United States of America for the use and benefit of American General Construction Inc. v. Yack Construction, Inc.

CourtDistrict Court, D. Nevada
DecidedSeptember 25, 2019
Docket2:17-cv-01994
StatusUnknown

This text of United States of America for the use and benefit of American General Construction Inc. v. Yack Construction, Inc. (United States of America for the use and benefit of American General Construction Inc. v. Yack Construction, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Nevada primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States of America for the use and benefit of American General Construction Inc. v. Yack Construction, Inc., (D. Nev. 2019).

Opinion

2 DISTRICT OF NEVADA

3 * * *

4 UNITED STATES OF AMERICA FOR Case No. 2:17-cv-01994-MMD-CWH THE USE AND BENEFIT OF AMERICAN 5 GENERAL CONSTRUCTION, INC., and ORDER AMERICAN GENERAL 6 CONSTRUCTION, INC. d/b/a AGC, INC.,

7 Plaintiffs, v. 8 YACK CONSTRUCTION, INC., 9 MERCHANTS BONDING COMPANY (MUTUAL), and PAE APPLIED 10 TECHNOLOGIES, LLC,

11 Defendants.

12 13 I. SUMMARY 14 This is a contractual dispute between construction companies. Defendant Yack 15 Construction, Inc. (“Yack”) was hired to construct a hangar at Creech Air Force Base (“the 16 Project”) and subcontracted with Plaintiff American General Construction, Inc. (“AGC”) to 17 carry out a portion of the Project. AGC completed part of its work, but then its relationship 18 with Yack deteriorated. Yack terminated AGC and hired one of AGC’s former 19 subcontractors to complete the work. Yack has refused to pay AGC, contending that AGC 20 violated the contractual agreement that governed their relationship. 21 The following motions are pending before the Court: (1) Defendants Yack and 22 Merchants Bonding Company (Mutual)’s (“Merchants”) motion for summary judgment 23 (ECF No. 47) and (2) Plaintiffs United States of America for the Use and Benefit of 24 American General Construction, Inc. and AGC’s motion for partial summary judgment 25 (ECF No. 48). The Court has reviewed the parties’ responses (ECF Nos. 51, 52) and 26 replies (ECF Nos. 53, 54). The Court also held a hearing on the pending motions on 27 September 24, 2019 (“the Hearing”). (ECF No. 59.) For the following reasons, the Court 28 denies the parties’ motions. 2 The following facts are undisputed unless otherwise indicated. 3 The United States Air Force entered into a Range Support Services Agreement 4 with PAE Applied Technologies, LLC (“PAE”) in 2002. (ECF No. 52-4 at 2.) Under that 5 agreement, PAE “provides a broad array of services to the Government at multiple 6 locations on the Nevada Test and Training Range . . . [including] Creech Air Force Base.” 7 (Id.) One of the services PAE provided was overseeing the construction of the Project. (Id. 8 at 3.) 9 PAE solicited proposals for the Project on October 6, 2016. (Id.) The request for 10 proposals “expressly required bidders to obtain a Performance and Payment bond, as 11 required under the Miller Act.” (Id.) PAE entered into an agreement with Yack on January 12 30, 2017 that made Yack primarily responsible for the Project and required Yack to obtain 13 the bond required under the Miller Act.1 (Id.) Yack obtained a bond in the amount of 14 $3,168,122 from Merchants on April 5, 2017. (Id.) 15 AGC submitted a proposal (“Proposal”) on December 22, 2016 to Yack to carry out 16 certain aspects of the Project. (See ECF No. 48-1 at 1.) The Proposal contains pricing for 17 a regular schedule, accelerated schedule, payment terms, and exclusions. (See id. at 2- 18 5.) Yack’s agent signed the Proposal on January 6, 2017, agreeing to the regular schedule 19 pricing and the following payment term: “Balance upon invoicing. Net 30 days.” (Id. at 4.) 20 The Proposal also bears the signature of AGC’s agent. (See id. at 5.) The Proposal 21 references additional forthcoming agreements between the parties, indicating that it “will 22 need to be added . . . to any Ownership Contract Agreements.” (Id. at 1.) 23 AGC contacted Yack on January 25, 2017 to ask whether a draft subcontract 24 agreement was ready for review. (ECF No. 48-4 at 2.) Yack instructed AGC two days later 25 to proceed with the work under the Proposal even though the subcontract agreement was 26 /// 27 1Yack disputes that the bond is a Miller Act bond. (See, e.g., ECF No. 47 at 2.) 28 2 commenced work on the Project sometime after that.2 (ECF No. 52 at 4-5; see also ECF 3 No. 52-5 at 6-7 (email dated January 27, 2017 stating: “Rodney, we will have the door 4 loads need [sic] in order to continue with the foundation work later today.”).) 