting Group (“Heffler”), Alliant Insurance Services, Inc., and DOES 1 through 10, inclusive. (ECF No. 1). On August 11, 2020, Plaintiff filed an Amended Complaint against Defendants Heffler, Nationwide Mutual Insurance Company (“Nationwide”), and DOES 1 through 10, inclusive. (ECF No. 4). Plaintiff alleges that the federal government named Defendant Heffler as the general contractor for construction of an Emergency Service Center at Fort Hunter Liggett, California. See id. at 2-3. Plaintiff alleges that Defendant “Heffler entered into a written subcontract with [Plaintiff] as the third mechanical subcontractor” on June 20, 2019. Id. at 3. Plaintiff alleges that, “in performing its services, [it] was forced to spend a tremendous and unanticipated overtime and incurred extra expenses . . . due to [Defendant] Heffler’s mismanagement of its subcontractors, inability to provide a proper schedule and failure to ensure coordination of the work and subcontractors . . . .” Id. at 3- 4. Plaintiff alleges that Defendant Heffler “refus[es] to compensate [Plaintiff] for the extra time and expenses” and “continues to withhold at least $8,697.78 owed to” Plaintiff. Id. at 4. Plaintiff brings the following four causes of action: (1) breach of contract, (2) quantum meruit, (3) imposition of statutory penalties, and (4) recovery under Mill Act Payment Bond. See id. at 5-9. Plaintiff seeks damages, statutory penalties, attorneys’ fees, costs, pre and post-judgment interest, and “[s]uch other and further relief as the Court may deem just and proper.” Id. at 9. On October 9, 2020, Defendants Heffler and Nationwide (“Defendants”) filed a Motion to Compel Arbitration and Stay Proceedings. (ECF No. 8). Defendants contend that section 17(B)(1) of the subcontract between Plaintiff and Defendant Heffler requires arbitration of Plaintiff’s claims because Plaintiff’s claims arise under or relate to the terms and conditions of the subcontract and do not involve the acts or omission of the owner of the project, the United States Army Corp of Engineers. On November 2, 2020, Plaintiff filed a Response in opposition. (ECF No. 13). Plaintiff contends that section 17(B)(1) of the subcontract between Plaintiff and Defendant Heffler does not require arbitration of Plaintiff’s claims because Plaintiff’s claims involve the acts or omission of the United States Army Corp of Engineers. On November 9, 2020, Defendants filed a Reply. (ECF No. 14). Defendant “Heffler was the general contractor for construction of the federally funded Emergency Services Center project [ ] located at Fort Hunter Liggett.” Castner Decl. ¶ 2, ECF No. 8-3 at 2. Defendant “Heffler entered into a written subcontract with [Plaintiff] pursuant to which [Plaintiff] agreed to perform mechanical and related work at [Fort Hunter Liggett] in exchange for payment by [Defendant] Heffler . . . .” Id. ¶ 3, ECF No. 8-3 at 2. “As part of the requirements of [Defendant] Heffler’s contract with the owner [of] the [p]roject, [Defendant] Heffler was required to obtain a Miller Act payment bond to provide security for unpaid labor and materials . . . .” Id. ¶ 5, ECF No. 8-3 at 2. Section 17 of the subcontract between Plaintiff and Defendant Heffler addresses dispute resolution procedure. See Ex. B to Amended Complaint, ECF No. 4-3 at 29-30; Ex. 1 to Defendants’ Motion, ECF No. 8-1 at 40-41; Ex. 1 to Castner Decl., ECF No. 8-3 at 34-35. Section 17 states that A. Preliminary Dispute Resolution Procedure and Agreement to Arbitrate

