United States Fidelity & Guaranty Co. v. Bangor Area Joint School Authority

355 F. Supp. 913, 1973 U.S. Dist. LEXIS 14638
CourtDistrict Court, E.D. Pennsylvania
DecidedMarch 7, 1973
DocketCiv. A. 72-764
StatusPublished
Cited by8 cases

This text of 355 F. Supp. 913 (United States Fidelity & Guaranty Co. v. Bangor Area Joint School Authority) is published on Counsel Stack Legal Research, covering District Court, E.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Fidelity & Guaranty Co. v. Bangor Area Joint School Authority, 355 F. Supp. 913, 1973 U.S. Dist. LEXIS 14638 (E.D. Pa. 1973).

Opinion

MEMORANDUM AND ORDER

TROUTMAN, District Judge.

On January 29, 1968, Fraim Construction Company entered into a contract with defendant school authority for the construction of a new junior high school in Bangor, Pennsylvania, for the sum of $2,058,839.68. On or about the same date, plaintiff [U.S.F.&G.], as surety, and Fraim, as principal, executed and delivered performance and labor and material payment bonds in connection with the construction project with defendant school authority as obligee. In February 1971, Fraim defaulted and purportedly assigned all his rights under the con *914 struction contract to U.S.F.&G. At defendant’s request, U.S.F.&G. completed the construction contract at a cost to it in excess of $240,000. Prior to Fraim’s default, the total contract price, except for $41,092.25, had been paid to Fraim. In October 1971, upon U.S.F.&G.’s completion of the construction contract, it made application to the defendant for the payment of the contract balance, i. e., $41,092.25. Upon defendant’s refusal to tender the balance, U.S.F.&G., as subrogated surety, commenced this action to recover the contract balance. Jurisdiction is based solely on diversity of citizenship and an amount in controversy in excess of $10,000. 28 U.S.C. § 1332. Before the Court is defendant’s motion to dismiss or, in the alternative, to stay the action pending arbitration.

The contract entered into between Fraim, U.S.F.&G.’s principal, and defendant provides in Section 7.10.1 of the Supplementary General Conditions thereof for the resolution of all disputes, with certain exceptions not pertinent here “ * * * by arbitration in accordance with the Construction Industry Arbitration [rules] * * 1 The contract further chooses Pennsylvania law as the governing law [Section 7.1.1] and provides that the contract shall be binding on successors and assigns. [Section 7.2.1] 2 Thus, the terms of the contract are completely binding on U.S.F. &G. and Pennsylvania law governs the construction of the contract. It should also be noted at this time that Section 16 of the Pennsylvania Arbitration Act, 5 P.S. § 176 3 makes the application of the state act, 5 P.S. § 161 et seq., mandatory in all written contracts to which the Commonwealth or any of its political subdivisions is a party. See Merritt-Chapman & Scott Corp. v. Pennsylvania Turnpike Comm’n., 387 F.2d 768, 773 (3rd Cir. 1967). Thus, even if the instant contract had not chosen Pennsyl *915 vania law as governing and provided for arbitration of disputes, the provisions of the Pennsylvania Arbitration Act would nonetheless be applicable by operation of law by virtue of 5 P.S. § 176.

I.

Initially, plaintiff contends that its claims are not within the scope of the arbitration provision. In Hussey Metals v. Lectromelt Furnace, 471 F.2d 556 (3rd Cir. 1972) the Court of Appeals restated the guidelines to be followed by the Courts in determining this issue:

“It is settled under both Federal and Pennsylvania law that the court must decide whether a party is bound to arbitrate and what issues he must arbitrate. Arbitration is a matter of contract, and a party cannot be forced to arbitrate something which he did not agree to. [citations omitted]
“In view of the favorable policy towards arbitration, Mendelson v. Shrager, 432 Pa. 383, 248 A.2d 234 (1968), doubts as to whether an arbitration clause may be interpreted to cover the asserted dispute should be resolved in favor of arbitration unless a court can state with ‘positive assurance’ that this dispute was not meant to be arbitrated. See United Steelworkers of America v. Warrior & Gulf Navigation Co., 363 U.S. 574, 582-583, 80 S.Ct. 1347, 4 L.Ed.2d 1409.”

U.S.F.&G. contends, relying on Hussey Metals, that this dispute is not arbitrable because the contract provides that work shall remain in progress during any arbitration proceeding. 4 It argues that since the work has been completed the above provision renders the arbitration clause inapplicable. In Hussey Metals, the contract contained a similar provision and, in addition, a clause providing that, in no case, shall a demand for arbitration be made later than the time for final payment. In holding that the dispute involved was not arbitrable, the Court reasoned that because of these two clauses, arbitration was required only when work was in progress. 5 It would be difficult to rationalize their inclusion, the Court continued, if there was no work which could have been stopped. In the instant case, the contract includes only the “work stoppage” clause and omits the “no demand” clause. It is the latter clause, omitted in this ease, which clearly ’evinces an intent that there be no arbitration following the completion of the work. The absence of a “no demand” clause is significant, for we see nothing in a “work stoppage” clause, standing alone, which is inconsistent with the intention that the arbitration clause remain viable after completion of the work. This arbitration clause is broad and comprehensive. Thus resolving any doubts in favor of arbitration, we conclude that the present dispute falls within the purview of the arbitration clause.

II.

Defendant argues that since this Court’s jurisdiction is based solely on diversity of citizenship, this Court clearly has the inherent power to stay the action pending arbitration. Defendant urges that we exercise our power for two reasons: (1) because of the size of this contract, it probably involves interstate commerce, thereby rendering the federal arbitration act, 9 U.S.C. § 1 et seq., applicable. Under Section 3 of that act, the Court would be statutorily required to stay proceedings pending arbitration, and (2) because this is a diversity case and the policy of Erie R. Co. v. Tompkins, 304 U.S. 64, 58 S.Ct. *916 817, 82 L.Ed. 1188 (1938) would be effectuated by a stay.

A.

Under the federal arbitration act, an arbitration provision in any maritime transaction or a contract evidencing a transaction involving commerce is valid, irrevocable, and enforceable. 9 U.S.C. § 2. 6

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Delta Funding Corp.
316 F. Supp. 2d 554 (N.D. Ohio, 2004)
Cecala v. Moore
982 F. Supp. 609 (N.D. Illinois, 1997)
STATE OF ILL. EX REL. SKINNER v. Lombard Co.
436 N.E.2d 566 (Appellate Court of Illinois, 1982)
Romnes v. Bache & Co., Inc.
439 F. Supp. 833 (W.D. Wisconsin, 1977)
Vespe Contracting Co. v. Anvan Corporation
399 F. Supp. 516 (E.D. Pennsylvania, 1975)
Litton RCS, Inc. v. Pennsylvania Turnpike Commission
376 F. Supp. 579 (E.D. Pennsylvania, 1974)
Ice City, Inc. v. Insurance Co. of North America
314 A.2d 236 (Supreme Court of Pennsylvania, 1974)
W. V. Pangborne & Co. v. Wark & Co.
64 Pa. D. & C.2d 109 (Philadelphia County Court of Common Pleas, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
355 F. Supp. 913, 1973 U.S. Dist. LEXIS 14638, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-fidelity-guaranty-co-v-bangor-area-joint-school-authority-paed-1973.