5 Yack provided a draft subcontract agreement (“Subcontract Agreement”) to AGC 6 on February 13, 2017. (ECF No. 52-11.) The Subcontract Agreement stated that upon 7 receipt of a copy for signature, if AGC “commences work on the site prior to signing,” such 8 commencement would be “deemed to be acceptance” of the Subcontract Agreement. (Id. 9 at 4 (Section 2.1).) AGC returned the Subcontract Agreement to Yack with numerous 10 changes. (See ECF No. 52-12 (draft with notations); ECF No. 52-13 (email 11 correspondence regarding changes to the Subcontract Agreement); ECF No. 52-10 at 20- 12 21 (describing redline edits).) Yack did not agree to all changes, and AGC refused to sign. 13 (ECF No. 52-13 (email exchange in which Yack refused to change the Subcontract 14 Agreement); ECF No. 52-10 at 20-21 (deposition testimony of AGC’s agent that “we never 15 came to terms”).) In fact, AGC never signed the Subcontract agreement. (ECF No. 52-10 16 at 20-21; see also ECF No. 52-14 at 3 (email from AGC’s agent stating that “[t]hese are 17 ‘Agreements’ not ‘take it or leave it’ documents”).) 18 AGC entered into a subcontract agreement with Central Concrete Company of Ohio 19 (“CCCO”) on February 14, 2017 for CCCO to perform certain work on the Project. (See 20 ECF No. 52-18.) AGC contends that certain failures on the part of Yack delayed this work: 21 [T]he presence of a hole near the pad where AGC’s Scope of Work was to be performed, Yack’s failure to ensure a complete pad was poured prior to 22 AGC’s arrival, Yack’s failure to clear the site of dirt piles or to pour the concrete so that AGC and CCCO could proceed in a prompt manner, Yack’s 23 refusal to approve necessary change orders, and Yack’s failure to create a master schedule to the Project. 24 25 /// 26 /// 27 2At the Hearing, Yack’s counsel made a distinction between work in preparation for the construction and actual mobilization of manpower on site. She asserts that while AGC 28 performed design work in preparation, AGC did not commence work until February 14, 2017. 2 6).) 3 Yack’s representatives complained about CCCO’s efforts in March 2017 and began 4 to encourage AGC to terminate CCCO. (ECF No. 52 at 8; see also, e.g., ECF No. 52-19 5 at 4 (“CCC did not show . . . . AGC needs to get control of their subcontractor[‘]s actions.”), 6 5 (“CCC is still a problem for AGC.”), 6 (“CCC’s performance is lacking and the crew 7 doesn’t seem motivated.”); ECF No. 52-10 at 29-31.) AGC ultimately provided CCCO with 8 a notice of termination on April 4, 2017. (ECF No. 52-25 at 2.) CCCO refused to return to 9 the Project site on April 17, 2017, and Yack notified AGC that AGC would be terminated 10 for failure to provide sufficient manpower at the Project site unless AGC provided sufficient 11 manpower within 48 hours. (See ECF No. 52-28 at 4.) Yack terminated AGC on April 20, 12 2017. (ECF No. 52-33 at 2-3.) 13 AGC asserts the following claims against Yack in the First Amended Complaint 14 (“FAC”): (1) breach of contract; (2) breach of the implied covenant of good faith and fair 15 dealing; (3) quantum meruit; (4) unjust enrichment; (5) civil conspiracy; and (6) recovery 16 from the Yack Bond. (ECF No. 14 at 13-19.) In the prayer for relief, AGC requests payment 17 for the amount of the labor, materials, and services furnished to the Project as well as 18 money damages, fees, and costs. (Id. at 20.) 19 III. LEGAL STANDARD 20 “The purpose of summary judgment is to avoid unnecessary trials when there is no 21 dispute as to the facts before the court.” Nw. Motorcycle Ass’n v. U.S. Dep’t of Agric., 18 22 F.3d 1468, 1471 (9th Cir. 1994). Summary judgment is appropriate when the pleadings, 23 the discovery and disclosure materials on file, and any affidavits “show there is no genuine 24 issue as to any material fact and that the movant is entitled to judgment as a matter of 25 law.” Celotex Corp. v. Catrett, 477 U.S. 317

Free access — add to your briefcase to read the full text and ask questions with AI

Related

First Nat. Bank of Ariz. v. Cities Service Co.
391 U.S. 253 (Supreme Court, 1968)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Robin Orr v. Bank of America, Nt & Sa
285 F.3d 764 (Ninth Circuit, 2002)
Roth v. Scott
921 P.2d 1262 (Nevada Supreme Court, 1996)
Bernard v. Rockhill Development Co.
734 P.2d 1238 (Nevada Supreme Court, 1987)
Consolidated Generator-Nevada, Inc. v. Cummins Engine Co.
971 P.2d 1251 (Nevada Supreme Court, 1998)
May v. Anderson
119 P.3d 1254 (Nevada Supreme Court, 2005)
Arno v. Club Med Inc.
22 F.3d 1464 (Ninth Circuit, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
United States of America for the use and benefit of American General Construction Inc. v. Yack Construction, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-of-america-for-the-use-and-benefit-of-american-general-nvd-2019.