1) Disputes Under Prime Contract. Any dispute resolution procedure in the Prime Contract shall be deemed incorporated in this Subcontract, and shall apply to any disputes arising hereunder, except for disputes not involving the acts, omissions or otherwise the responsibility of the Owner under the Prime Contract, and those which have been waived by the making or acceptance of final payment. Subject to compliance with all applicable laws, including but not limited to those relating to false claims, dispute and claim certifications, and cost and pricing data requirements, Contractor’s sole obligation is to present any timely-filed claims by Subcontractor to Owner under such procedure and, subject to the other provisions of this Subcontract, to pay to Subcontractor the proportionate part of any sums paid by the Owner to which Subcontractor is entitled. 2) Settlement Negotiations. Subject to Prime Contract dispute resolution procedures under Section 17.1.1, and as to disputes not involving the acts, omissions or otherwise the responsibility of the Owner under the Prime Contract, promptly upon notification by the Subcontractor of a dispute, the Contractor and Subcontractor shall meet to informally resolve such dispute. If no resolution is achieved, the parties, prior to the initiation of any action or proceeding under this Section, shall make a good faith effort to resolve the dispute by negotiation between representatives with decision-making power, who, to the extent possible, shall not have had substantive involvement in the matters of the dispute, unless the parties otherwise agree. To facilitate the negotiation, the parties agree either to fashion a procedure themselves or seek the assistance of a person or organization experienced in alternative dispute resolution procedures, such as mediation or other similar procedures.

B. Arbitration Procedures. In the event the Prime Contract contains an arbitration provision or for disputes not involving the acts, omissions or otherwise the responsibility of the Owner under the Prime Contract, or allocation issues pertaining to Section 15.2(a) which were resolved by the trier of fact in any underlying litigation or binding dispute resolution, the following shall apply:

1) Notice of Demand. For arbitration under the Prime Contract, notice of the demand for arbitration shall be filed in writing with the other party to this Subcontract and shall conform to the requirements of the arbitration provision set forth in the Prime Contract. For claims not involving the acts or omission or otherwise the responsibility of the Owner under the Prime Contract, the parties hereto shall submit all disputes arising under or relating to the terms and conditions of this Subcontract to arbitration in accordance with the Construction Industry Rules of the American Arbitration Association then in effect. In either case, the demand for arbitration shall be made within a reasonable time after written notice of the claim, dispute or other matter in question has been given, and in no event, shall it be made after the date when institution of legal or equitable proceedings based on such claim dispute or other matter in question would be barred by the applicable statute of limitations. 2) Award. The award rendered by the arbitrator(s) shall be final and judgment may be entered upon it in accordance with applicable law in any court having jurisdiction.

3) Work Continuation and Payment. Unless otherwise agreed in writing, Subcontractor shall carry on the work and maintain the Contractor’s schedule pending arbitration, and if so, Contractor shall continue to make payments in accordance with this Subcontract.

Free access — add to your briefcase to read the full text and ask questions with AI

United States of America for The Use and Benefit of Facilities Mechanical Contractors, Inc. v. Heffler Contracting Group, (S.D. Cal. 2021).

United States of America for The Use and Benefit of Facilities Mechanical Contractors, Inc. v. Heffler Contracting Group (United States of America for The Use and Benefit of Facilities Mechanical Contractors, Inc. v. Heffler Contracting Group) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Dean Witter Reynolds Inc. v. Byrd
470 U.S. 213 (Supreme Court, 1985)
Matthew Kilgore v. Keybank, National Association
718 F.3d 1052 (Ninth Circuit, 2013)
Perdue v. Crocker National Bank
702 P.2d 503 (California Supreme Court, 1985)
Shroyer v. New Cingular Wireless Services, Inc.
498 F.3d 976 (Ninth Circuit, 2007)
Roman v. Superior Court
172 Cal. App. 4th 1462 (California Court of Appeal, 2009)
Armendariz v. Found. Health Psychcare Servs., Inc.
6 P.3d 669 (California Supreme Court, 2000)
Sanchez v. Valencia Holding Co.
353 P.3d 741 (California Supreme Court, 2015)
Norcia v. Samsung Telecommunications America, LLC
845 F.3d 1279 (Ninth Circuit, 2017)
Samaniego v. Empire Today, LLC
205 Cal. App. 4th 1138 (California Court of Appeal, 2012)
Jacobs v. Regents of the Univ. of Cal.
219 Cal. Rptr. 3d 838 (California Court of Appeals, 5th District, 2017)
Net Global Marketing, Inc. v. Dialtone, Inc.
217 F. App'x 598 (Ninth Circuit, 2007)